Share Phase 2 Begins Tuesday, July 1 on Facebook
Share Phase 2 Begins Tuesday, July 1 on Linkedin
Email Phase 2 Begins Tuesday, July 1 link
Phase 2 of the Eagle Road, Lake Hazel to Amity Road project will begin next week.
Starting Tuesday, July 1, Lake Hazel Road will be open to east-west traffic. Also beginning Tuesday, Eagle Road will be fully closed between Lake Hazel and Amity Roads.
Local access will be maintained during the construction. Temporary stop signs and speed bumps will be installed in several neighborhood intersections near the road closure. Non-local traffic should use Cloverdale to the east, and Locust Grove to the west to get around the closure. (see detour map)
The roadwork is part of ACHD’s Eagle Road, Lake Hazel to Amity Road project, which includes widening and signalizing the intersection of Eagle and Lake Hazel, a multi-lane roundabout at Eagle and Taconic, widening Eagle Road, and adding a multi-use pathway for bicyclists and pedestrians. The entire project is expected to be complete in November 2025.

Share June 26, 2025 on Facebook
Share June 26, 2025 on Linkedin
Email June 26, 2025 link
- Phase 1 – Eagle and Lake Hazel Intersection.
- Lake Hazel and Eagle Intersection opening July 1st in the East/West Direction.
- Conduits and pole foundations being placed. Concrete buffer being placed. Concrete paving completed until soundwall installed. Paving ongoing until June 30th.
- Phase 2 anticipated starting July 1st. Lake Hazel to Amity closed for duration of 2nd phase. Milling Starting July 1st – 3rd. Utilities will be relocating services.
Share June 20, 2025 on Facebook
Share June 20, 2025 on Linkedin
Email June 20, 2025 link
- Lake Hazel and Eagle Intersection closed
- Wall A and other miscellaneous walls ongoing
- Conduits and pole foundations being placed
- Placing road base
- Sidewalk being placed
- Concrete Paving completed until Soundwall installed
- Preparing road for asphalt
- Paving anticipated June 26th
- Phase 2 Anticipated starting first week of July
- Lake Hazel to Amity closed for duration of 2nd phase
- Lake Hazel & Eagle Intersection will be open in the East/West direction.
Share June 13, 2025 on Facebook
Share June 13, 2025 on Linkedin
Email June 13, 2025 link
- Lake Hazel and Eagle Intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving started June 2nd and will be on-going through June 18th.
- South and West legs complete.
Share June 6, 2025 on Facebook
Share June 6, 2025 on Linkedin
Email June 6, 2025 link
- Lake Hazel and Eagle Intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving June 2nd and will be on-going through June 18th.
Share May 30, 2025 on Facebook
Share May 30, 2025 on Linkedin
Email May 30, 2025 link
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving anticipated starting June 2nd – 18th.
Share May 23, 2025 on Facebook
Share May 23, 2025 on Linkedin
Email May 23, 2025 link
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving anticipated starting June 2nd – 18th.
Share May 16, 2025 on Facebook
Share May 16, 2025 on Linkedin
Email May 16, 2025 link
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
Share May 8, 2025 on Facebook
Share May 8, 2025 on Linkedin
Email May 8, 2025 link
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
Share May 2, 2025 on Facebook
Share May 2, 2025 on Linkedin
Email May 2, 2025 link
- Lake Hazel and Eagle Intersection closed.
- Walls ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk prep ongoing.