Resseguie | Fort | 15th St: Pavement Preservation & ADA Project
The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.
- Resseguie St., 9th to 16th streets,
- Fort St., 16th St. to 15th St.
- 15th St., Fort St. to Resseguie St.
Project Description
- Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
- Replace select sections of curb where trees will not be impacted.
- Install pedestrian ramps as needed to improve accessibility.
- Retain historic curb stamps wherever feasible.
*Schedule subject to change.
The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.
- Resseguie St., 9th to 16th streets,
- Fort St., 16th St. to 15th St.
- 15th St., Fort St. to Resseguie St.
Project Description
- Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
- Replace select sections of curb where trees will not be impacted.
- Install pedestrian ramps as needed to improve accessibility.
- Retain historic curb stamps wherever feasible.
*Schedule subject to change.
-
February 12, 2026
Share February 12, 2026 on Facebook Share February 12, 2026 on Twitter Share February 12, 2026 on Linkedin Email February 12, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
February 5, 2026
Share February 5, 2026 on Facebook Share February 5, 2026 on Twitter Share February 5, 2026 on Linkedin Email February 5, 2026 linkNo change to the project timeline.
-
January 30, 2026
Share January 30, 2026 on Facebook Share January 30, 2026 on Twitter Share January 30, 2026 on Linkedin Email January 30, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
January 16, 2026
Share January 16, 2026 on Facebook Share January 16, 2026 on Twitter Share January 16, 2026 on Linkedin Email January 16, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
January 9, 2026
Share January 9, 2026 on Facebook Share January 9, 2026 on Twitter Share January 9, 2026 on Linkedin Email January 9, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
December 18, 2025
Share December 18, 2025 on Facebook Share December 18, 2025 on Twitter Share December 18, 2025 on Linkedin Email December 18, 2025 linkProject includes work on the following segments:
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
December 11, 2025
Share December 11, 2025 on Facebook Share December 11, 2025 on Twitter Share December 11, 2025 on Linkedin Email December 11, 2025 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring
-
December 4, 2025
Share December 4, 2025 on Facebook Share December 4, 2025 on Twitter Share December 4, 2025 on Linkedin Email December 4, 2025 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
November 20, 2025
Share November 20, 2025 on Facebook Share November 20, 2025 on Twitter Share November 20, 2025 on Linkedin Email November 20, 2025 link- Resseguie Street, 16th Street to 9th Street
- PROJECT WORK: Resseguie Street will be closed from 13th Street to 15th Street on November 18th – November 26th for pipe replacement work.
- Work is weather dependent. Sidewalk and roadway improvements will resume in the spring.
- UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026. Fort Street, 16th Street to 15th Street
- PROJECT WORK: Fort Street will be closed from 16th Street to 15th Street on December 1st – December 5th for pipe replacement work. Sidewalk and roadway improvements will resume in the spring.
- UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
November 18, 2025
Share November 18, 2025 on Facebook Share November 18, 2025 on Twitter Share November 18, 2025 on Linkedin Email November 18, 2025 linkBeginning Wednesday, Resseguie Street will be closed between 13th and 15th Streets for pipe replacement work and roadway improvements. The intersection of 14th and Resseguie Streets will also be closed as part of the work. The roadway is expected to reopen by the December 5.
Photos
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email connect@achdidaho.org -
Supervisor, Construction
Phone 208-387-6100 Email connect@achdidaho.org




