15th and 16th Street Pedestrian Crossings

Share 15th and 16th Street Pedestrian Crossings on Facebook Share 15th and 16th Street Pedestrian Crossings on Twitter Share 15th and 16th Street Pedestrian Crossings on Linkedin Email 15th and 16th Street Pedestrian Crossings link

This project is substantially complete. 

Starting as early as March, the Ada County Highway District (ACHD) will start construction on the 15th and 16th Street Pedestrian Crossings at Front Street. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is expected to be complete late summer of 2024.*

Project Description

  • Install a rectangular rapid flashing beacon (RRFB) across 15th Street at Front Street
  • Install a rectangular rapid flashing beacon (RRFB) across 16th Street at Front Street
  • Reconstruct adjacent pedestrian ramps to meet modern standards

A Rectangular Rapid Flashing Beacon (RRFB) is a type of enhanced pedestrian crossing that uses flashing signals and signage to increase pedestrian visibility.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

Starting as early as March, the Ada County Highway District (ACHD) will start construction on the 15th and 16th Street Pedestrian Crossings at Front Street. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is expected to be complete late summer of 2024.*

Project Description

  • Install a rectangular rapid flashing beacon (RRFB) across 15th Street at Front Street
  • Install a rectangular rapid flashing beacon (RRFB) across 16th Street at Front Street
  • Reconstruct adjacent pedestrian ramps to meet modern standards

A Rectangular Rapid Flashing Beacon (RRFB) is a type of enhanced pedestrian crossing that uses flashing signals and signage to increase pedestrian visibility.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

This project is substantially complete. 

  • August 9, 2024

    Share August 9, 2024 on Facebook Share August 9, 2024 on Twitter Share August 9, 2024 on Linkedin Email August 9, 2024 link
    • 15th & Front is substantially complete.
    • RRFB has been activated.
    • RRFB at 16th & Front has been activated.
    • Minor work remains, including final striping and permanent signing.
  • August 2, 2024

    Share August 2, 2024 on Facebook Share August 2, 2024 on Twitter Share August 2, 2024 on Linkedin Email August 2, 2024 link
    • 15th & Front is substantially complete. RRFB has been activated.
    • At 16th & Front, concrete work and asphalt paving is complete. Remaining work includes permanent striping, permanent signing and RRFB activation.
  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link
    • 15th & Front is substantially complete. RRFB has been activated.
    • At 16th & Front, concrete work and asphalt paving is complete.
    • Remaining work includes permanent striping and RRFB activation.
    • Front Street will be closed between 16th & 17th through the end of July.
  • July 19, 2024

    Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link
    • 15th & Front is substantially complete. RRFB has been activated.
    • Work on the east side of 16th & Front is complete.
    • Work on the west side of 16th & Front started July 9th.
    • Front Street will be closed between 16th & 17th through the end of July.
  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link
    • 15th & Front is substantially complete. RRFB has been activated. Work on the east side of 16th & Front is complete.
    • Work on the west side of 16th & Front started July 9th.
    • Front Street will be closed between 16th & 17th through the end of July.
  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link
    • 15th & Front is substantially complete.
    • RRFB has been activated.
    • Work on the east side of 16th & Front started May 29th.
    • Front Street will be closed between 15th & 16th through early July.
    • Work on the west side of 16th & Front is scheduled for July.
  • June 21, 2024

    Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link
    • 15th & Front is substantially complete. RRFB has been activated.
    • Work on the east side of 16th & Front started May 29th.
    • Front Street will be closed between 15th & 16th through the end of June.
    • Work on the west side of 16th & Front is scheduled for July.
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link
    • 15th & Front is substantially complete. RRFB has been activated.
    • Work on the east side of 16th & Front started May 29th. Front Street will be closed between 15th & 16th through the end of June.
    • Work on the west side of 16th & Front is scheduled for July.
  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link
    • 15th & Front is substantially complete. RRFB has been activated.
    • Work on the east side of 16th & Front started May 29th. Front Street will be closed between 15th & 16th through the end of June.
    • Work on the west side of 16th & Front is scheduled for July.
  • May 23, 2024

    Share May 23, 2024 on Facebook Share May 23, 2024 on Twitter Share May 23, 2024 on Linkedin Email May 23, 2024 link
    • The west side of 15th & Front Streets is complete.
    • Contractor working on the east side of 15th & Front Streets.
    • Front Street will be closed between 14th & 15th Streets through late May.
    • Work on the east side of 16th & Front is scheduled for late May through late June.
    • Work on the west side of 16th & Front is scheduled for July.
    • 16th Street will be closed the week of June 3rd for City of Boise sewer work.