Cole Road, Victory Road to Overland Road

Share Cole Road, Victory Road to Overland Road on Facebook Share Cole Road, Victory Road to Overland Road on X (formerly Twitter) Share Cole Road, Victory Road to Overland Road on Linkedin Email Cole Road, Victory Road to Overland Road link

Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*

Project Highlights

  • Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
  • Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
  • Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards

Construction Impacts

  • Night work is expected to help reduce daytime traffic impacts
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

Starting as early as mid-April, the Ada County Highway District (ACHD) will begin reconstructing Cole Road from Victory Road to Overland Road. The pavement has reached the end of its service life and no longer meets current standards. Construction is expected to be complete in late fall 2026.*

Project Highlights

  • Reconstructing the road surface on Cole Road from south of Overland Road to south of Mossy Cup Street, resulting in a new roadway surface throughout the corridor
  • Upgrading existing pedestrian signals to Accessible Pedestrian Signals (APS) at the intersections of Cole Road and Entertainment Avenue, and Cole Road and Century Way
  • Updating pedestrian ramps as needed to meet Americans with Disabilities Act (ADA) accessibility standards

Construction Impacts

  • Night work is expected to help reduce daytime traffic impacts
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction impacts including noise, dust, equipment backup alarms, and ground vibration
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

  • September 5, 2025

    Share September 5, 2025 on Facebook Share September 5, 2025 on X (formerly Twitter) Share September 5, 2025 on Linkedin Email September 5, 2025 link
    • Contractor intends to start on the east leg on September 7th. Eastbound Overland Road will be restricted to one through lane; turn lanes will remain open.
    • Contractor intends to start on the east leg on September 7th. Eastbound Overland Road will be restricted to one through lane; turn lanes will remain open.
  • April 15, 2025

    Share April 15, 2025 on Facebook Share April 15, 2025 on X (formerly Twitter) Share April 15, 2025 on Linkedin Email April 15, 2025 link
    • Project is currently in the Right of Way phase.
    • Notice to proceed date March 2026.
    • Cole Road Joint Repair - Notice to proceed date June 2025.
    • Project is currently in the Right of Way phase.
    • Notice to proceed date March 2026.
    • Cole Road Joint Repair - Notice to proceed date June 2025.
  • April 8, 2025

    Share April 8, 2025 on Facebook Share April 8, 2025 on X (formerly Twitter) Share April 8, 2025 on Linkedin Email April 8, 2025 link
    • Project is currently in the Right of Way phase.
    • Notice to proceed date for the project is March 2026.
    • Project is currently in the Right of Way phase.
    • Notice to proceed date for the project is March 2026.