2021 Residential Capital Maintenance

Share 2021 Residential Capital Maintenance on Facebook Share 2021 Residential Capital Maintenance on Twitter Share 2021 Residential Capital Maintenance on Linkedin Email 2021 Residential Capital Maintenance link

This project is substantially complete.

The Ada County Highway District will start construction on the 2021 Residential Capital Maintenance Project in early May. This pavement maintenance project primarily consists of removing and replacing all or a portion of the existing asphalt pavement (depending on the street segment). Work also includes reconstructing adjacent curb ramps to meet modern standards and minor stormwater pipe replacements in downtown Meridian. Construction is anticipated to be complete fall of 2022.

Streets to be reconstructed:

  • 2nd Street, Idaho Avenue to Carlton Avenue
  • 4th Street, Broadway Avenue to State Avenue
  • 4th Street, Washington Avenue to North End
  • 5th Avenue, State Avenue to North End
  • 5th Avenue, Franklin Road to Bower Street
  • Bower Street, 2nd Street to East End
  • State Avenue, 2nd Street to Cathy Lane
  • Washington Avenue, 4th Street to Cathy Lane

Construction impacts:

  • Temporary on-street parking impacts
  • Lane restrictions
  • Temporary closures
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • General construction noise, dust, equipment backup alarms, and ground vibration

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.


The Ada County Highway District will start construction on the 2021 Residential Capital Maintenance Project in early May. This pavement maintenance project primarily consists of removing and replacing all or a portion of the existing asphalt pavement (depending on the street segment). Work also includes reconstructing adjacent curb ramps to meet modern standards and minor stormwater pipe replacements in downtown Meridian. Construction is anticipated to be complete fall of 2022.

Streets to be reconstructed:

  • 2nd Street, Idaho Avenue to Carlton Avenue
  • 4th Street, Broadway Avenue to State Avenue
  • 4th Street, Washington Avenue to North End
  • 5th Avenue, State Avenue to North End
  • 5th Avenue, Franklin Road to Bower Street
  • Bower Street, 2nd Street to East End
  • State Avenue, 2nd Street to Cathy Lane
  • Washington Avenue, 4th Street to Cathy Lane

Construction impacts:

  • Temporary on-street parking impacts
  • Lane restrictions
  • Temporary closures
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • General construction noise, dust, equipment backup alarms, and ground vibration

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.


This project is substantially complete.

  • December 2, 2022

    Share December 2, 2022 on Facebook Share December 2, 2022 on Twitter Share December 2, 2022 on Linkedin Email December 2, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Grade work ongoing - irrigation work ongoing.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Waiting for Idaho Power to patch up their trench.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • State Avenue, 2nd Street to Cathy Lane - Irrigation work ongoing. Grade work ongoing. Paving Friday at the intersection of 2nd for the parade.
    • Washington Avenue, 4th Street to Cathy Lane - Substantially complete.
  • November 23, 2022

    Share November 23, 2022 on Facebook Share November 23, 2022 on Twitter Share November 23, 2022 on Linkedin Email November 23, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Grade work ongoing - irrigation work ongoing.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Waiting for Idaho Power to patch up their trench.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • State Avenue, 2nd Street to Cathy Lane - Irrigation work ongoing. Grade work ongoing. Concrete prep and curb started.
    • Washington Avenue, 4th Street to Cathy Lane - Substantially complete.
  • November 18, 2022

    Share November 18, 2022 on Facebook Share November 18, 2022 on Twitter Share November 18, 2022 on Linkedin Email November 18, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Grade work ongoing - irrigation work ongoing.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Landscapers on site intermittently - substantially complete.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • State Avenue, 2nd Street to Cathy Lane - Irrigation work ongoing. Grade work ongoing. Concrete prep and curb started.
    • Washington Avenue, 4th Street to Cathy Lane - Paving complete. Minor house keeping items remain.
  • November 10, 2022

    Share November 10, 2022 on Facebook Share November 10, 2022 on Twitter Share November 10, 2022 on Linkedin Email November 10, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Grade work ongoing - irrigation work ongoing.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Landscapers on site intermittently - substantially complete.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • State Avenue, 2nd Street to Cathy Lane - Irrigation work ongoing. Grade work ongoing.
    • Washington Avenue, 4th Street to Cathy Lane - Paving complete.
  • November 4, 2022

    Share November 4, 2022 on Facebook Share November 4, 2022 on Twitter Share November 4, 2022 on Linkedin Email November 4, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Grade work ongoing - concrete work ongoing.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Landscapers on site intermittently - substantially complete.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • State Avenue, 2nd Street to Cathy Lane - Irrigation work ongoing. Mainline curbing is scheduled for the week of November 7th.
    • Washington Avenue, 4th Street to Cathy Lane - Paving complete. Minor housekeeping items remain.
  • October 28, 2022

    Share October 28, 2022 on Facebook Share October 28, 2022 on Twitter Share October 28, 2022 on Linkedin Email October 28, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Grade work ongoing - irrigation work ongoing.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Landscapers on site intermittently - substantially complete.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • State Avenue, 2nd Street to Cathy Lane - Grade work ongoing. Irrigation work ongoing.
    • Washington Avenue, 4th Street to Cathy Lane - Paving complete.
  • October 21, 2022

    Share October 21, 2022 on Facebook Share October 21, 2022 on Twitter Share October 21, 2022 on Linkedin Email October 21, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Paving will be completed this week.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Landscapers on site intermittently - substantially complete.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • State Avenue, 2nd Street to Cathy Lane - Milling and grade work ongoing. Irrigation work ongoing.
    • Washington Avenue, 4th Street to Cathy Lane - Paving will be completed this week. Minor concrete work and landscaping remain.
  • October 14, 2022

    Share October 14, 2022 on Facebook Share October 14, 2022 on Twitter Share October 14, 2022 on Linkedin Email October 14, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Paving will be completed this week.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • State Avenue, 2nd Street to Cathy Lane - Milling and grade work has started.
    • Washington Avenue, 4th Street to Cathy Lane - Paving will be completed this week. Minor concrete work and landscaping remain.
  • September 30, 2022

    Share September 30, 2022 on Facebook Share September 30, 2022 on Twitter Share September 30, 2022 on Linkedin Email September 30, 2022 link
    • E. Washington Avenue, E. 4th Street to N. Cathy Ave - Road is closed. Grade work ongoing. Concrete work is expected to be complete next week.
    • 4th St. - Washington to Janie - Landscapers on site intermittently. Substantially complete.
    • E. 2nd Street, E. Idaho Ave to E. Carlton Ave - Work from Pine to Carlton ongoing.
    • E.5th Ave, E. Franklin Road to E. Bower Street - Minor concrete items remain, driveway approaches remain - waiting on landscaping.
    • E. Bower Street, N. Main Street to east end - Minor concrete items remain. Waiting on landscaping.
    • E. 5th Street, State Ave to the north end - Work substantially complete