- Utility work started in advance of construction.
- Tree removal started October 27th.
- Temporary speed cushions have been installed in the neighborhoods to the east and west of Linder Road.
- Linder Road will be closed November 18th thru mid-March 2026.
- Bridge removal ongoing.
- Utility work started in advance of construction.
- Tree removal started October 27th.
- Temporary speed cushions have been installed in the neighborhoods to the east and west of Linder Road.
- Linder Road will be closed November 18th thru mid-March 2026.
- Bridge removal ongoing.
Share November 14, 2025 on Facebook
Share November 14, 2025 on X (formerly Twitter)
Share November 14, 2025 on Linkedin
Email November 14, 2025 link
- Tree removal started October 27th.
- Traffic calming measures will be implemented in the neighborhoods to the east and west of Linder Road starting November 3rd, ongoing.
- Linder Road will be closed beginning November 18th for bridge construction.
- Tree removal started October 27th.
- Traffic calming measures will be implemented in the neighborhoods to the east and west of Linder Road starting November 3rd, ongoing.
- Linder Road will be closed beginning November 18th for bridge construction.
Share Detour Map - Closure November 18th on Facebook
Share Detour Map - Closure November 18th on X (formerly Twitter)
Share Detour Map - Closure November 18th on Linkedin
Email Detour Map - Closure November 18th link
Share November 7, 2025 on Facebook
Share November 7, 2025 on X (formerly Twitter)
Share November 7, 2025 on Linkedin
Email November 7, 2025 link
- Utility work is starting in advance of construction.
- Tree removal started October 27th.
- Traffic calming measures will be implemented in the neighborhoods to the east and west of Linder Road starting November 3rd, ongoing.
- Linder Road will be closed beginning November 18th for bridge construction.
- Utility work is starting in advance of construction.
- Tree removal started October 27th.
- Traffic calming measures will be implemented in the neighborhoods to the east and west of Linder Road starting November 3rd, ongoing.
- Linder Road will be closed beginning November 18th for bridge construction.
Share October 31, 2025 on Facebook
Share October 31, 2025 on X (formerly Twitter)
Share October 31, 2025 on Linkedin
Email October 31, 2025 link
- Utility work is starting in advance of construction.
- Tree removal started October 27th. Traffic calming measures will be implemented in the neighborhoods to the east and west of Linder Road starting November 3rd.
- Utility work is starting in advance of construction.
- Tree removal started October 27th. Traffic calming measures will be implemented in the neighborhoods to the east and west of Linder Road starting November 3rd.
Share October 24, 2025 on Facebook
Share October 24, 2025 on X (formerly Twitter)
Share October 24, 2025 on Linkedin
Email October 24, 2025 link
- Notice to Proceed is anticipated for November 13th.
- Utility work is starting in advance of construction.
- Notice to Proceed is anticipated for November 13th.
- Utility work is starting in advance of construction.
Share October 17, 2025 on Facebook
Share October 17, 2025 on X (formerly Twitter)
Share October 17, 2025 on Linkedin
Email October 17, 2025 link
Utility work is starting in advance of construction.
Utility work is starting in advance of construction.
Share Construction Public Meeting - November 6th on Facebook
Share Construction Public Meeting - November 6th on X (formerly Twitter)
Share Construction Public Meeting - November 6th on Linkedin
Email Construction Public Meeting - November 6th link
Please join ACHD Staff and the Contractor for a Construction Public Meeting to learn more about the Linder Road, State Highway 44, to Floating Feather Road Construction Project. Construction is expected to begin mid November.
Construction Public Meeting
Thursday, November 6th
-
6:30 to 8:30 pm | Presentations will begin at 6:30 pm and 7:30 pm
Galileo STEM Academy | 4735 W. Saguaro Dr., Eagle
Please join ACHD Staff and the Contractor for a Construction Public Meeting to learn more about the Linder Road, State Highway 44, to Floating Feather Road Construction Project. Construction is expected to begin mid November.
Construction Public Meeting
Thursday, November 6th
-
6:30 to 8:30 pm | Presentations will begin at 6:30 pm and 7:30 pm
Galileo STEM Academy | 4735 W. Saguaro Dr., Eagle
Share September 11, 2025 on Facebook
Share September 11, 2025 on X (formerly Twitter)
Share September 11, 2025 on Linkedin
Email September 11, 2025 link
Notice to proceed date for this project has been updated to middle of November.
Notice to proceed date for this project has been updated to middle of November.
Share April 23, 2025 on Facebook
Share April 23, 2025 on X (formerly Twitter)
Share April 23, 2025 on Linkedin
Email April 23, 2025 link
- Construction to start mid to late October 2025 due to the irrigation crossings.
- Irrigation crossings will need to be constructed while irrigation water is off.
- Additional information will be provided once a traffic control plan is developed.
- Construction to start mid to late October 2025 due to the irrigation crossings.
- Irrigation crossings will need to be constructed while irrigation water is off.
- Additional information will be provided once a traffic control plan is developed.