Lake Hazel and Eagle Intersection

Share Lake Hazel and Eagle Intersection on Facebook Share Lake Hazel and Eagle Intersection on Twitter Share Lake Hazel and Eagle Intersection on Linkedin Email Lake Hazel and Eagle Intersection link

The Ada County Highway District (ACHD) is designing future improvements for the intersection at Lake Hazel Road and Eagle Road to improve traffic flow and increase safety for all users.

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks

This intersection is being reconstructed with the Eagle, Lake Hazel to Amity Project, which is now scheduled to start in fall 2024. Learn more about construction on the roadway webpage.


The Ada County Highway District (ACHD) is designing future improvements for the intersection at Lake Hazel Road and Eagle Road to improve traffic flow and increase safety for all users.

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks

This intersection is being reconstructed with the Eagle, Lake Hazel to Amity Project, which is now scheduled to start in fall 2024. Learn more about construction on the roadway webpage.


  • September 19, 2025

    Share September 19, 2025 on Facebook Share September 19, 2025 on Twitter Share September 19, 2025 on Linkedin Email September 19, 2025 link

    Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete.

    Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Utilities relocating services. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel. Working on Taconic intersection.

  • September 12, 2025

    Share September 12, 2025 on Facebook Share September 12, 2025 on Twitter Share September 12, 2025 on Linkedin Email September 12, 2025 link

    Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Concrete fence being placed. Finishing up concrete.

    Lake Hazel to Amity - Lake Hazel to Amity closed for duration. Utilities relocating services. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel. Working on Taconic intersection.

  • September 5, 2025

    Share September 5, 2025 on Facebook Share September 5, 2025 on Twitter Share September 5, 2025 on Linkedin Email September 5, 2025 link
    • Lake Hazel and Eagle Intersection opened July 1st in the east/west direction
    • Conduits and pole foundations placed August 12th
    • Concrete buffer ongoing
    • Wall starting on northwest corner in early September
    • Lake Hazel to Amity closed for duration of 2nd phase
    • Utilities relocating services
    • Excavation ongoing
    • Storm drain ongoing
    • Sidewalk ongoing between Taconic and Lake Hazel
    • Working on Taconic intersection
  • August 29, 2025

    Share August 29, 2025 on Facebook Share August 29, 2025 on Twitter Share August 29, 2025 on Linkedin Email August 29, 2025 link

    Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction.

    • Conduits and pole foundations placed August 12th.
    • Concrete buffer ongoing.
    • Wall starting on northwest corner in early September.
    • Lake Hazel to Amity closed for duration of 2nd phase.
    • Utilities relocating services.
    • Excavation ongoing.
    • Storm drain ongoing.
    • Sidewalk ongoing between Taconic and Lake Hazel.
    • Working on Taconic intersection.
  • August 21, 2025

    Share August 21, 2025 on Facebook Share August 21, 2025 on Twitter Share August 21, 2025 on Linkedin Email August 21, 2025 link

    Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Conduits and pole foundations placed August 12th. Concrete buffer ongoing. Wall starting on northwest corner in early September. Lake Hazel to Amity closed for duration of 2nd phase. Utilities relocating services. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel.

  • August 15, 2025

    Share August 15, 2025 on Facebook Share August 15, 2025 on Twitter Share August 15, 2025 on Linkedin Email August 15, 2025 link

    Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Conduits and pole foundations placed 8/12. Concrete buffer ongoing. Wall starting on northwest corner as early as August 11th.

    Lake Hazel to Amity closed for duration of 2nd phase. Milling complete. Utilities relocating services. Removal ongoing. Excavation ongoing. Storm drain ongoing. Sidewalk ongoing between Taconic and Lake Hazel. Concrete fence foundations anticipated starting 8/18.

  • August 8, 2025

    Share August 8, 2025 on Facebook Share August 8, 2025 on Twitter Share August 8, 2025 on Linkedin Email August 8, 2025 link

    Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opened July 1st in the east/west direction. Conduits and pole foundations ongoing. Concrete buffer being placed. Wall starting on northwest corner as early as August 11th.

    Lake Hazel to Amity closed for duration of 2nd phase - Milling complete. Utilities relocating services. Removal ongoing. Excavation ongoing. Storm drain ongoing.

  • June 26, 2025

    Share June 26, 2025 on Facebook Share June 26, 2025 on Twitter Share June 26, 2025 on Linkedin Email June 26, 2025 link
    • Eagle and Lake Hazel Intersection - Lake Hazel and Eagle Intersection opening July 1st in the East/West Direction.
    • Conduits and pole foundations being placed.
    • Concrete buffer being placed.
    • Concrete paving completed until soundwall installed.
    • Paving ongoing until June 30th.
    • Phase 2 anticipated starting July 1st - Lake Hazel to Amity closed for duration of 2nd phase o Milling Starting July 1st – 3rd.
    • Utilities will be relocating services.
  • December 6, 2024

    Share December 6, 2024 on Facebook Share December 6, 2024 on Twitter Share December 6, 2024 on Linkedin Email December 6, 2024 link
    • Lake Hazel and Eagle Intersection closed.
    • Cut and fill ongoing at Lake Hazel intersection.
    • Wall excavation ongoing.
    • Wall blocks ongoing.
    • City of Meridian water ongoing.
    • Irrigation will start after City of Meridian water is complete.
  • August 23, 2024

    Share August 23, 2024 on Facebook Share August 23, 2024 on Twitter Share August 23, 2024 on Linkedin Email August 23, 2024 link

    Anticipated notice to proceed is mid-September.