State Street, 8th Street to 4th Street
Share State Street, 8th Street to 4th Street on Facebook
Share State Street, 8th Street to 4th Street on Twitter
Share State Street, 8th Street to 4th Street on Linkedin
Email State Street, 8th Street to 4th Street link
- Reconstruct State Street between 8th and 4th streets.
- Upgrade all three traffic signals on this section of State St.
- Construct bulb-outs for shorter pedestrian crossings and better visibility.
- Add vegetated bioretention facilities for stormwater treatment.
- Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
- Reconstruct State Street between 8th and 4th streets.
- Upgrade all three traffic signals on this section of State St.
- Construct bulb-outs for shorter pedestrian crossings and better visibility.
- Add vegetated bioretention facilities for stormwater treatment.
- Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
-
July 12, 2024
Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link- Project includes work on State Street between 4th Street and 8th Street - Veolia water work complete.
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Contractor completed demo on State and 8th this week.
- Excavation started this week, on the north side, in preparation for base materials.
-
June 28, 2024
Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link- Veolia water work started April 1st and is on-going.
- State and 8th intersection work is complete.
- 8th Street electrical work ongoing.
- Contractor completed demo on State and 8th this week.
-
June 21, 2024
Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link- Project includes work on State Street between 4th Street and 8th Street.
- Veolia water work started April 1st and is on-going.
- State and 8th intersection work is complete.
- 8th Street electrical work ongoing.
- Contractor completed demo on State and 8th this week.
-
June 14, 2024
Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 linkProject includes work on State Street between 4th Street and 8th Street
- Veolia water work started April 1st and is on-going
- State and 8th intersection work is complete
- 8th Street utility work ongoing.
- Electrical work ongoing.
- Contractor started demo on State and 8th this week.
- Veolia water work started April 1st and is on-going
-
June 7, 2024
Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link- Veolia water work started April 1st and is on-going
- State and 8th intersection work is complete minus a hydrant tieover
- 8th Street utility work ongoing
- Electrical work ongoing
- Contractor expects to start demo on State and 8th as early as next week
- Veolia water work started April 1st and is on-going
-
May 31, 2024
Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link- Veolia water work started April 1st and is on-going.
- 8th Street utility work ongoing.
- Electrical work ongoing.
-
May 23, 2024
Share May 23, 2024 on Facebook Share May 23, 2024 on Twitter Share May 23, 2024 on Linkedin Email May 23, 2024 link- Veolia water work started April 1st and is on-going.
- 8th Street utility work ongoing.
- Electrical work ongoing.
- Pole bases on 5th and 6th have been placed.
-
May 16, 2024
Share May 16, 2024 on Facebook Share May 16, 2024 on Twitter Share May 16, 2024 on Linkedin Email May 16, 2024 link- Veolia water work started April 1st and is on-going.
- 8th Street utility work ongoing.
- Electrical work ongoing.
- Pole bases on 5th and 6th have been placed.
-
May 10, 2024
Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link- Project includes work on State Street between 4th Street and 8th Street.
- Veolia water work started April 1st and is on-going.
- 8th Street utility work ongoing.
- Electrical work ongoing.
-
May 3, 2024
Share May 3, 2024 on Facebook Share May 3, 2024 on Twitter Share May 3, 2024 on Linkedin Email May 3, 2024 link- Veolia water work started April 1st and is on-going.
- 8 th Street utility work ongoing.
Page last updated: 15 Nov 2024, 10:53 AM
State Street 8th to 4th Design
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Community and Business Relations Coordinator
Phone 208-387-6100 Email projects@achdidaho.org
Follow Project
Stay informed
Subscribe for project updates
56 members of your community are following this project