2025 Meridian Downtown Pavement and Pedestrian Improvements

Share 2025 Meridian Downtown Pavement and Pedestrian Improvements on Facebook Share 2025 Meridian Downtown Pavement and Pedestrian Improvements on Twitter Share 2025 Meridian Downtown Pavement and Pedestrian Improvements on Linkedin Email 2025 Meridian Downtown Pavement and Pedestrian Improvements link

The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.

Work could include

  • Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
  • Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
  • Adding crosswalk markings for school walk route crossings
  • Stormwater and irrigation upgrades to improve flows

Street Segments


To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org(External link).

Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org(External link)


The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.

Work could include

  • Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
  • Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
  • Adding crosswalk markings for school walk route crossings
  • Stormwater and irrigation upgrades to improve flows

Street Segments


To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org(External link).

Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org(External link)


  • July 2, 2025

    02 Jul 2025
    Share July 2, 2025 on Facebook Share July 2, 2025 on Twitter Share July 2, 2025 on Linkedin Email July 2, 2025 link

    Project includes work on the following segments:

    • Broadway Ave, E 3rd Street to E 6th Street - COMPLETE.
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
    • Idaho Ave, W 8th St to Meridian Rd - Milling complete.
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
    • Washington St, NW 7th Street to Meridian Rd -Grade prep and complete. Utility work complete. Concrete prep and placements ongoing.
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
    • E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep are ongoing. Concrete placements are ongoing.
    • W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work started.
    • W 3rd Street, Pine Ave to north end - Site prep ongoing. Concrete placements have started. Pine will be closed starting June 24th. Broadway will be the detour.
    • NW 4th Street, Broadway Ave to Maple Ave - COMPLETE.
    • NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
    • NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements have started.
  • June 26, 2025

    26 Jun 2025
    Share June 26, 2025 on Facebook Share June 26, 2025 on Twitter Share June 26, 2025 on Linkedin Email June 26, 2025 link

    Project includes work on the following segments:

    • Broadway Ave, E 3rd Street to E 6th Street - COMPLETE
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE
    • Idaho Ave, W 8th St to Meridian Rd - Milling complete.
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
    • Washington St, NW 7th Street to Meridian Rd - Grade prep and complete. Utility work complete. Concrete prep and placements ongoing.
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
    • E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep are ongoing. Concrete placements are ongoing.
    • W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work started.
    • W 3rd Street, Pine Ave to north end - Site prep ongoing. Concrete placements have started. Pine will be closed starting June 24th. Broadway will be the detour.
    • NW 4th Street, Broadway Ave to Maple Ave - COMPLETE.
    • NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
    • NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements have started.
  • June 20, 2025

    21 Jun 2025
    Share June 20, 2025 on Facebook Share June 20, 2025 on Twitter Share June 20, 2025 on Linkedin Email June 20, 2025 link

    Project includes work on the following segments:

    • Broadway Ave, E 3rd Street to E 6th Street
      • COMPLETE
    • Cherry Ave, NW 4th Street to Meridian Rd
      • COMPLETE
    • Idaho Ave, W 8th St to Meridian Rd
      • Milling started this week.
    • Maple Ave, W 1st Street to Meridian Rd
      • COMPLETE
    • Washington St, NW 7th Street to Meridian Rd
      • Grade prep and demo ongoing.
      • Utility work complete.
      • Concrete prep and placements ongoing.
    • E 2nd Street, Idaho Ave to Pine Ave
      • COMPLETE
    • E 4th Street, Broadway Ave to State Ave
      • Demo, utility work, and grade prep are ongoing
      • Concrete placements have ongoing
    • W 2nd Street, Cherry Ave to Cherry Lane
      • Milling started this week.
    • W 3rd Street, Pine Ave to north end
      • Site prep ongoing.
      • Concrete placements have started.
      • Pine will be closed starting next week. Broadway will be the detour.
    • NW 4th Street, Broadway Ave to Maple Ave
      • COMPLETE
    • NW 6th Street, Carlton Ave to Washington St
      • Demo complete.
      • Utility work complete.
      • Concrete placements ongoing.
    • NW 7th Street, McFadden Ave to Washington St
      • Demo and utility work complete.
      • Concrete placements have started.
  • June 13, 2025

    13 Jun 2025
    Share June 13, 2025 on Facebook Share June 13, 2025 on Twitter Share June 13, 2025 on Linkedin Email June 13, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - COMPLETE.
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
    • Idaho Ave, W 8th St to Meridian Rd - Milling started this week.
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
    • Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work complete. Concrete prep and placements ongoing.
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
    • E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep are ongoing. Concrete placements have ongoing.
    • W 2nd Street, Cherry Ave to Cherry Lane - Milling started this week.
    • W 3rd Street, Pine Ave to north end - Site prep ongoing. Concrete placements have started.
    • NW 4th Street, Broadway Ave to Maple Ave - COMPLETE.
    • NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
    • NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements have started.
    • *Irrigation work complete.
  • June 6, 2025

