2021 Residential Capital Maintenance

Share 2021 Residential Capital Maintenance on Facebook Share 2021 Residential Capital Maintenance on Twitter Share 2021 Residential Capital Maintenance on Linkedin Email 2021 Residential Capital Maintenance link

This project is substantially complete.

The Ada County Highway District will start construction on the 2021 Residential Capital Maintenance Project in early May. This pavement maintenance project primarily consists of removing and replacing all or a portion of the existing asphalt pavement (depending on the street segment). Work also includes reconstructing adjacent curb ramps to meet modern standards and minor stormwater pipe replacements in downtown Meridian. Construction is anticipated to be complete fall of 2022.

Streets to be reconstructed:

  • 2nd Street, Idaho Avenue to Carlton Avenue
  • 4th Street, Broadway Avenue to State Avenue
  • 4th Street, Washington Avenue to North End
  • 5th Avenue, State Avenue to North End
  • 5th Avenue, Franklin Road to Bower Street
  • Bower Street, 2nd Street to East End
  • State Avenue, 2nd Street to Cathy Lane
  • Washington Avenue, 4th Street to Cathy Lane

Construction impacts:

  • Temporary on-street parking impacts
  • Lane restrictions
  • Temporary closures
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • General construction noise, dust, equipment backup alarms, and ground vibration

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.


The Ada County Highway District will start construction on the 2021 Residential Capital Maintenance Project in early May. This pavement maintenance project primarily consists of removing and replacing all or a portion of the existing asphalt pavement (depending on the street segment). Work also includes reconstructing adjacent curb ramps to meet modern standards and minor stormwater pipe replacements in downtown Meridian. Construction is anticipated to be complete fall of 2022.

Streets to be reconstructed:

  • 2nd Street, Idaho Avenue to Carlton Avenue
  • 4th Street, Broadway Avenue to State Avenue
  • 4th Street, Washington Avenue to North End
  • 5th Avenue, State Avenue to North End
  • 5th Avenue, Franklin Road to Bower Street
  • Bower Street, 2nd Street to East End
  • State Avenue, 2nd Street to Cathy Lane
  • Washington Avenue, 4th Street to Cathy Lane

Construction impacts:

  • Temporary on-street parking impacts
  • Lane restrictions
  • Temporary closures
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • General construction noise, dust, equipment backup alarms, and ground vibration

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.


This project is substantially complete.

  • February 17, 2023

    Share February 17, 2023 on Facebook Share February 17, 2023 on Twitter Share February 17, 2023 on Linkedin Email February 17, 2023 link
    • Still minor clean up items on State Ave.
    • All temporary traffic control removed.
    • Striping to take place as soon as weather permits.
    • Preliminary punch list work ongoing.
  • February 10, 2023

    Share February 10, 2023 on Facebook Share February 10, 2023 on Twitter Share February 10, 2023 on Linkedin Email February 10, 2023 link

    State Street Avenue is the last segment for this project.

    • Concrete complete.
    • Roadway open to vehicle traffic.
    • Minor clean up items continue.
    • All temporary traffic control removed.
  • February 3, 2023

    Share February 3, 2023 on Facebook Share February 3, 2023 on Twitter Share February 3, 2023 on Linkedin Email February 3, 2023 link
    • Concrete work nearly complete.
    • Roadway opened back up to vehicle traffic.
    • Minor clean up items continue.
    • All temporary traffic control to be removed.
  • January 27, 2023

    Share January 27, 2023 on Facebook Share January 27, 2023 on Twitter Share January 27, 2023 on Linkedin Email January 27, 2023 link
    • State Avenue - Last section of work for the project.
    • Concrete nearly complete.
    • Roadway opened back up to vehicle traffic.
    • Minor clean up items continue.
  • January 20, 2023

    Share January 20, 2023 on Facebook Share January 20, 2023 on Twitter Share January 20, 2023 on Linkedin Email January 20, 2023 link
    • State Avenue - Last section of work for the project.
    • Concrete nearly complete.
    • Roadway opened back up to vehicle traffic.
    • Minor clean up items continue.
  • January 13, 2023

    Share January 13, 2023 on Facebook Share January 13, 2023 on Twitter Share January 13, 2023 on Linkedin Email January 13, 2023 link
    • State Avenue - Last section of work for the project. Concrete nearly complete. Roadway opened back up to vehicle traffic.
  • January 6, 2023

    Share January 6, 2023 on Facebook Share January 6, 2023 on Twitter Share January 6, 2023 on Linkedin Email January 6, 2023 link
    • State Ave. - Last section of work for the project
    • Concrete work nearly complete
    • Roadway opened back up to vehicle traffic
  • December 22, 2022

    Share December 22, 2022 on Facebook Share December 22, 2022 on Twitter Share December 22, 2022 on Linkedin Email December 22, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Concrete work nearly complete. Mainline paving complete.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Central Paving patched the trench for Idaho Power.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete.
    • State Avenue, 2nd Street to Cathy Lane - Substantially complete.
    • Washington Avenue, 4th Street to Cathy Lane - Substantially complete.
  • December 16, 2022

    Share December 16, 2022 on Facebook Share December 16, 2022 on Twitter Share December 16, 2022 on Linkedin Email December 16, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Grade work complete. Concrete work nearly complete. Irrigation work complete. Paving tentatively scheduled for the week of December 12th pending weather. Contractor expects to pave bottom lift December 16th and possibly top lift December 17th.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Central Paving will patch the trench for Idaho Power on the next pave date.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete.
    • State Avenue, 2nd Street to Cathy Lane - Grade work nearly complete. Concrete prep and curb ongoing. Paving complete at the intersection of 2nd for the parade. Remaining paving is tentatively scheduled for the week of December 12th - pending weather.
    • Washington Avenue, 4th Street to Cathy Lane - Substantially complete.
  • December 9, 2022

    Share December 9, 2022 on Facebook Share December 9, 2022 on Twitter Share December 9, 2022 on Linkedin Email December 9, 2022 link
    • 2nd Street, Idaho Avenue to Carlton Avenue - Grade work complete. Concrete work nearly complete. Irrigation work complete. Paving tentatively scheduled for the week of December 12th pending weather.
    • 4th Street, Broadway Avenue to State Avenue
    • 4th Street, Washington Avenue to North End - Central Paving will patch the trench for Idaho Power on the next pave date.
    • 5th Avenue, State Avenue to North End - Substantially complete.
    • 5th Avenue, Franklin Road to Bower Street - Substantially complete. Waiting on landscaping.
    • Bower Street, 2nd Street to East End - Substantially complete. Minor concrete items remain. Waiting on landscaping.
    • State Avenue, 2nd Street to Cathy Lane - Grade work nearly complete. Concrete prep and curb ongoing. Paving complete at the intersection of 2nd for the parade. Remaining paving is tentatively scheduled for the week of December 12th - pending weather.
    • Washington Avenue, 4th Street to Cathy Lane - Substantially complete.