Victory and Century Way
- Started May 7th.
- Removing and replacing sidewalk on the west side.
- Starting east side May 27th.
Victory and Century Way
- Started May 7th.
- Removing and replacing sidewalk on the west side.
- Starting east side May 27th.
-
Share May 13, 2026 on Facebook
Share May 13, 2026 on X (formerly Twitter)
Share May 13, 2026 on Linkedin
Email May 13, 2026 link
- Victory and Century Way - Started May 7th. Removing and replacing sidewalk.
- Victory and Century Way - Started May 7th. Removing and replacing sidewalk.
-
Share May 8, 2026 on Facebook
Share May 8, 2026 on X (formerly Twitter)
Share May 8, 2026 on Linkedin
Email May 8, 2026 link
- Victory and Century Way - Starting May 7th.
- Removing and replacing sidewalk.
- Victory and Century Way - Starting May 7th.
- Removing and replacing sidewalk.
-
Share Construction to Start Soon on Facebook
Share Construction to Start Soon on X (formerly Twitter)
Share Construction to Start Soon on Linkedin
Email Construction to Start Soon link
Starting as early as mid-April, ACHD will begin reconstructing Cole Road from Victory Road to Overland Road. Construction is expected to be complete in late fall 2026.*
Construction Impacts
- Night work is expected to help reduce daytime traffic impacts
- Lane restrictions with flaggers
- Pedestrian detours and sidewalk closures
- General construction impacts including noise, dust, equipment backup alarms, and ground vibration
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
Starting as early as mid-April, ACHD will begin reconstructing Cole Road from Victory Road to Overland Road. Construction is expected to be complete in late fall 2026.*
Construction Impacts
- Night work is expected to help reduce daytime traffic impacts
- Lane restrictions with flaggers
- Pedestrian detours and sidewalk closures
- General construction impacts including noise, dust, equipment backup alarms, and ground vibration
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
-
Share October 2, 2025 on Facebook
Share October 2, 2025 on X (formerly Twitter)
Share October 2, 2025 on Linkedin
Email October 2, 2025 link
- Excavation and paving is complete.
- Remaining work includes pavement markings. Work was scheduled for September 29th but delayed due to rain. Work has been rescheduled for October 7th.
- Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
- Work is weather-dependent.
- Excavation and paving is complete.
- Remaining work includes pavement markings. Work was scheduled for September 29th but delayed due to rain. Work has been rescheduled for October 7th.
- Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
- Work is weather-dependent.
-
Share September 26, 2025 on Facebook
Share September 26, 2025 on X (formerly Twitter)
Share September 26, 2025 on Linkedin
Email September 26, 2025 link
- Excavation and paving is complete.
- Remaining work includes pavement markings. Work is scheduled for September 29th.
- Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
- Work is weather-dependent.
- Excavation and paving is complete.
- Remaining work includes pavement markings. Work is scheduled for September 29th.
- Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
- Work is weather-dependent.
-
Share September 19, 2025 on Facebook
Share September 19, 2025 on X (formerly Twitter)
Share September 19, 2025 on Linkedin
Email September 19, 2025 link
- Excavation and paving is complete.
- Remaining work includes pavement markings.
- Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
- Work is weather-dependent.
- Excavation and paving is complete.
- Remaining work includes pavement markings.
- Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
- Work is weather-dependent.
-
Share September 12, 2025 on Facebook
Share September 12, 2025 on X (formerly Twitter)
Share September 12, 2025 on Linkedin
Email September 12, 2025 link
Cole Road and Overland Road - Joint Repair
- Contractor started on the east leg on September 7th.
- Work will then proceed to the north and west legs.
- Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
- Work is weather-dependent.
Cole Road and Overland Road - Joint Repair
- Contractor started on the east leg on September 7th.
- Work will then proceed to the north and west legs.
- Work is being done at night. Lane restrictions will be in place from 8:00pm to 6:00am.
- Work is weather-dependent.
-
Share September 5, 2025 on Facebook
Share September 5, 2025 on X (formerly Twitter)
Share September 5, 2025 on Linkedin
Email September 5, 2025 link
- Contractor intends to start on the east leg on September 7th. Eastbound Overland Road will be restricted to one through lane; turn lanes will remain open.
- Contractor intends to start on the east leg on September 7th. Eastbound Overland Road will be restricted to one through lane; turn lanes will remain open.
-
Share April 15, 2025 on Facebook
Share April 15, 2025 on X (formerly Twitter)
Share April 15, 2025 on Linkedin
Email April 15, 2025 link
- Project is currently in the Right of Way phase.
- Notice to proceed date March 2026.
- Cole Road Joint Repair - Notice to proceed date June 2025.
- Project is currently in the Right of Way phase.
- Notice to proceed date March 2026.
- Cole Road Joint Repair - Notice to proceed date June 2025.