    06 Jun 2025
    Share June 6, 2025 on Facebook Share June 6, 2025 on Twitter Share June 6, 2025 on Linkedin Email June 6, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Paving this week.
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
    • Idaho Ave, W 8th St to Meridian Rd - Work starting June 9th.
    • Maple Ave, W 1st Street to Meridian Rd -COMPLETE.
    • Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work complete. Concrete placements have started.
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
    • E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep are ongoing. Concrete placements have started.
    • W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
    • W 3rd Street, Pine Ave to north end. Site prep ongoing. Concrete placements have started.
    • NW 4th Street, Broadway Ave to Maple Ave - Paving complete.
    • NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements have started.
    • NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements have started.
    • *Irrigation work complete.
  • May 30, 2025

    30 May 2025
    Share May 30, 2025 on Facebook Share May 30, 2025 on Twitter Share May 30, 2025 on Linkedin Email May 30, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Prepping for concrete. Grade work started.
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
    • Idaho Ave, W 8th St to Meridian Rd
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
    • Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
    • E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west. Demo, utility work, and grade prep are ongoing.
    • W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
    • W 3rd Street, Pine Ave to north end - Site prep ongoing.
    • NW 4th Street, Broadway Ave to Maple Ave - Paving this week.
    • NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work ongoing.
    • NW 7th Street, McFadden Ave to Washington St - Demo and utility work ongoing.
    • *Irrigation work complete.
  • May 23, 2025

    23 May 2025
    Share May 23, 2025 on Facebook Share May 23, 2025 on Twitter Share May 23, 2025 on Linkedin Email May 23, 2025 link

    Project includes work on the following segments:

    • Broadway Ave, E 3rd Street to E 6th Street - Prepping for concrete. Grade work started.
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE
    • Idaho Ave, W 8th St to Meridian Rd
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE
    • Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE
    • E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west. Demo, utility work, and grade prep are ongoing.
    • W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE
    • W 3rd Street, Pine Ave to north end - Site prep ongoing.
    • NW 4th Street, Broadway Ave to Maple Ave - Paving this week.
    • NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work ongoing.
    • NW 7th Street, McFadden Ave to Washington St - Demo and utility work ongoing.
    • *Irrigation work complete.
  • May 16, 2025

    16 May 2025
    Share May 16, 2025 on Facebook Share May 16, 2025 on Twitter Share May 16, 2025 on Linkedin Email May 16, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Prepping for concrete. Grade work started.
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
    • Idaho Ave, W 8th St to Meridian Rd.
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
    • Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
    • E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west. Demo, utility work, and grade prep are ongoing.
    • W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
    • W 3rd Street, Pine Ave to north end - Site prep ongoing.
    • NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
    • NW 6th Street, Carlton Ave to Washington St - Demo ongoing. Utility work ongoing.
    • NW 7th Street, McFadden Ave to Washington St - Demo and utility work ongoing.
    • *Irrigation work complete.
  • May 8, 2025

    08 May 2025
    Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 link

    Project includes work on the following segments:

    • Broadway Ave, E 3rd Street to E 6th Street - Prepping for concrete. Grade work started.
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
    • Idaho Ave, W 8th St to Meridian Rd.
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
    • Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
    • E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west. Demo, utility work, and grade prep are ongoing.
    • W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
    • W 3rd Street, Pine Ave to north end - Site prep ongoing.
    • NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
    • NW 6th Street, Carlton Ave to Washington St - Demo started.
    • NW 7th Street, McFadden Ave to Washington St - Demo and utility work ongoing.
    • *Irrigation work complete.
  • May 2, 2025

    02 May 2025
    Share May 2, 2025 on Facebook Share May 2, 2025 on Twitter Share May 2, 2025 on Linkedin Email May 2, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Prepping for concrete. Grade work started.
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
    • Idaho Ave, W 8th St to Meridian Rd.
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
    • Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
    • E 4th Street, Broadway Ave to State Ave - Milled. Intersections are open east/west. Demo, utility work, and grade prep are ongoing.
    • W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
    • W 3rd Street, Pine Ave to north end - Site prep ongoing.
    • NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
    • NW 6th Street, Carlton Ave to Washington St - Demo started.
    • NW 7th Street, McFadden Ave to Washington St - Demo and utility work ongoing.
    • *Irrigation work complete.
Page last updated: 02 Jul 2025, 11:48 AM