State Street and Pierce Park Lane Intersection

Share State Street and Pierce Park Lane Intersection on Facebook Share State Street and Pierce Park Lane Intersection on Twitter Share State Street and Pierce Park Lane Intersection on Linkedin Email State Street and Pierce Park Lane Intersection link

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street
  • September 19, 2025

    Share September 19, 2025 on Facebook Share September 19, 2025 on Twitter Share September 19, 2025 on Linkedin Email September 19, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Underground electrical work is on-going.
    • Work on stormwater system is complete on the north side.
    • Contractor placing base gravels for sidewalk and roadway.
    • Concrete for sidewalk, curb, and gutter is on-going.
    • Concrete paving is anticipated to start the week of September 29th.
  • September 12, 2025

    Share September 12, 2025 on Facebook Share September 12, 2025 on Twitter Share September 12, 2025 on Linkedin Email September 12, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Underground electrical work is on-going.
    • Work on stormwater system is on-going.
    • Contractor placing base gravels for sidewalk and roadway.
    • Concrete for sidewalk, curb, and gutter is expected to start the week of September 15th.
    • Concrete paving is anticipated to start the week of September 22nd.
  • September 5, 2025

    Share September 5, 2025 on Facebook Share September 5, 2025 on Twitter Share September 5, 2025 on Linkedin Email September 5, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street.
    • Underground electrical work is on-going.
    • Work on stormwater system is on-going.
    • Contractor placing base gravels for sidewalk and roadway.
    • Concrete for sidewalk, curb, and gutter is expected to start the week of September 9th.
    • Concrete paving is anticipated to start the week of September 22nd.
  • August 29, 2025

    Share August 29, 2025 on Facebook Share August 29, 2025 on Twitter Share August 29, 2025 on Linkedin Email August 29, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone. Contractor is excavating the north side of State Street.
    • Underground electrical work is on-going.
    • Work on stormwater system is on-going.
    • Contractor placing base gravels for sidewalk and roadway.
    • Concrete for sidewalk, curb, and gutter is expected to start the week of September 9th.
    • Concrete paving is anticipated to start the week of September 22nd.
  • August 21, 2025

    Share August 21, 2025 on Facebook Share August 21, 2025 on Twitter Share August 21, 2025 on Linkedin Email August 21, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street.
    • Underground electrical work is on-going.
    • Work on stormwater system is on-going.
    • Contractor placing base gravels for sidewalk.
    • Concrete for sidewalk, curb, and gutter is expected to start the week of September 2nd.
    • Concrete paving is anticipated to start the week of September 15th.
  • August 15, 2025

    Share August 15, 2025 on Facebook Share August 15, 2025 on Twitter Share August 15, 2025 on Linkedin Email August 15, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
    • Underground electrical work is on-going.
    • Work on stormwater system is on-going.
    • Contractor starting placement of base gravels for sidewalk.
  • August 8, 2025

    Share August 8, 2025 on Facebook Share August 8, 2025 on Twitter Share August 8, 2025 on Linkedin Email August 8, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
    • Underground electrical work is on-going.
    • Work on stormwater system is on-going.
    • Contractor starting placement of base gravels for sidewalk.
  • August 1, 2025

    Share August 1, 2025 on Facebook Share August 1, 2025 on Twitter Share August 1, 2025 on Linkedin Email August 1, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
    • Underground electrical work is on-going.
    • Work on stormwater system is on-going.
    • Contractor starting placement of base gravels for sidewalk.
  • July 25, 2025

    Share July 25, 2025 on Facebook Share July 25, 2025 on Twitter Share July 25, 2025 on Linkedin Email July 25, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
    • Underground electrical work is on-going.
    • Work on stormwater system is on-going.
    • Contractor starting placement of base gravels for sidewalk.
  • July 18, 2025

    Share July 18, 2025 on Facebook Share July 18, 2025 on Twitter Share July 18, 2025 on Linkedin Email July 18, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street
    • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
    • Underground electrical work is on-going.
    • Work on stormwater system is on-going.