This project is substantially complete. 

In January 2024, The Ada County Highway District (ACHD) will start construction on the 2024 Arterial and Collector Capital Maintenance Project. This maintenance project includes pavement rehabilitation, upgraded pedestrian ramps, and new curb, gutter, and sidewalk at certain locations. Construction is anticipated to be completed late in the summer of 2024.

Road Segments

  • Swan Falls Road, King Road to Sunbeam Street
  • Stagecoach Way, Swan Falls Road to Luker Road
  • Luker Road, King Road to Stagecoach Way
    • Fill in a sidewalk gap on Luker Road between Access Street and Stage Coach Way
    • Replace an existing culvert at the Luker Road and Stagecoach Road intersection
  • Poen Road, Swan Falls Road to Cloverdale Road

Construction Impacts

  • Temporary road closures and lane restrictions
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

In January 2024, The Ada County Highway District (ACHD) will start construction on the 2024 Arterial and Collector Capital Maintenance Project. This maintenance project includes pavement rehabilitation, upgraded pedestrian ramps, and new curb, gutter, and sidewalk at certain locations. Construction is anticipated to be completed late in the summer of 2024.

Road Segments

  • Swan Falls Road, King Road to Sunbeam Street
  • Stagecoach Way, Swan Falls Road to Luker Road
  • Luker Road, King Road to Stagecoach Way
    • Fill in a sidewalk gap on Luker Road between Access Street and Stage Coach Way
    • Replace an existing culvert at the Luker Road and Stagecoach Road intersection
  • Poen Road, Swan Falls Road to Cloverdale Road

Construction Impacts

  • Temporary road closures and lane restrictions
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

This project is substantially complete. 

  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link

    Project includes work on the following segments:

    • Swan Falls Rd, King Rd to Sunbeam St
      • Paving complete.
      • Shouldering complete as of May 28th
    • Stagecoach Way, Swan Falls Rd to Luker Rd
      • Closure started May 30th
      • Milling complete.
    • Luker Rd, King Rd to Stagecoach Way
      • Irrigation pipe crossing complete and patched back.
      • Remaining work expected to start next week
    • Poen Rd, Swan Falls Rd to Cloverdale Rd
      • Complete – waiting 45 days before second coat of paint is applied.
  • May 31, 2024

    Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Paving complete. Shouldering complete as of May 28th.
    • Stagecoach Way, Swan Falls Rd to Luker Rd - Closure expected to start May 30th.
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back. Remaining work expected to start next week.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Lane lines are scheduled to be painted next week, if crews are available.
  • May 23, 2024

    Share May 23, 2024 on Facebook Share May 23, 2024 on Twitter Share May 23, 2024 on Linkedin Email May 23, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Contractor will be paving on Friday.
    • Stagecoach Way, Swan Falls Rd to Luker Rd.
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back. Remaining work waiting until Swan Falls is done.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Lane lines are scheduled to be painted next week, if crews are available.
  • May 16, 2024

    Share May 16, 2024 on Facebook Share May 16, 2024 on Twitter Share May 16, 2024 on Linkedin Email May 16, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Contractor started milling this week.
    • Stagecoach Way, Swan Falls Rd to Luker Rd
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back. Remaining work waiting until Swan Falls is done.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Lane lines are scheduled to be painted this week, if crews are available.
  • May 10, 2024

    Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Contractor expects to start work in end of May.
    • Stagecoach Way, Swan Falls Rd to Luker Rd.
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Phase 1 Shoulder work complete. Paving is complete on the north and south side of the road. Minor soft spot repairs need fixed. Lane lines are scheduled to be painted next week, if crews are available.
  • May 3, 2024

    Share May 3, 2024 on Facebook Share May 3, 2024 on Twitter Share May 3, 2024 on Linkedin Email May 3, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St
      • Contractor expects to start work in June.
      • Stagecoach Way, Swan Falls Rd to Luker Rd
      • Luker Rd, King Rd to Stagecoach Way
        • Irrigation pipe crossing complete and patched back.
      • Poen Rd, Swan Falls Rd to Cloverdale Rd
        • Phase 1 Shoulder work continues.
        • Paving is complete on the south side of the road. Minor soft spot repairs fixed.
        • Start paving north side and overlay this week, weather permitting.
        • Lane lines are scheduled to be painted next week, if crews are available.
  • April 25, 2024

    Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Contractor expects to start work in June.
    • Stagecoach Way, Swan Falls Rd to Luker Rd
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Phase 1 Shoulder work continues. Paving is complete on the south side of the road. Minor soft spot repairs needed. Contractor continues excavating and importing base material on the north side of the road. Tentatively planning to start paving north side and overlay this week, weather permitting.
  • April 14, 2024

    Share April 14, 2024 on Facebook Share April 14, 2024 on Twitter Share April 14, 2024 on Linkedin Email April 14, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Contractor expects to start work in June.
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Phase 1 Shoulder work continues. Paving is complete on the south side of the road. Contractor continues excavating and importing base material on the north side of the road.
  • April 12, 2024

    Share April 12, 2024 on Facebook Share April 12, 2024 on Twitter Share April 12, 2024 on Linkedin Email April 12, 2024 link
    • Luker Rd, King Rd to Stagecoach Way
      • Irrigation pipe crossing complete and patched back.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Phase 1 Shoulder work continues. Paving is complete on the south side of the road. Contractor continues excavating and importing base material on the north side of the road.
  • April 5, 2024

    Share April 5, 2024 on Facebook Share April 5, 2024 on Twitter Share April 5, 2024 on Linkedin Email April 5, 2024 link
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Phase 1 Shoulder work continues. Paving is complete on the south side of the road. Contractor continues excavating and importing base material on the north side of the road.