Eagle Road, Lake Hazel Road to Amity Road

Share Eagle Road, Lake Hazel Road to Amity Road on Facebook Share Eagle Road, Lake Hazel Road to Amity Road on Twitter Share Eagle Road, Lake Hazel Road to Amity Road on Linkedin Email Eagle Road, Lake Hazel Road to Amity Road link

The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.

Roadway Description

  • Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
  • Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
  • Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.

Eagle and Lake Hazel Intersection Description

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks

The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.

Roadway Description

  • Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
  • Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
  • Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.

Eagle and Lake Hazel Intersection Description

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks
  • January 30, 2026

    Share January 30, 2026 on Facebook Share January 30, 2026 on Twitter Share January 30, 2026 on Linkedin Email January 30, 2026 link
    • Eagle Road was opened to one lane in each direction on December 23rd.
    • Signal at Eagle and Lake Hazel active starting January 28th.
    • Sidewalk and other minor work ongoing.
  • January 23, 2026

    Share January 23, 2026 on Facebook Share January 23, 2026 on Twitter Share January 23, 2026 on Linkedin Email January 23, 2026 link
    • Sidewalk and other minor work ongoing.
  • January 16, 2026

    Share January 16, 2026 on Facebook Share January 16, 2026 on Twitter Share January 16, 2026 on Linkedin Email January 16, 2026 link
    • Eagle Road open to one lane in each direction on December 23rd.
    • Sidewalk and other minor work ongoing.
  • January 9, 2026

    Share January 9, 2026 on Facebook Share January 9, 2026 on Twitter Share January 9, 2026 on Linkedin Email January 9, 2026 link
    • Eagle Road open to one lane in each direction on December 23rd.
    • Sidewalk and other minor work ongoing.
  • December 18, 2025

    Share December 18, 2025 on Facebook Share December 18, 2025 on Twitter Share December 18, 2025 on Linkedin Email December 18, 2025 link

    Eagle and Lake Hazel Intersection

    • Weather dependent.
    • Finishing up site concrete.
    • Signal poles placed.

    Lake Hazel to Amity

    • Lake Hazel to Amity closed for duration.
    • Working on Taconic intersection.
    • Concrete paving complete.
    • Placing School Flashers. Placing RRFB poles.
    • Pavement Markings at Taconic once concrete cure complete - Weather dependent.


  • December 11, 2025

    Share December 11, 2025 on Facebook Share December 11, 2025 on Twitter Share December 11, 2025 on Linkedin Email December 11, 2025 link

    Eagle and Lake Hazel Intersection

    • Signage and Pavement markings being placed - Weather dependent.
    • Preparing for placement of signal poles.
    • Anticipated December 17th.

    Lake Hazel to Amity

    • Lake Hazel to Amity closed for duration.
    • Working on Taconic intersection.
    • Concrete paving ongoing until December 18th.
    • Placements pending weather.
  • December 4, 2025

    Share December 4, 2025 on Facebook Share December 4, 2025 on Twitter Share December 4, 2025 on Linkedin Email December 4, 2025 link

    Eagle and Lake Hazel Intersection

    • Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
    • Concrete fence complete
    • Concrete Intersection placed: Signage and Pavement markings being placed. Preparing for placement of signal poles. Anticipated December 17th. Finishing asphalt paving between Lake Hazel and Levin Dr week of November 24th.

    Lake Hazel to Amity

    • Lake Hazel to Amity closed for duration.
    • Working on Taconic intersection.
    • Placed concrete paving at all approaches of roundabout.
    • Anticipated paving between Taconic and Amity week of November 10th.
    • Taconic Intersection concrete placement starting November 19th – December 12th.
  • November 20, 2025

    Share November 20, 2025 on Facebook Share November 20, 2025 on Twitter Share November 20, 2025 on Linkedin Email November 20, 2025 link
    • Eagle and Lake Hazel Intersection o Lake Hazel and Eagle Intersection opened July 1st in the east/west direction.
    • Concrete fence complete.
    • Concrete Intersection being placed: November 21st starting at 2am. November 24th starting at 3 am.
    • Prepping for placement of signal poles. Anticipated December 3rd. Finishing asphalt paving between Lake Hazel and Levine week of November 24th.Lake Hazel to Amity.
    • Lake Hazel to Amity closed for duration.
    • Working on Taconic intersection.
    • Placed concrete paving at all approaches of roundabout o Anticipated paving between Taconic and Amity week of November 10th.
    • Taconic Intersection concrete placement starting November 19th.
  • November 14, 2025

    Share November 14, 2025 on Facebook Share November 14, 2025 on Twitter Share November 14, 2025 on Linkedin Email November 14, 2025 link

    Eagle and Lake Hazel Intersection

    • Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
    • Concrete fence being placed
    • Finishing up concrete
    • Prepping for placement of Signal poles

    Lake Hazel to Amity

    • Lake Hazel to Amity closed for duration
    • Working on Taconic intersection
    • Placed concrete paving at all approaches of roundabout
    • Anticipated paving between Taconic and Amity week of November 10th
    • Taconic Intersection concrete placement starting November 19th


  • November 7, 2025

    Share November 7, 2025 on Facebook Share November 7, 2025 on Twitter Share November 7, 2025 on Linkedin Email November 7, 2025 link

    Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete. Prepping for placement of Signal poles.

    Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Sidewalk & curb ongoing between Taconic and Amity. Working on Taconic intersection. Placed concrete paving at all approaches of roundabout. Anticipated paving between Taconic and Amity week of November 10th .

Page last updated: 30 Jan 2026, 09:49 AM