- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is complete.
- Concrete placements throughout the southwest portion of the project are ongoing.
- Contractor continues to excavate and import material for the permeable asphalt section on Ashwood. Anticipate paving on Friday, October 9th.
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is complete.
- Concrete placements throughout the southwest portion of the project are ongoing.
- Contractor continues to excavate and import material for the permeable asphalt section on Ashwood. Anticipate paving on Friday, October 9th.
This project is substantially complete.
Share October 2, 2026 on Facebook
Share October 2, 2026 on X (formerly Twitter)
Share October 2, 2026 on Linkedin
Email October 2, 2026 link
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations has been completed.
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is ongoing.
- Concrete placements throughout the southwest portion of the project are ongoing.
- Contractor continues to excavate and import material for the permeable asphalt section on Ashwood. Anticipate paving next week.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations has been completed.
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is ongoing.
- Concrete placements throughout the southwest portion of the project are ongoing.
- Contractor continues to excavate and import material for the permeable asphalt section on Ashwood. Anticipate paving next week.
This project is substantially complete.
Share September 24, 2026 on Facebook
Share September 24, 2026 on X (formerly Twitter)
Share September 24, 2026 on Linkedin
Email September 24, 2026 link
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations has been completed.
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is ongoing.
- Concrete placements throughout the southwest portion of the project are ongoing.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations has been completed.
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is ongoing.
- Concrete placements throughout the southwest portion of the project are ongoing.
This project is substantially complete.
Share September 17, 2026 on Facebook
Share September 17, 2026 on X (formerly Twitter)
Share September 17, 2026 on Linkedin
Email September 17, 2026 link
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is ongoing.
- Concrete placements throughout the southwest portion of the project are ongoing.
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is ongoing.
- Concrete placements throughout the southwest portion of the project are ongoing.
This project is substantially complete.
Share September 11, 2026 on Facebook
Share September 11, 2026 on X (formerly Twitter)
Share September 11, 2026 on Linkedin
Email September 11, 2026 link
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is ongoing.
- Concrete placements throughout the southwest portion of the project are ongoing.
- Asphalt milling/demo is complete at the remaining project locations.
- Excavation and grade prep on the southwest portion of the project is ongoing.
- Concrete placements throughout the southwest portion of the project are ongoing.
This project is substantially complete.
Share September 3, 2026 on Facebook
Share September 3, 2026 on X (formerly Twitter)
Share September 3, 2026 on Linkedin
Email September 3, 2026 link
- Paving at various project locations has been completed.
- Asphalt milling/demo is complete at the remaining project locations.
- Contractor has started excavation and grade prep on the SW portion of the project.
- Paving at various project locations has been completed.
- Asphalt milling/demo is complete at the remaining project locations.
- Contractor has started excavation and grade prep on the SW portion of the project.
This project is substantially complete.
Share August 28, 2026 on Facebook
Share August 28, 2026 on X (formerly Twitter)
Share August 28, 2026 on Linkedin
Email August 28, 2026 link
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations was completed this week.
- Asphalt milling/demo is scheduled for next week at the remaining project locations.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations was completed this week.
- Asphalt milling/demo is scheduled for next week at the remaining project locations.
This project is substantially complete.
Share August 20, 2026 on Facebook
Share August 20, 2026 on X (formerly Twitter)
Share August 20, 2026 on Linkedin
Email August 20, 2026 link
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations is scheduled for the end of August.
- Concrete work along 2nd Street is on-going.
- Anticipate paving 2nd Street by the end of August.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations is scheduled for the end of August.
- Concrete work along 2nd Street is on-going.
- Anticipate paving 2nd Street by the end of August.
This project is substantially complete.
Share August 14, 2026 on Facebook
Share August 14, 2026 on X (formerly Twitter)
Share August 14, 2026 on Linkedin
Email August 14, 2026 link
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations is scheduled for the end of August.
- Concrete work along 2nd Street has started this week in anticipation of paving by the end of August.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations is scheduled for the end of August.
- Concrete work along 2nd Street has started this week in anticipation of paving by the end of August.
This project is substantially complete.
Share August 7, 2026 on Facebook
Share August 7, 2026 on X (formerly Twitter)
Share August 7, 2026 on Linkedin
Email August 7, 2026 link
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations this week.
- Concrete work along 2nd Street has started this week in anticipation for paving, possibly next week.
- Contractor has placed new sidewalk/ped ramps at various locations around the northwest and northeast quadrants.
- Contactor has completed the milling and paving at select streets around the project.
- Demo and placement of new sidewalk curb and gutter continues at various locations.
- Paving at various project locations this week.
- Concrete work along 2nd Street has started this week in anticipation for paving, possibly next week.
This project is substantially complete.