Victory Road and Apple Street Pedestrian Crossing

Share Victory Road and Apple Street Pedestrian Crossing on Facebook Share Victory Road and Apple Street Pedestrian Crossing on Twitter Share Victory Road and Apple Street Pedestrian Crossing on Linkedin Email Victory Road and Apple Street Pedestrian Crossing link

This project is substantially complete. 

Starting as early as June, the Ada County Highway District (ACHD) will start construction on the Victory Road and Apple Street Enhanced Pedestrian Crossing. The purpose of this project is to improve safety near Timberline High School. Construction is expected to be completed in early August of 2024.*

Project Description

  • Install a rectangular rapid flashing beacon (RRFB) at Victory Road and Apple Street
  • Add a bulb-out on the northeast corner of Apple and Victory to improve safety

*Due to high demand for contractors, labor and supplies, the construction schedules may change.

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

Starting as early as June, the Ada County Highway District (ACHD) will start construction on the Victory Road and Apple Street Enhanced Pedestrian Crossing. The purpose of this project is to improve safety near Timberline High School. Construction is expected to be completed in early August of 2024.*

Project Description

  • Install a rectangular rapid flashing beacon (RRFB) at Victory Road and Apple Street
  • Add a bulb-out on the northeast corner of Apple and Victory to improve safety

*Due to high demand for contractors, labor and supplies, the construction schedules may change.

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

This project is substantially complete. 

  • August 9, 2024

    Share August 9, 2024 on Facebook Share August 9, 2024 on Twitter Share August 9, 2024 on Linkedin Email August 9, 2024 link
    • Apple/Victory - Complete; waiting for power for the RRFB.
    • Adams and 42nd/43 - Complete.
  • August 2, 2024

    Share August 2, 2024 on Facebook Share August 2, 2024 on Twitter Share August 2, 2024 on Linkedin Email August 2, 2024 link
    • Preconstruction meeting was held May 30th.
    • Apple/Victory - Complete; waiting for power for the RRFB.
    • Adams and 42nd/43rd - Complete; waiting for power for the RRFB.
  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link
    • Preconstruction meeting was held May 30th.
    • Apple/Victory - All sidewalk placed. Asphalt paving was done July 23rd. RRFB ongoing.
    • Adams and 42nd/43rd - Curb and sidewalk complete. RRFB ongoing. Waiting for concrete to cure. Paving anticipated starting July 26th.
  • July 19, 2024

    Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link
    • Preconstruction meeting was held May 30th.
    • Apple/Victory - All sidewalk placed.
      • Sawcutting for paving on July 18th.
      • Paving anticipated the week of July 22nd.
      • RRFB ongoing.
    • 42nd/43rd - Curb and Sidewalk complete.
      • RRFB ongoing.
      • Waiting for concrete to cure.
      • Paving anticipated starting June 26th.
  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link
    • Apple/Victory - Starting June 25th.
    • 42nd/43rd - Curb being placed June 20th.
    • Pole foundation placed - Waiting for concrete to cure.
    • Paving anticipated starting June 26th.
  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link
    • Apple/Victory - Starting June 25th.
    • 42nd/43rd - Curb being placed June 20th.
    • Pole foundation placed.
    • Waiting for concrete to cure.
    • Paving anticipated starting June 26th.
  • June 21, 2024

    Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link

    Apple/Victory

    • Starting June 25th