Palmer Lane Bridge

Share Palmer Lane Bridge on Facebook Share Palmer Lane Bridge on Twitter Share Palmer Lane Bridge on Linkedin Email Palmer Lane Bridge link

This project is substantially complete

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Palmer Lane north of Floating Feather Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Foothill Ditch.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Palmer Lane north of Floating Feather Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Foothill Ditch.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

This project is substantially complete

  • May 10, 2024

    10 May 2024
    Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link

    Project substantially complete

  • May 3, 2024

    03 May 2024
    Share May 3, 2024 on Facebook Share May 3, 2024 on Twitter Share May 3, 2024 on Linkedin Email May 3, 2024 link
    • Road grading complete.
    • Paving is scheduled for May 2nd.
  • April 25, 2024

    25 Apr 2024
    Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link
    • Road grading has started.
    • Paving is scheduled for next week.
  • April 19, 2024

    19 Apr 2024
    Share April 19, 2024 on Facebook Share April 19, 2024 on Twitter Share April 19, 2024 on Linkedin Email April 19, 2024 link
    • Walls are backfilled.
    • Prep for road base has started.
    • Road grading has started.
  • April 12, 2024

    12 Apr 2024
    Share April 12, 2024 on Facebook Share April 12, 2024 on Twitter Share April 12, 2024 on Linkedin Email April 12, 2024 link
    • Walls are backfilled.
    • Prep for road base has started.
  • April 5, 2024

    05 Apr 2024
    Share April 5, 2024 on Facebook Share April 5, 2024 on Twitter Share April 5, 2024 on Linkedin Email April 5, 2024 link
    • Walls are backfilled.
    • Prep for road base has started.
  • March 29, 2024

    29 Mar 2024
    Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link
    • Walls are expected to be backfilled next week.
    • Prep for road base is expected to start late this week or early next week.
  • March 21, 2024

    21 Mar 2024
    Share March 21, 2024 on Facebook Share March 21, 2024 on Twitter Share March 21, 2024 on Linkedin Email March 21, 2024 link
    • Waterproofing complete on box sections.
    • Contractor has placed the walls and aprons.
    • Walls are expected to be backfilled next week.
  • March 15, 2024

    15 Mar 2024
    Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link
    • All sections have been set, welded and grouted.
    • Contractor waiting on weather to waterproof box.
    • Contractor has placed the walls.
  • March 8, 2024

    08 Mar 2024
    Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link
    • All sections have been set, welded and grouted.
    • Contractor waiting on weather to waterproof box.
    • Contractor plans to place the walls this week pending weather.