Share January 30, 2026 on Facebook
Share January 30, 2026 on Linkedin
Email January 30, 2026 link
- Eagle Road was opened to one lane in each direction on December 23rd.
- Signal at Eagle and Lake Hazel active starting January 28th.
- Sidewalk and other minor work ongoing.
Share January 23, 2026 on Facebook
Share January 23, 2026 on Linkedin
Email January 23, 2026 link
- Sidewalk and other minor work ongoing.
Share January 16, 2026 on Facebook
Share January 16, 2026 on Linkedin
Email January 16, 2026 link
- Eagle Road open to one lane in each direction on December 23rd.
- Sidewalk and other minor work ongoing.
Share January 9, 2026 on Facebook
Share January 9, 2026 on Linkedin
Email January 9, 2026 link
- Eagle Road open to one lane in each direction on December 23rd.
- Sidewalk and other minor work ongoing.
Share December 18, 2025 on Facebook
Share December 18, 2025 on Linkedin
Email December 18, 2025 link
Eagle and Lake Hazel Intersection
- Weather dependent.
- Finishing up site concrete.
- Signal poles placed.
Lake Hazel to Amity
- Lake Hazel to Amity closed for duration.
- Working on Taconic intersection.
- Concrete paving complete.
- Placing School Flashers. Placing RRFB poles.
- Pavement Markings at Taconic once concrete cure complete - Weather dependent.
Share December 11, 2025 on Facebook
Share December 11, 2025 on Linkedin
Email December 11, 2025 link
Eagle and Lake Hazel Intersection
- Signage and Pavement markings being placed - Weather dependent.
- Preparing for placement of signal poles.
- Anticipated December 17th.
Lake Hazel to Amity
- Lake Hazel to Amity closed for duration.
- Working on Taconic intersection.
- Concrete paving ongoing until December 18th.
- Placements pending weather.
Share December 4, 2025 on Facebook
Share December 4, 2025 on Linkedin
Email December 4, 2025 link
Eagle and Lake Hazel Intersection
- Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
- Concrete fence complete
- Concrete Intersection placed: Signage and Pavement markings being placed. Preparing for placement of signal poles. Anticipated December 17th. Finishing asphalt paving between Lake Hazel and Levin Dr week of November 24th.
Lake Hazel to Amity
- Lake Hazel to Amity closed for duration.
- Working on Taconic intersection.
- Placed concrete paving at all approaches of roundabout.
- Anticipated paving between Taconic and Amity week of November 10th.
- Taconic Intersection concrete placement starting November 19th – December 12th.
Share November 20, 2025 on Facebook
Share November 20, 2025 on Linkedin
Email November 20, 2025 link
- Eagle and Lake Hazel Intersection o Lake Hazel and Eagle Intersection opened July 1st in the east/west direction.
- Concrete fence complete.
- Concrete Intersection being placed: November 21st starting at 2am. November 24th starting at 3 am.
- Prepping for placement of signal poles. Anticipated December 3rd. Finishing asphalt paving between Lake Hazel and Levine week of November 24th.Lake Hazel to Amity.
- Lake Hazel to Amity closed for duration.
- Working on Taconic intersection.
- Placed concrete paving at all approaches of roundabout o Anticipated paving between Taconic and Amity week of November 10th.
- Taconic Intersection concrete placement starting November 19th.
Share November 14, 2025 on Facebook
Share November 14, 2025 on Linkedin
Email November 14, 2025 link
Eagle and Lake Hazel Intersection
- Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
- Concrete fence being placed
- Finishing up concrete
- Prepping for placement of Signal poles
Lake Hazel to Amity
- Lake Hazel to Amity closed for duration
- Working on Taconic intersection
- Placed concrete paving at all approaches of roundabout
- Anticipated paving between Taconic and Amity week of November 10th
- Taconic Intersection concrete placement starting November 19th
Share November 7, 2025 on Facebook
Share November 7, 2025 on Linkedin
Email November 7, 2025 link
Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete. Prepping for placement of Signal poles.
Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Sidewalk & curb ongoing between Taconic and Amity. Working on Taconic intersection. Placed concrete paving at all approaches of roundabout. Anticipated paving between Taconic and Amity week of November 10th .