Resseguie | Fort | 15th St: Pavement Preservation & ADA Project

Share Resseguie | Fort | 15th St: Pavement Preservation & ADA Project on Facebook Share Resseguie | Fort | 15th St: Pavement Preservation & ADA Project on Twitter Share Resseguie | Fort | 15th St: Pavement Preservation & ADA Project on Linkedin Email Resseguie | Fort | 15th St: Pavement Preservation & ADA Project link

The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.

  • Resseguie St., 9th to 16th streets,
  • Fort St., 16th St. to 15th St.
  • 15th St., Fort St. to Resseguie St.

Project Description

  • Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
  • Replace select sections of curb where trees will not be impacted.
  • Install pedestrian ramps as needed to improve accessibility.
  • Retain historic curb stamps wherever feasible.

*Schedule subject to change.

The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.

  • Resseguie St., 9th to 16th streets,
  • Fort St., 16th St. to 15th St.
  • 15th St., Fort St. to Resseguie St.

Project Description

  • Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
  • Replace select sections of curb where trees will not be impacted.
  • Install pedestrian ramps as needed to improve accessibility.
  • Retain historic curb stamps wherever feasible.

*Schedule subject to change.

  • Completion date extended

    24 Jul 2025
    Share Completion date extended on Facebook Share Completion date extended on Twitter Share Completion date extended on Linkedin Email Completion date extended link

    Originally scheduled for completion in late fall 2025, the project is now expected to be complete in spring 2026 due to utility work.

    Please note that in an effort to keep a paved surface during the winter months, the bulk of the work will pause during winter since the pavement plants will be closed. Concrete work, such as sidewalk work, will continue.

  • July 18, 2025

    18 Jul 2025
    Share July 18, 2025 on Facebook Share July 18, 2025 on Twitter Share July 18, 2025 on Linkedin Email July 18, 2025 link

    Construction is anticipated to begin mid-August.

    Project includes work on the following segments:

    • Resseguie Street, 16th Street to 9th Street
    • Fort Street, 16th Street to 15th Street
    • 15th Street, Fort Street to Resseguie Street
  • Pavement work to start as early as mid-August

    02 Jun 2025
    Share Pavement work to start as early as mid-August on Facebook Share Pavement work to start as early as mid-August on Twitter Share Pavement work to start as early as mid-August on Linkedin Email Pavement work to start as early as mid-August link

    Construction will start as early as mid-August 2025* and is expected to be complete in spring 2026. Neighbors can expect the following impacts:

    • Temporary street closures
    • Restricted on-street parking
    • Lane restrictions with flaggers
    • Pedestrians and bike route detours
    • General construction noise, including equipment backup alarms, dust and ground vibration.
    • Access to homes and businesses will stay open, and the contractor will work with residents and business owners to keep entrances clear or provide alternate accesses.


    Thank you for your patience as we work to improve pavement and accessibility conditions on these streets.