Reutzel Drive Bridge

Share Reutzel Drive Bridge on Facebook Share Reutzel Drive Bridge on Twitter Share Reutzel Drive Bridge on Linkedin Email Reutzel Drive Bridge link

This project is substantially complete

Construction January- Early Summer 2023*

The Ada County Highway District (ACHD) will start construction on Reutzel Drive, north of Amity Road, as early as the beginning of January 2023. Construction is anticipated to be completed early summer of 2023.*

Project Description

  • As part of the Bridge Maintenance Program, ACHD will remove and replace the existing Reutzel Drive culvert over Eight Mile Creek
  • Install bulb-outs at the intersection of Reutzel Drive and Summerset Way
  • Fill the sidewalk gaps on the north side of Reutzel Drive
  • Upgrade pedestrian ramps to current standards
  • Install a drainage basin west of Summerset Way
  • Reconstruct the roadway

*Due to high demand for contractors, labor and supplies, construction schedules may change.

Construction Impacts

  • Temporary road closures
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

Construction January- Early Summer 2023*

The Ada County Highway District (ACHD) will start construction on Reutzel Drive, north of Amity Road, as early as the beginning of January 2023. Construction is anticipated to be completed early summer of 2023.*

Project Description

  • As part of the Bridge Maintenance Program, ACHD will remove and replace the existing Reutzel Drive culvert over Eight Mile Creek
  • Install bulb-outs at the intersection of Reutzel Drive and Summerset Way
  • Fill the sidewalk gaps on the north side of Reutzel Drive
  • Upgrade pedestrian ramps to current standards
  • Install a drainage basin west of Summerset Way
  • Reconstruct the roadway

*Due to high demand for contractors, labor and supplies, construction schedules may change.

Construction Impacts

  • Temporary road closures
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete

  • April 21, 2023

    Share April 21, 2023 on Facebook Share April 21, 2023 on Twitter Share April 21, 2023 on Linkedin Email April 21, 2023 link
    • Utility work ongoing. Waiting on Idaho Power.
    • Grade work for the basin is nearly complete.
    • Wingwalls placed, placing aprons and cut off walls by April 21st.
    • Veolia starting water line.
  • April 14, 2023

    Share April 14, 2023 on Facebook Share April 14, 2023 on Twitter Share April 14, 2023 on Linkedin Email April 14, 2023 link
    • Utility work ongoing. Waiting on Idaho Power.
    • Grade work for the basin is nearly complete.
    • North and south foundation formwork complete.
    • Culvert pieces placed April 11th.
    • Grouting and waterproof membrane ongoing.
  • April 7, 2023

    Share April 7, 2023 on Facebook Share April 7, 2023 on Twitter Share April 7, 2023 on Linkedin Email April 7, 2023 link
    • Utility work ongoing - waiting for Idaho Power.
    • Grade work for the basin is nearly complete.
    • North and south foundation form work complete.
    • Placement of box culvert scheduled for early to mid April.
  • March 31, 2023

    Share March 31, 2023 on Facebook Share March 31, 2023 on Twitter Share March 31, 2023 on Linkedin Email March 31, 2023 link
    • Utility work ongoing. Waiting on Idaho Power.
    • Grade work for the basin is nearly complete.
    • North and south foundation form work complete.
    • Placement of box culvert scheduled for early-mid April.
  • March 24, 2023

    Share March 24, 2023 on Facebook Share March 24, 2023 on Twitter Share March 24, 2023 on Linkedin Email March 24, 2023 link
    • Utility work ongoing.
    • Contractor closed Reutzel on March 6th.
    • Grade work for the basin is nearly complete.
    • North and south foundation form work complete.
    • Placement of box culvert scheduled for early April.
  • March 17, 2023

    Share March 17, 2023 on Facebook Share March 17, 2023 on Twitter Share March 17, 2023 on Linkedin Email March 17, 2023 link
    • Utility work ongoing.
    • Contractor closed Reutzel on March 6th.
    • Grade work for the basin is nearly complete.
    • North and south foundation form work - complete.
  • March 10, 2023

    Share March 10, 2023 on Facebook Share March 10, 2023 on Twitter Share March 10, 2023 on Linkedin Email March 10, 2023 link
    • Contractor has removed the majority of the trees.
    • Utility work ongoing.
    • Contractor closed Reutzel on March 6th.
    • Grade work for the basin is nearly complete. Contractor needs topsoil.
    • North and south foundation formwork complete. Concrete placed March 6th.
  • March 3, 2023

    Share March 3, 2023 on Facebook Share March 3, 2023 on Twitter Share March 3, 2023 on Linkedin Email March 3, 2023 link
    • Contractor has removed the majority of the trees.
    • Utility work ongoing.
    • Contractor anticipates closing Reutzel on March 6th.
    • Grade work for the basin is nearly complete.
    • North and south foundation formwork complete. Waiting for rebar.
  • February 24, 2023

    Share February 24, 2023 on Facebook Share February 24, 2023 on Twitter Share February 24, 2023 on Linkedin Email February 24, 2023 link
    • Contractor has removed the majority of the trees.
    • Utility work ongoing.
    • Road has been re-opened back up to traffic until the contractor can procure the precast structure.
    • Grade work for the basin is nearly complete.
  • February 17, 2023

    Share February 17, 2023 on Facebook Share February 17, 2023 on Twitter Share February 17, 2023 on Linkedin Email February 17, 2023 link
    • Contractor has removed the majority of the trees.
    • Utility work ongoing.
    • Road has been re-opened back up to traffic until the contractor can procure the precast structure.
    • Grade work for the basin is nearly complete.
    • Cofferdams have been installed and dewatering has started.