Beacon Light, Ballantyne to HWY 16

Share on Facebook Share on Twitter Share on Linkedin Email this link

This project is substantially complete

Roadway and ADA Improvements (2023), Part 2

This fall, the Ada County Highway District will begin work on Beacon Light Road between Highway 16 and Ballantyne Lane. This pavement maintenance project consists primarily of removing and replacing the existing asphalt pavement. Work also includes reconstructing existing adjacent curb ramps to meet modern standards and stormwater pipe replacements. Construction is anticipated to end early summer of 2023.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

Roadway and ADA Improvements (2023), Part 2

This fall, the Ada County Highway District will begin work on Beacon Light Road between Highway 16 and Ballantyne Lane. This pavement maintenance project consists primarily of removing and replacing the existing asphalt pavement. Work also includes reconstructing existing adjacent curb ramps to meet modern standards and stormwater pipe replacements. Construction is anticipated to end early summer of 2023.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete

  • March 17, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipe work is complete.
    • Roadway work will be one in April or May.
  • March 10, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipe work is complete.
    • Road work will be completed in April or May.
  • March 3, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Beacon Light between Meridian Road and Ballantyne Lane will be closed March 6-10.
    • Roadway work will be done in April or May.
  • February 24, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Updated closure information starting March 3rd for one week.
    • Beacon Light will be closed from Meridian to Ballantyne for construction work.

  • February 17, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipe work ongoing.
    • Beacon Light Road between Park Lane and Meridian Road will be closed February 22 - March 1.
    • Beacon Light Road between Meridian Road and Ballantyne Lane will be closed march 1 - March 8.

  • February 10, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipe work is ongoing - weather dependent.
  • February 3, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipe work continues weather dependent.
  • January 27, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Beacon Light will be closed between Linder Road and Park Lane February 2 - 9
  • January 20, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipe work is ongoing.
    • Beacon Light will be closed between Lanewood and Palmer - January 18-25th.
  • January 17- Update to Closure Starting Date

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    The road closure between Lanewood Road and Palmer Lane is now expected to begin Thursday, January 19. Work is still expected to wrap up January 25, however, all work is weather dependent.