Palmer Lane Bridge

Share Palmer Lane Bridge on Facebook Share Palmer Lane Bridge on Twitter Share Palmer Lane Bridge on Linkedin Email Palmer Lane Bridge link

This project is substantially complete

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Palmer Lane north of Floating Feather Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Foothill Ditch.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Palmer Lane north of Floating Feather Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Foothill Ditch.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

This project is substantially complete

  • March 1, 2024

    Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link
    • Excavation complete.
    • Footings placed.
    • Precast sections have been delivered. All sections have been set, welded and grouted.
    • Contractor plans to place the walls next week.
    • Excavation complete.
    • Footings placed.
    • Precast sections have been delivered. All sections have been set, welded and grouted.
    • Contractor plans to place the walls next week.

    This project is substantially complete

  • February 23, 2024

    Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link
    • Excavation complete.
    • Footings placed.
    • Precast sections have been delivered. 6 sections have been set. The other sections are still in fabrication.
    • Excavation complete.
    • Footings placed.
    • Precast sections have been delivered. 6 sections have been set. The other sections are still in fabrication.

    This project is substantially complete

  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Excavation complete.
    • Footings placed.
    • Precast sections have been delivered.
    • Excavation complete.
    • Footings placed.
    • Precast sections have been delivered.

    This project is substantially complete

  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • Contractor started excavating.
    • Footings complete.
    • Precast sections are scheduled for next week.
    • Contractor started excavating.
    • Footings complete.
    • Precast sections are scheduled for next week.

    This project is substantially complete

  • February 2, 2024

    Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link
    • Contractor started excavating.
    • Contractor started excavating.

    This project is substantially complete

  • December 1, 2023

    Share December 1, 2023 on Facebook Share December 1, 2023 on Twitter Share December 1, 2023 on Linkedin Email December 1, 2023 link
    • Contractor anticipates starting on Palmer in January.
    • Contractor anticipates starting on Palmer in January.

    This project is substantially complete

  • November 17, 2023

    Share November 17, 2023 on Facebook Share November 17, 2023 on Twitter Share November 17, 2023 on Linkedin Email November 17, 2023 link
    • Preconstruction meeting was held October 25 th.
    • NTP is scheduled for early November.
      • Contractor anticipates starting in January.
    • Preconstruction meeting was held October 25 th.
    • NTP is scheduled for early November.
      • Contractor anticipates starting in January.

    This project is substantially complete

  • August 24, 2023

    Share August 24, 2023 on Facebook Share August 24, 2023 on Twitter Share August 24, 2023 on Linkedin Email August 24, 2023 link

    Construction Impacts

    • Temporary road closures
    • Lane restrictions with flaggers
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize construction impacts

    Construction Impacts

    • Temporary road closures
    • Lane restrictions with flaggers
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize construction impacts

    This project is substantially complete