Downtown Eagle Mobility Improvements: Eagle Road and State Street

Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

This project is substantially complete. 

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

This project is substantially complete. 

  • July 25, 2025

    Share July 25, 2025 on Facebook Share July 25, 2025 on Twitter Share July 25, 2025 on Linkedin Email July 25, 2025 link

    Olde Park

    Landscape and brick pavers ongoing

    Aikens between 2nd and Eagle

    Parking lot ongoing. Landscaping ongoing.

    Eagle Rd & State Intersection

    Started July 7th. Removal of road and signal equipment. Underground work after removals. Veolia starting potentially July 21st. Underground electrical ongoing.


  • July 18, 2025

    Share July 18, 2025 on Facebook Share July 18, 2025 on Twitter Share July 18, 2025 on Linkedin Email July 18, 2025 link

    Olde Park

    • Landscape and brick pavers ongoing

    Aikens between 2nd and Eagle

    • Parking lot ongoing
    • Landscaping ongoing

    Eagle Rd & State Intersection

    • Started July 7th
    • Removal of road and signal equipment
    • Underground work after removals
    • Veolia starting potentially July 21st
  • Pedestrian Detour Route Map

    Share Pedestrian Detour Route Map on Facebook Share Pedestrian Detour Route Map on Twitter Share Pedestrian Detour Route Map on Linkedin Email Pedestrian Detour Route Map link

  • July 11, 2025

    Share July 11, 2025 on Facebook Share July 11, 2025 on Twitter Share July 11, 2025 on Linkedin Email July 11, 2025 link

    Olde Park

    • Landscape and brick pavers ongoing

    Aikens between 2nd and Eagle

    • Parking lot ongoing

    Eagle Rd & State Intersection

    • Closure started July 7th. Removal of road and signal equipment. Underground work after removals.


  • Detour Map - Closure July 6th

    Share Detour Map - Closure July 6th on Facebook Share Detour Map - Closure July 6th on Twitter Share Detour Map - Closure July 6th on Linkedin Email Detour Map - Closure July 6th link

  • July 2, 2025

    Share July 2, 2025 on Facebook Share July 2, 2025 on Twitter Share July 2, 2025 on Linkedin Email July 2, 2025 link

    Olde Park

    • Landscape and brick pavers ongoing.

    Aikens between 2nd and Eagle

    • Landscaping ongoing - Parking lot ongoing.

    Eagle Rd, Where Phase 1 stopped to Intersection of Eagle and Old State - Complete.

    Eagle Rd & State Intersection - Closure - Starting July 7th. Removal of road and signal equipment. Underground work after removals.


  • June 26, 2025

    Share June 26, 2025 on Facebook Share June 26, 2025 on Twitter Share June 26, 2025 on Linkedin Email June 26, 2025 link

    Olde Park

    • Landscape and brick pavers ongoing

    Aikens between 2nd and Eagle

    • Landscaping ongoing. Parking lot ongoing. Private contractor working at 128 S. Eagle Rd.

    Eagle Rd

    • Milling complete. Concrete work ongoing. Paving scheduled for June 26th. Planning on being open for Eagle Fun Days.

    The intersection of Eagle and Old State is anticipated to be closed July 7th until the middle of August.


  • June 20, 2025

    Share June 20, 2025 on Facebook Share June 20, 2025 on Twitter Share June 20, 2025 on Linkedin Email June 20, 2025 link
    • Olde Park (1A)
      • Landscape and brick pavers ongoing
      • Aikens between 2nd and Eagle (1B)
      • Landscaping ongoing
      • Parking lot ongoing
    • Eagle Rd, Where Phase 1 stopped to Intersection of Eagle and Old State.
      • Starting June 6th, Eagle Road will be closed between Plaza and Old State.
      • Veolia working on Tie-overs and testing
      • Storm Drain ongoing
      • Anticipated paving June 26th
  • June 13, 2025

    Share June 13, 2025 on Facebook Share June 13, 2025 on Twitter Share June 13, 2025 on Linkedin Email June 13, 2025 link

    Olde Park

    • Landscape and brick pavers ongoing.

    Aikens between 2nd and Eagle

    • Landscaping ongoing.

    Starting June 6th, Eagle Road will be closed between Plaza and Old State. Veolia installing water line. Excavation and storm drain installation.


  • June 6, 2025

    Share June 6, 2025 on Facebook Share June 6, 2025 on Twitter Share June 6, 2025 on Linkedin Email June 6, 2025 link

    Olde Park

    • Landscape and brick pavers ongoing.

    Aikens between 2nd and Eagle

    • Placing silva cells.
    • Electrical work ongoing.
    • Curb and sidewalk ongoing.
    • Asphalt paving was done May 29th.
    • Road to be opened June 6th after striping and manhole collaring is complete.

    Olde Park To Eagle Rd

    • Road closure anticipated May 5th - June 6th.
    • Silva cells ongoing.
    • Prepping and placing sidewalk crossings.
    • Paving was done May 30th.

    Starting June 6th, Eagle Road will be closed between Plaza and Old State. Veolia installing water line installation. Excavation and storm drain installation.