- Concrete at Pueblo complete.
- Water work will resume on Hays between 11th and 12th early this year.
- Power service is complete.
- Concrete at Pueblo complete.
- Water work will resume on Hays between 11th and 12th early this year.
- Power service is complete.
This project is substantially complete.
-
Share December 29, 2022 on Facebook
Share December 29, 2022 on X (formerly Twitter)
Share December 29, 2022 on Linkedin
Email December 29, 2022 link
- Traffic signals have been set at the intersection of Fort and 11th.
- Concrete at Pueblo complete.
- Water work will resume on Hays between 11th and 12th next year.
- Traffic signals have been set at the intersection of Fort and 11th.
- Concrete at Pueblo complete.
- Water work will resume on Hays between 11th and 12th next year.
This project is substantially complete.
-
Share December 22, 2022 on Facebook
Share December 22, 2022 on X (formerly Twitter)
Share December 22, 2022 on Linkedin
Email December 22, 2022 link
- Traffic signals have been set.
- Concrete at Pueblo complete.
- Water work will resume at Hays between 11th and 12th next year.
- Power service is scheduled for December 26th at 11th and Franklin.
- Traffic signals have been set.
- Concrete at Pueblo complete.
- Water work will resume at Hays between 11th and 12th next year.
- Power service is scheduled for December 26th at 11th and Franklin.
This project is substantially complete.
-
Share December 16, 2022 on Facebook
Share December 16, 2022 on X (formerly Twitter)
Share December 16, 2022 on Linkedin
Email December 16, 2022 link
- Traffic signals have been set.
- Prep work has started for ped ramps at Pueblo - waiting on concrete.
- Water work will resume on Hays between 11th and 12th next year.
- Power service is scheduled for December 20th at 11th and Franklin.
- Traffic signals have been set.
- Prep work has started for ped ramps at Pueblo - waiting on concrete.
- Water work will resume on Hays between 11th and 12th next year.
- Power service is scheduled for December 20th at 11th and Franklin.
This project is substantially complete.
-
Share December 9, 2022 on Facebook
Share December 9, 2022 on X (formerly Twitter)
Share December 9, 2022 on Linkedin
Email December 9, 2022 link
- Traffic signals have been set.
- Prep work has started for ped ramps at Pueblo - waiting on concrete.
- Water work will resume on Hays between 11th and 12th next year.
- Power service is scheduled for December 20th at 11th and Franklin.
- Traffic signals have been set.
- Prep work has started for ped ramps at Pueblo - waiting on concrete.
- Water work will resume on Hays between 11th and 12th next year.
- Power service is scheduled for December 20th at 11th and Franklin.
This project is substantially complete.
-
Share December 2, 2022 on Facebook
Share December 2, 2022 on X (formerly Twitter)
Share December 2, 2022 on Linkedin
Email December 2, 2022 link
- Waiting on signals to be set.
- Prep work has started for ped ramps at Pueblo.
- Water work will resume on Hays between 11th and 12th.
- Waiting on signals to be set.
- Prep work has started for ped ramps at Pueblo.
- Water work will resume on Hays between 11th and 12th.
This project is substantially complete.
-
Share November 23, 2022 on Facebook
Share November 23, 2022 on X (formerly Twitter)
Share November 23, 2022 on Linkedin
Email November 23, 2022 link
- Intersection has been reopened to traffic.
- Waiting on signals to be set.
- Prep work has started for ped ramps at Pueblo.
- Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
- Intersection has been reopened to traffic.
- Waiting on signals to be set.
- Prep work has started for ped ramps at Pueblo.
- Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
This project is substantially complete.
-
Share November 18, 2022 on Facebook
Share November 18, 2022 on X (formerly Twitter)
Share November 18, 2022 on Linkedin
Email November 18, 2022 link
- The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
- Contractor started back up on October 3rd at the intersection of Fort and 11th.
- Intersection has been paved back and three of the four corners have been placed.
- Waiting on signals to be set.
- Paving mainline from Fort to O'Farrell St. - Complete.
- Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
- The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
- Contractor started back up on October 3rd at the intersection of Fort and 11th.
- Intersection has been paved back and three of the four corners have been placed.
- Waiting on signals to be set.
- Paving mainline from Fort to O'Farrell St. - Complete.
- Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
This project is substantially complete.
-
Share November 10, 2022 on Facebook
Share November 10, 2022 on X (formerly Twitter)
Share November 10, 2022 on Linkedin
Email November 10, 2022 link
- The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
- Contractor started back up on October 3rd at the intersection of Fort and 11th.
- All four corners are demoed.
- Concrete formwork set in preparation for concrete.
- Paving mainline from Fort to O'Farrell St. - November 8th.
- Water work will resume on Hays between 11th and 12th once the work on Fort is complete.
- The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
- Contractor started back up on October 3rd at the intersection of Fort and 11th.
- All four corners are demoed.
- Concrete formwork set in preparation for concrete.
- Paving mainline from Fort to O'Farrell St. - November 8th.
- Water work will resume on Hays between 11th and 12th once the work on Fort is complete.
This project is substantially complete.
-
Share November 4, 2022 on Facebook
Share November 4, 2022 on X (formerly Twitter)
Share November 4, 2022 on Linkedin
Email November 4, 2022 link
- The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
- Contractor started back up on October 3rd at the intersection of Fort and 11th.
- Concrete formwork set in preparation for concrete.
- 3 of the 4 corners have been placed.
- Paving mainline from Fort to Ofarell, Wednesday November 9th - pending weather.
- Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
- The intersection of 11th and Fort is closed for roadwork and pedestrian modifications.
- Contractor started back up on October 3rd at the intersection of Fort and 11th.
- Concrete formwork set in preparation for concrete.
- 3 of the 4 corners have been placed.
- Paving mainline from Fort to Ofarell, Wednesday November 9th - pending weather.
- Water work will resume on Hays between 11th and 12th, once the work on Fort is complete.
This project is substantially complete.