Shoreline Dr, Americana Blvd to Fairview Ave
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
Shoreline Dr, Americana Blvd to Fairview Ave
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
Share October 9, 2026 on Facebook
Share October 9, 2026 on X (formerly Twitter)
Share October 9, 2026 on Linkedin
Email October 9, 2026 link
Shoreline Dr, Americana Blvd to Fairview Ave
- The signal at Americana & Shoreline was activated Wednesday night, September 23rd.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
Shoreline Dr, Americana Blvd to Fairview Ave
- The signal at Americana & Shoreline was activated Wednesday night, September 23rd.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
Share October 2, 2026 on Facebook
Share October 2, 2026 on X (formerly Twitter)
Share October 2, 2026 on Linkedin
Email October 2, 2026 link
Shoreline Dr, Americana Blvd to Fairview Ave
- The signal at Americana & Shoreline was activated Wednesday night, September 23rd.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
Shoreline Dr, Americana Blvd to Fairview Ave
- The signal at Americana & Shoreline was activated Wednesday night, September 23rd.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
Share September 24, 2026 on Facebook
Share September 24, 2026 on X (formerly Twitter)
Share September 24, 2026 on Linkedin
Email September 24, 2026 link
Shoreline Dr, Americana Blvd to Fairview Ave
- The signal at Americana & Shoreline was activated Wednesday night, September 23rd.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
Shoreline Dr, Americana Blvd to Fairview Ave
- The signal at Americana & Shoreline was activated Wednesday night, September 23rd.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
Share September 17, 2026 - Eisenman - Substantially Complete on Facebook
Share September 17, 2026 - Eisenman - Substantially Complete on X (formerly Twitter)
Share September 17, 2026 - Eisenman - Substantially Complete on Linkedin
Email September 17, 2026 - Eisenman - Substantially Complete link
Eisenman Rd, Gowen Rd to 2000’ South - Substantially complete.
Eisenman Rd, Freight St to I-84 - Substantially complete.
Eisenman Rd, Gowen Rd to 2000’ South - Substantially complete.
Eisenman Rd, Freight St to I-84 - Substantially complete.
Share September 17, 2026 - Shoreline/Americana on Facebook
Share September 17, 2026 - Shoreline/Americana on X (formerly Twitter)
Share September 17, 2026 - Shoreline/Americana on Linkedin
Email September 17, 2026 - Shoreline/Americana link
- Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
- Signal activation is scheduled for Wednesday night, September 23rd.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
- The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
- The east leg of Shoreline was closed August 24th for the signal work.
- Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
- Signal activation is scheduled for Wednesday night, September 23rd.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
- The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
- The east leg of Shoreline was closed August 24th for the signal work.
Share September 11, 2026 - Eisenman on Facebook
Share September 11, 2026 - Eisenman on X (formerly Twitter)
Share September 11, 2026 - Eisenman on Linkedin
Email September 11, 2026 - Eisenman link
Eisenman Rd, Gowen Rd to 2000’ South
- Milling and paving is complete.
- Veolia’s work to replace the water line is complete.
Eisenman Rd, Freight St to I-84
- Work is started August 24th.
- Eisenman Road will remain open for the work.
- Milling and paving on the segment from Freight Street to the truck stop is complete.
- Mill and paving from the truck stop to I-84 was completed September 11th.c
- Minor work remains, including manhole adjustments and striping.
Eisenman Rd, Gowen Rd to 2000’ South
- Milling and paving is complete.
- Veolia’s work to replace the water line is complete.
Eisenman Rd, Freight St to I-84
- Work is started August 24th.
- Eisenman Road will remain open for the work.
- Milling and paving on the segment from Freight Street to the truck stop is complete.
- Mill and paving from the truck stop to I-84 was completed September 11th.c
- Minor work remains, including manhole adjustments and striping.
Share September 11, 2026 - Americana on Facebook
Share September 11, 2026 - Americana on X (formerly Twitter)
Share September 11, 2026 - Americana on Linkedin
Email September 11, 2026 - Americana link
- Shoreline Dr, Americana Blvd to Fairview Ave
- Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
- The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
- The east leg of Shoreline was closed August 24th for the signal work.
- Shoreline Dr, Americana Blvd to Fairview Ave
- Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
- The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
- The east leg of Shoreline was closed August 24th for the signal work.
Share September 3, 2026 - Eisenman on Facebook
Share September 3, 2026 - Eisenman on X (formerly Twitter)
Share September 3, 2026 - Eisenman on Linkedin
Email September 3, 2026 - Eisenman link
- Eisenman Rd, Gowen Rd to 2000’ South - Milling and paving is complete. Minor work remains – striping, manhole adjustments, concrete sidewalk, etc. Veolia’s work to replace the water line is complete.
- Eisenman Rd, Freight St to I-84 - Work is started August 24th. Eisenman Road will remain open for the work. Milling and paving on the segment from Freight Street to the truck stop is complete. Mill and paving from the truck stop to I-84 will continue on September 9th. Work impacting I-84 will be done at night.
- Eisenman Rd, Gowen Rd to 2000’ South - Milling and paving is complete. Minor work remains – striping, manhole adjustments, concrete sidewalk, etc. Veolia’s work to replace the water line is complete.
- Eisenman Rd, Freight St to I-84 - Work is started August 24th. Eisenman Road will remain open for the work. Milling and paving on the segment from Freight Street to the truck stop is complete. Mill and paving from the truck stop to I-84 will continue on September 9th. Work impacting I-84 will be done at night.
Share September 3, 2026 on Facebook
Share September 3, 2026 on X (formerly Twitter)
Share September 3, 2026 on Linkedin
Email September 3, 2026 link
- Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
- The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
- The east leg of Shoreline was closed August 24th for the signal work.
- Signal work at Americana & Shoreline began August 24th and will take 3-4 weeks to complete.
- Signal work at Americana & Ann Morrison Park/Kathryn Albertson Park is expected to resume in November after remaining signal materials are delivered.
- Concrete sidewalk improvements are complete until signal materials arrive.
- Milling, paving, and striping are complete.
- The west leg of Shoreline will remain open to right-in and right-out only traffic and will remain in this configuration until the new traffic signal is complete.
- The east leg of Shoreline was closed August 24th for the signal work.