Floating Feather Emergency Infrastructure Repair

Share Floating Feather Emergency Infrastructure Repair on Facebook Share Floating Feather Emergency Infrastructure Repair on Twitter Share Floating Feather Emergency Infrastructure Repair on Linkedin Email Floating Feather Emergency Infrastructure Repair link

This emergency repair is substantially complete.


Floating Feather Road between Ballantyne Lane and Eagle Road has reopened to vehicles, pedestrians, and bicyclists following the completion of emergency infrastructure repairs.

The sinkhole formed beneath the westbound lane on July 30th, with a surface opening approximately three feet in diameter. Below the pavement, the underground void extends about seven feet horizontally. Veolia initially performed temporary patching over the opening, and flaggers routed traffic into the eastbound lanes during the early assessment. After further evaluation, a full closure was determined to be necessary to immediately begin the extensive work required for long-term repairs.

Veolia crews completed the repairs quickly and safely allowing the road to fully reopen in time for the start of the school year. ACHD extends a big thank you to Veolia for their tireless efforts, including weekend work, to reopen the road before school was back in session.

Commuters should note that another section of Floating Feather Road, between Palmer Lane and Linder Road, will be closed next week for planned underground utility work unrelated to the emergency repairs near Eagle Road. Drivers, bicyclists, and pedestrians are encouraged to follow posted detours and plan alternate routes.


Floating Feather Road between Ballantyne Lane and Eagle Road has reopened to vehicles, pedestrians, and bicyclists following the completion of emergency infrastructure repairs.

The sinkhole formed beneath the westbound lane on July 30th, with a surface opening approximately three feet in diameter. Below the pavement, the underground void extends about seven feet horizontally. Veolia initially performed temporary patching over the opening, and flaggers routed traffic into the eastbound lanes during the early assessment. After further evaluation, a full closure was determined to be necessary to immediately begin the extensive work required for long-term repairs.

Veolia crews completed the repairs quickly and safely allowing the road to fully reopen in time for the start of the school year. ACHD extends a big thank you to Veolia for their tireless efforts, including weekend work, to reopen the road before school was back in session.

Commuters should note that another section of Floating Feather Road, between Palmer Lane and Linder Road, will be closed next week for planned underground utility work unrelated to the emergency repairs near Eagle Road. Drivers, bicyclists, and pedestrians are encouraged to follow posted detours and plan alternate routes.

This emergency repair is substantially complete.

  • Floating Feather Road Reopens Following Emergency Repairs

    Share Floating Feather Road Reopens Following Emergency Repairs on Facebook Share Floating Feather Road Reopens Following Emergency Repairs on Twitter Share Floating Feather Road Reopens Following Emergency Repairs on Linkedin Email Floating Feather Road Reopens Following Emergency Repairs link

    EAGLE — Floating Feather Road between Ballantyne Lane and Eagle Road has reopened to vehicles, pedestrians, and bicyclists following the completion of emergency infrastructure repairs.

    The road was closed July 31 after a sinkhole was discovered in the westbound lane. Veolia crews completed the repairs quickly and safely allowing the road to fully reopen in time for the start of the school year.

    ACHD extends a big thank you to Veolia crews for their tireless efforts, including weekend work, to reopen the road before school is back in session.

    Commuters should note that another section of Floating Feather Road, between Palmer Lane and Linder Road, will be closed next week for planned underground utility work unrelated to the emergency repairs near Eagle Road. Drivers, bicyclists, and pedestrians are encouraged to follow posted detours and plan alternate routes.

  • Repair Update - August 11, 2025

    Share Repair Update - August 11, 2025 on Facebook Share Repair Update - August 11, 2025 on Twitter Share Repair Update - August 11, 2025 on Linkedin Email Repair Update - August 11, 2025 link

    Veolia crews and contractors worked through the weekend and have continued to make great progress. The water main repairs are completed and the excavation has been backfilled. Water quality samples came back exactly where we expected – all clear – and customers remain in water service. Roadway paving and striping took place on Monday and Veolia will work on sidewalk repairs on Tuesday (8/12) morning. The road is expected to reopen on Tuesday (8/12) afternoon.


    Water main repairs completed and excavation backfilled.



  • Repair Update - August 8, 2025

    Share Repair Update - August 8, 2025 on Facebook Share Repair Update - August 8, 2025 on Twitter Share Repair Update - August 8, 2025 on Linkedin Email Repair Update - August 8, 2025 link
    Veolia crews and contractors have made great progress over the last week. The water main was excavated and exposed, over 25 feet below the roadway surface. Safety shoring of the hole walls was installed to ensure our work crews could work safely and effectively. A 20-foot section of the broken 16-inch water main was removed and a new piece installed. The installation was complex and required extensive planning across multiple departments within Veolia and in partnership with ACHD.

    The infrastructure work continues through this weekend, to shore up and backfill the large hole, and then replace the roadway. Veolia appreciates the patience of our customers and the community with the detour and the extensive repairs that were critically necessary.


    Image 1
    Excavated pipe illustrating over 25 foot depth of casing under Dry Creek bridge.
    Image 2
    16-inch diameter broken water transmission, 20 foot long section split in half.
    Image 3
    Excavating roadway to dig down and access broken water main.
  • Emergency Closure - July 31

    Share Emergency Closure - July 31 on Facebook Share Emergency Closure - July 31 on Twitter Share Emergency Closure - July 31 on Linkedin Email Emergency Closure - July 31 link
    Following an evaluation of road conditions after discovering a sinkhole, Veolia has implemented a full closure of Floating Feather Road between Eagle Road and Ballantyne Lane to further investigate the cause and begin permanent repairs.

    The sinkhole formed beneath the westbound lane on July 30th, with a surface opening approximately three feet in diameter. Below the pavement, the underground void extends about seven feet horizontally. Veolia initially performed temporary patching over the opening, and flaggers routed traffic into the eastbound lanes during the early assessment. After further evaluation, a full closure was determined to be necessary to immediately begin the extensive work required for long-term repairs.


    The duration of the closure is currently unknown. A timeline will be provided once the full extent of subsurface damage is determined. Every effort will be made to reopen the roadway before the start of the school year.


    Veolia is coordinating closely with the Ada County Highway District throughout the repair and restoration process. ACHD will continue to monitor the condition of the roadway and support detour management. Traffic impacts and project updates will be shared as new information becomes available.


    The closure applies to all vehicle, bicycle, and pedestrian traffic. Commuters should use either Ballantyne Lane or Eagle Road up to Beacon Light Road (please see the posted detour map). Local access will be maintained for residents.