Share July 9, 2026 on Facebook
Share July 9, 2026 on X (formerly Twitter)
Share July 9, 2026 on Linkedin
Email July 9, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base:
- N Miner Ave.
- W. Mendi Pl.
- 2nd Street
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling complete.
- Locations actively working on excavation and preparation of base:
- N Miner Ave.
- W. Mendi Pl.
- 2nd Street
Share July 1, 2026 on Facebook
Share July 1, 2026 on X (formerly Twitter)
Share July 1, 2026 on Linkedin
Email July 1, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling is expected to start again next week. Locations: N Miner Ave and W. Mendi Pl.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Milling is expected to start again next week. Locations: N Miner Ave and W. Mendi Pl.
Share June 26, 2026 on Facebook
Share June 26, 2026 on X (formerly Twitter)
Share June 26, 2026 on Linkedin
Email June 26, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
Share June 18, 2026 on Facebook
Share June 18, 2026 on X (formerly Twitter)
Share June 18, 2026 on Linkedin
Email June 18, 2026 link
- Road closures continue this week for the milling and paving operations.
- June 18 - Strike Way
- June 19 - Gold Street
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Road closures continue this week for the milling and paving operations.
- June 18 - Strike Way
- June 19 - Gold Street
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
Share June 12, 2026 on Facebook
Share June 12, 2026 on X (formerly Twitter)
Share June 12, 2026 on Linkedin
Email June 12, 2026 link
- Road closures have started this week for the milling and paving operations.
- Paving June 15 and 16 - Shady Grove Way
- Paving June 17 - Kacie Way
- Paving June 18 - Strike Way
- Paving June 19 - Gold Street
- Road closures have started this week for the milling and paving operations.
- Paving June 15 and 16 - Shady Grove Way
- Paving June 17 - Kacie Way
- Paving June 18 - Strike Way
- Paving June 19 - Gold Street
Share June 5, 2026 on Facebook
Share June 5, 2026 on X (formerly Twitter)
Share June 5, 2026 on Linkedin
Email June 5, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Road closures are expected to start next week for the milling and paving operations.
- June 8 - Shandy Grove Way and E. Boise Street
- June 9 - Shady Grove Way and E. Boise Street
- June 10 - Katie Way
- June 11 - Strike Way and W. Gold Street
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Road closures are expected to start next week for the milling and paving operations.
- June 8 - Shandy Grove Way and E. Boise Street
- June 9 - Shady Grove Way and E. Boise Street
- June 10 - Katie Way
- June 11 - Strike Way and W. Gold Street
Share May 29, 2026 on Facebook
Share May 29, 2026 on X (formerly Twitter)
Share May 29, 2026 on Linkedin
Email May 29, 2026 link
- No road closures have been implemented yet.
- Contractor has started saw cutting and demo at the northwest and northeast project improvement areas.
- Work does not include road or intersection closures yet.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- No road closures have been implemented yet.
- Contractor has started saw cutting and demo at the northwest and northeast project improvement areas.
- Work does not include road or intersection closures yet.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
Share May 21, 2026 on Facebook
Share May 21, 2026 on X (formerly Twitter)
Share May 21, 2026 on Linkedin
Email May 21, 2026 link
- No road closures have been implemented yet.
- Contractor has started saw cutting and demo at the northwest and northeast project improvement areas.
- Work does not include road or intersection closures yet.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest quadrant.
- No road closures have been implemented yet.
- Contractor has started saw cutting and demo at the northwest and northeast project improvement areas.
- Work does not include road or intersection closures yet.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest quadrant.
Share May 13, 2026 on Facebook
Share May 13, 2026 on X (formerly Twitter)
Share May 13, 2026 on Linkedin
Email May 13, 2026 link
- Project includes work in multiple residential neighborhoods in Kuna.
- No road closures have been implemented yet.
- Contractor has started saw cutting and demo at the northwest project improvement area.
- Work does not include road or intersection closures yet.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest quadrant.
- Project includes work in multiple residential neighborhoods in Kuna.
- No road closures have been implemented yet.
- Contractor has started saw cutting and demo at the northwest project improvement area.
- Work does not include road or intersection closures yet.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest quadrant.
Share May 8, 2026 on Facebook
Share May 8, 2026 on X (formerly Twitter)
Share May 8, 2026 on Linkedin
Email May 8, 2026 link
- Project includes work in multiple residential neighborhoods in Kuna.
- No road closures have been implemented yet.
- Contractor has started saw cutting and demo at the northwest project improvement area.
- Work does not include road or intersection closures yet.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest quadrant.
- Project includes work in multiple residential neighborhoods in Kuna.
- No road closures have been implemented yet.
- Contractor has started saw cutting and demo at the northwest project improvement area.
- Work does not include road or intersection closures yet.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest quadrant.