Lake Hazel and Eagle Intersection
The Ada County Highway District (ACHD) is designing future improvements for the intersection at Lake Hazel Road and Eagle Road to improve traffic flow and increase safety for all users.
- Widen and signalize the Lake Hazel and Eagle intersection
- Add dual left-turn lanes on most approaches
- Include additional thru lanes
- Add dedicated right turn lanes on two approaches
- Install a multi-use pathway for bicyclists and pedestrians
- Include painted crosswalks
This intersection is being reconstructed with the Eagle, Lake Hazel to Amity Project, which is now scheduled to start in fall 2024. Learn more about construction on the roadway webpage.
The Ada County Highway District (ACHD) is designing future improvements for the intersection at Lake Hazel Road and Eagle Road to improve traffic flow and increase safety for all users.
- Widen and signalize the Lake Hazel and Eagle intersection
- Add dual left-turn lanes on most approaches
- Include additional thru lanes
- Add dedicated right turn lanes on two approaches
- Install a multi-use pathway for bicyclists and pedestrians
- Include painted crosswalks
This intersection is being reconstructed with the Eagle, Lake Hazel to Amity Project, which is now scheduled to start in fall 2024. Learn more about construction on the roadway webpage.
-
October 31, 2025
Share October 31, 2025 on Facebook Share October 31, 2025 on Twitter Share October 31, 2025 on Linkedin Email October 31, 2025 link- Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete. Idaho Power boring for power for intersection.
- Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Sidewalk & curb ongoing between Taconic and Amity. Working on Taconic intersection. Taconic concrete paving anticipated to start October 31st.
-
October 24, 2025
Share October 24, 2025 on Facebook Share October 24, 2025 on Twitter Share October 24, 2025 on Linkedin Email October 24, 2025 linkEagle and Lake Hazel Intersection
- Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
- Concrete fence being placed
- Finishing up concrete
- Idaho Power boring for power for intersection
Lake Hazel to Amity
- Lake Hazel to Amity closed for duration
- Sidewalk & curb ongoing between Taconic and Amity
- Working on Taconic intersection
- Starting to place base aggregate
-
October 17, 2025
Share October 17, 2025 on Facebook Share October 17, 2025 on Twitter Share October 17, 2025 on Linkedin Email October 17, 2025 linkEagle and Lake Hazel Intersection
Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete
Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Sidewalk ongoing between Taconic and Amity. Working on Taconic intersection. Starting to place base aggregate.
-
October 10, 2025
Share October 10, 2025 on Facebook Share October 10, 2025 on Twitter Share October 10, 2025 on Linkedin Email October 10, 2025 linkEagle and Lake Hazel Intersection
- Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
- Concrete fence being placed
- Finishing up concrete
Lake Hazel to Amity
- Lake Hazel to Amity closed for duration
- Utilities relocating services
- Excavation ongoing
- Storm drain ongoing
- Sidewalk ongoing between Taconic and Lake Hazel
- Working on Taconic intersection
- Starting to place base aggregate
-
October 2, 2025
Share October 2, 2025 on Facebook Share October 2, 2025 on Twitter Share October 2, 2025 on Linkedin Email October 2, 2025 linkEagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete
Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Utilities relocating services. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel. Working on Taconic intersection. Starting to place base.
-
September 26, 2025
Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 linkEagle and Lake Hazel Intersection
- Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
- Concrete fence being placed
- Finishing up concrete
Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Utilities relocating services. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel. Working on Taconic intersection.
-
September 19, 2025
Share September 19, 2025 on Facebook Share September 19, 2025 on Twitter Share September 19, 2025 on Linkedin Email September 19, 2025 linkEagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete.
Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Utilities relocating services. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel. Working on Taconic intersection.
-
September 12, 2025
Share September 12, 2025 on Facebook Share September 12, 2025 on Twitter Share September 12, 2025 on Linkedin Email September 12, 2025 linkEagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete.
Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Utilities relocating services. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel. Working on Taconic intersection.
-
September 5, 2025
Share September 5, 2025 on Facebook Share September 5, 2025 on Twitter Share September 5, 2025 on Linkedin Email September 5, 2025 link- Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
- Conduits and pole foundations placed August 12th
- Concrete buffer ongoing
- Wall starting on northwest corner in early September
- Lake Hazel to Amity closed for duration of 2nd phase
- Utilities relocating services
- Excavation ongoing
- Storm drain ongoing
- Sidewalk ongoing between Taconic and Lake Hazel
- Working on Taconic intersection
-
August 29, 2025
Share August 29, 2025 on Facebook Share August 29, 2025 on Twitter Share August 29, 2025 on Linkedin Email August 29, 2025 linkEagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction.
- Conduits and pole foundations placed August 12th.
- Concrete buffer ongoing.
- Wall starting on northwest corner in early September.
- Lake Hazel to Amity closed for duration of 2nd phase.
- Utilities relocating services.
- Excavation ongoing.
- Storm drain ongoing.
- Sidewalk ongoing between Taconic and Lake Hazel.
- Working on Taconic intersection.
Follow Project
Who's Listening
-
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org
Timeline
-
Spring 2020
Lake Hazel and Eagle Intersection has finished this stageBegin design
-
Fall 2020
Lake Hazel and Eagle Intersection has finished this stageSeek public input
-
2020
Lake Hazel and Eagle Intersection has finished this stageRefine design
-
2022-2023
Lake Hazel and Eagle Intersection has finished this stagePurchase property necessary for project
-
2024
Lake Hazel and Eagle Intersection is currently at this stageConstruction