-
Share June 5, 2026 on Facebook
Share June 5, 2026 on X (formerly Twitter)
Share June 5, 2026 on Linkedin
Email June 5, 2026 link
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling was completed June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in late June.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling was completed June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in late June.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share May 29, 2026 on Facebook
Share May 29, 2026 on X (formerly Twitter)
Share May 29, 2026 on Linkedin
Email May 29, 2026 link
- Edgewood Lane, Hill Road to Floating Feather Road
- Work began March 2 nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in mid June.
- Edgewood Lane, Hill Road to Floating Feather Road
- Work began March 2 nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in mid June.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share May 21, 2026 on Facebook
Share May 21, 2026 on X (formerly Twitter)
Share May 21, 2026 on Linkedin
Email May 21, 2026 link
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in early June.
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Milling is scheduled for June 1-2.
- Asphalt paving is scheduled for June 3-5.
- Work is anticipated to be complete in early June.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share Goldenrod Avenue Improvements Begin This June on Facebook
Share Goldenrod Avenue Improvements Begin This June on X (formerly Twitter)
Share Goldenrod Avenue Improvements Begin This June on Linkedin
Email Goldenrod Avenue Improvements Begin This June link
Starting as early as June, the Ada County Highway District (ACHD) will start construction on Goldenrod Avenue between the west end and Cloverdale Road. Construction is expected to be complete by late 2026*
Construction Impacts
- Temporary road closures
- Pedestrian detours and sidewalk closures
- On-street parking restrictions
- Lane restrictions with flaggers
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
Starting as early as June, the Ada County Highway District (ACHD) will start construction on Goldenrod Avenue between the west end and Cloverdale Road. Construction is expected to be complete by late 2026*
Construction Impacts
- Temporary road closures
- Pedestrian detours and sidewalk closures
- On-street parking restrictions
- Lane restrictions with flaggers
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share May 13, 2026 on Facebook
Share May 13, 2026 on X (formerly Twitter)
Share May 13, 2026 on Linkedin
Email May 13, 2026 link
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share May 8, 2026 on Facebook
Share May 8, 2026 on X (formerly Twitter)
Share May 8, 2026 on Linkedin
Email May 8, 2026 link
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share May 1, 2026 on Facebook
Share May 1, 2026 on X (formerly Twitter)
Share May 1, 2026 on Linkedin
Email May 1, 2026 link
- Work began March 2nd.
- Edgewood lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
- Work began March 2nd.
- Edgewood lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share April 24, 2026 on Facebook
Share April 24, 2026 on X (formerly Twitter)
Share April 24, 2026 on Linkedin
Email April 24, 2026 link
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share April 16, 2026 on Facebook
Share April 16, 2026 on X (formerly Twitter)
Share April 16, 2026 on Linkedin
Email April 16, 2026 link
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
- Work began March 2nd.
- Edgewood Lane will be closed during construction.
- Contractor is currently working on sidewalk improvements.
- Work is anticipated to be complete by the end of May.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.
-
Share April 10, 2026 on Facebook
Share April 10, 2026 on X (formerly Twitter)
Share April 10, 2026 on Linkedin
Email April 10, 2026 link
▪ Edgewood Lane will be closed during construction.
▪ Contractor is currently working on sidewalk improvements.
▪ Work is anticipated to be complete by the end of May.
▪ Edgewood Lane will be closed during construction.
▪ Contractor is currently working on sidewalk improvements.
▪ Work is anticipated to be complete by the end of May.
Project is substantially complete.
Follow Allumbaugh Street construction updates here.