-
Share June 2, 2023 on Facebook
Share June 2, 2023 on X (formerly Twitter)
Share June 2, 2023 on Linkedin
Email June 2, 2023 link
- IMC started May 8th at 12th and Hays - Electrical work complete.
- Concrete placements ongoing.
- Paving 12th and Hays intersection scheduled for the end of the week - June 1st and 2nd.
- Contractor expects to start on 11th (Fort to Franklin) first week of June.
- IMC started May 8th at 12th and Hays - Electrical work complete.
- Concrete placements ongoing.
- Paving 12th and Hays intersection scheduled for the end of the week - June 1st and 2nd.
- Contractor expects to start on 11th (Fort to Franklin) first week of June.
This project is substantially complete.
-
Share May 26, 2023 on Facebook
Share May 26, 2023 on X (formerly Twitter)
Share May 26, 2023 on Linkedin
Email May 26, 2023 link
- IMC started work May 8th at 12th and Hays - Electrical work ongoing.
- Concrete placement scheduled for May 25th.
- Contractor expects to start on 11th (Fort to Franklin) first week of June.
- IMC started work May 8th at 12th and Hays - Electrical work ongoing.
- Concrete placement scheduled for May 25th.
- Contractor expects to start on 11th (Fort to Franklin) first week of June.
This project is substantially complete.
-
Share May 19, 2023 on Facebook
Share May 19, 2023 on X (formerly Twitter)
Share May 19, 2023 on Linkedin
Email May 19, 2023 link
- Contractor will be back to finish work when school is let out for the summer.
- Veolia work on 11th and 12th and Hays complete.
- IMC started May 8th at 12th and Hays - working on the electrical.
- Contractor will be back to finish work when school is let out for the summer.
- Veolia work on 11th and 12th and Hays complete.
- IMC started May 8th at 12th and Hays - working on the electrical.
This project is substantially complete.
-
Share May 12, 2023 on Facebook
Share May 12, 2023 on X (formerly Twitter)
Share May 12, 2023 on Linkedin
Email May 12, 2023 link
- Contractor will be back in the summer - when school is out - to complete the section of work from Fort to Franklin.
- Veolia is at 12th and Hays - anticipated completion by the 8th.
- IMC started May 8th at 12th and Hays.
- Contractor will be back in the summer - when school is out - to complete the section of work from Fort to Franklin.
- Veolia is at 12th and Hays - anticipated completion by the 8th.
- IMC started May 8th at 12th and Hays.
This project is substantially complete.
-
Share May 5, 2023 on Facebook
Share May 5, 2023 on X (formerly Twitter)
Share May 5, 2023 on Linkedin
Email May 5, 2023 link
- Contractor will be back in the summer when school is out to complete the section of work from Fort to Franklin.
- Veolia starting at 11th and Hays to complete their work starting the 20th. Will move to 12th when complete.
- IMC starting May 8th and 11th at Hays.
- Contractor will be back in the summer when school is out to complete the section of work from Fort to Franklin.
- Veolia starting at 11th and Hays to complete their work starting the 20th. Will move to 12th when complete.
- IMC starting May 8th and 11th at Hays.
This project is substantially complete.
-
Share April 21, 2023 on Facebook
Share April 21, 2023 on X (formerly Twitter)
Share April 21, 2023 on Linkedin
Email April 21, 2023 link
- Water work will resume on 11th and 12th around the end of April.
- Contractor will be back in the summer - when school is out - to complete the section of work from Fort to Franklin.
- Veolia starting at 11th and Hays to complete their work starting the 20th. Will move to 12th when complete.
- Water work will resume on 11th and 12th around the end of April.
- Contractor will be back in the summer - when school is out - to complete the section of work from Fort to Franklin.
- Veolia starting at 11th and Hays to complete their work starting the 20th. Will move to 12th when complete.
This project is substantially complete.
-
Share April 14, 2023 on Facebook
Share April 14, 2023 on X (formerly Twitter)
Share April 14, 2023 on Linkedin
Email April 14, 2023 link
- Water work will resume on Hays between 11th and 12th around the middle of April.
- Contractor will be back in the summer to complete the work from Fort to Franklin when school is out.
- Water work will resume on Hays between 11th and 12th around the middle of April.
- Contractor will be back in the summer to complete the work from Fort to Franklin when school is out.
This project is substantially complete.
-
Share April 7, 2023 on Facebook
Share April 7, 2023 on X (formerly Twitter)
Share April 7, 2023 on Linkedin
Email April 7, 2023 link
- Water work will resume on Hays between 11th and 12th around the middle of April.
- Contractor will be back in the summer to complete the work from Fort to Franklin when school is out.
- Water work will resume on Hays between 11th and 12th around the middle of April.
- Contractor will be back in the summer to complete the work from Fort to Franklin when school is out.
This project is substantially complete.
-
Share March 31, 2023 on Facebook
Share March 31, 2023 on X (formerly Twitter)
Share March 31, 2023 on Linkedin
Email March 31, 2023 link
- Water work will resume on Hays between 11th and 12th around the middle of April.
- Contractor will be back in the summer when school is out to complete the section of work from Fort to Franklin.
- Water work will resume on Hays between 11th and 12th around the middle of April.
- Contractor will be back in the summer when school is out to complete the section of work from Fort to Franklin.
This project is substantially complete.
-
Share March 24, 2023 on Facebook
Share March 24, 2023 on X (formerly Twitter)
Share March 24, 2023 on Linkedin
Email March 24, 2023 link
- Water work will resume on Hays between 11th and 12th around the middle of April.
- Contractor will be back in the summer when school is out to complete the section of work from Fort to Franklin.
- Water work will resume on Hays between 11th and 12th around the middle of April.
- Contractor will be back in the summer when school is out to complete the section of work from Fort to Franklin.
This project is substantially complete.