- Mainline asphalt paving is complete. Minor work remains, including approach paving, manhole adjustments, and permanent striping.
- Mainline asphalt paving is complete. Minor work remains, including approach paving, manhole adjustments, and permanent striping.
This project is substantially complete
-
Share June 2, 2023 on Facebook
Share June 2, 2023 on X (formerly Twitter)
Share June 2, 2023 on Linkedin
Email June 2, 2023 link
- Asphalt paving resumed May 25th and will continue into early June. The roadway will remain open during construction. However, drivers should expect delays and consider alternative routes.
- Asphalt paving resumed May 25th and will continue into early June. The roadway will remain open during construction. However, drivers should expect delays and consider alternative routes.
This project is substantially complete
-
Share May 26, 2023 on Facebook
Share May 26, 2023 on X (formerly Twitter)
Share May 26, 2023 on Linkedin
Email May 26, 2023 link
- Milling started May 1st and is now complete.
- Asphalt paving resumed May 25th and will continue to early June. The roadway will remain open during construction. However, drivers should expect delays and consider alternative routes.
- Milling started May 1st and is now complete.
- Asphalt paving resumed May 25th and will continue to early June. The roadway will remain open during construction. However, drivers should expect delays and consider alternative routes.
This project is substantially complete
-
Share May 19, 2023 on Facebook
Share May 19, 2023 on X (formerly Twitter)
Share May 19, 2023 on Linkedin
Email May 19, 2023 link
- Milling started May 1st and is complete.
- Asphalt paving began May 15th. The roadway will remain open during construction, however, drivers should expect delays and consider alternate routes.
- Milling started May 1st and is complete.
- Asphalt paving began May 15th. The roadway will remain open during construction, however, drivers should expect delays and consider alternate routes.
This project is substantially complete
-
Share May 12, 2023 on Facebook
Share May 12, 2023 on X (formerly Twitter)
Share May 12, 2023 on Linkedin
Email May 12, 2023 link
- Milling started May 1st and is complete.
- Asphalt paving is scheduled to begin May 15th. The roadway will remain open during construction. However, drivers should expect delays and consider alternative routes.
- Milling started May 1st and is complete.
- Asphalt paving is scheduled to begin May 15th. The roadway will remain open during construction. However, drivers should expect delays and consider alternative routes.
This project is substantially complete
-
Share May 5, 2023 on Facebook
Share May 5, 2023 on X (formerly Twitter)
Share May 5, 2023 on Linkedin
Email May 5, 2023 link
- Milling is scheduled to begin May 1st. Asphalt paving is scheduled to begin May 8th. The roadway will remain open during construction. However, drivers should expect delays and consider alternate routes.
- Milling is scheduled to begin May 1st. Asphalt paving is scheduled to begin May 8th. The roadway will remain open during construction. However, drivers should expect delays and consider alternate routes.
This project is substantially complete
-
Share April 21, 2023 on Facebook
Share April 21, 2023 on X (formerly Twitter)
Share April 21, 2023 on Linkedin
Email April 21, 2023 link
- Pipe work is complete.
- Roadway work is scheduled to begin May 1st.
- Pipe work is complete.
- Roadway work is scheduled to begin May 1st.
This project is substantially complete
-
Share April 14, 2023 on Facebook
Share April 14, 2023 on X (formerly Twitter)
Share April 14, 2023 on Linkedin
Email April 14, 2023 link
- Pipework is complete.
- Roadway work is scheduled to begin May 1st.
- Pipework is complete.
- Roadway work is scheduled to begin May 1st.
This project is substantially complete
-
Share March 31, 2023 on Facebook
Share March 31, 2023 on X (formerly Twitter)
Share March 31, 2023 on Linkedin
Email March 31, 2023 link
- Pipe work is complete. Roadway work will be done in April or May.
- Pipe work is complete. Roadway work will be done in April or May.
This project is substantially complete
-
Share March 24, 2023 on Facebook
Share March 24, 2023 on X (formerly Twitter)
Share March 24, 2023 on Linkedin
Email March 24, 2023 link
- Pipe work is complete.
- Roadway work will be done in April or May.
- Pipe work is complete.
- Roadway work will be done in April or May.
This project is substantially complete