- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair complete.
- State Street/16th Street intersection - Planning to boring for electrical next week.
- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair complete.
- State Street/16th Street intersection - Planning to boring for electrical next week.
This project is substantially complete.
-
Share February 23, 2024 on Facebook
Share February 23, 2024 on X (formerly Twitter)
Share February 23, 2024 on Linkedin
Email February 23, 2024 link
- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair ongoing- weather dependent.
- State Street/16th Street intersection - Planning to boring for electrical next week.
- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair ongoing- weather dependent.
- State Street/16th Street intersection - Planning to boring for electrical next week.
This project is substantially complete.
-
Share February 16, 2024 on Facebook
Share February 16, 2024 on X (formerly Twitter)
Share February 16, 2024 on Linkedin
Email February 16, 2024 link
- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair ongoing- weather dependent.
- State Street/16th Street intersection - Planning to start in February.
- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair ongoing- weather dependent.
- State Street/16th Street intersection - Planning to start in February.
This project is substantially complete.
-
Share February 9, 2024 on Facebook
Share February 9, 2024 on X (formerly Twitter)
Share February 9, 2024 on Linkedin
Email February 9, 2024 link
- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair ongoing- weather dependent.
- State Street/16th Street intersection.
- Planning to start in February.
- State Street, 2nd Street to east of 4th Street - Concrete complete.
- Landscape repair ongoing- weather dependent.
- State Street/16th Street intersection.
- Planning to start in February.
This project is substantially complete.
-
Share February 2, 2024 on Facebook
Share February 2, 2024 on X (formerly Twitter)
Share February 2, 2024 on Linkedin
Email February 2, 2024 link
- State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
- Minor striping work remains at pedestrian crossings.
- Landscape repair ongoing - weather dependent.
- State Street/16th Street intersection - Planning to start in February.
- State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
- Minor striping work remains at pedestrian crossings.
- Landscape repair ongoing - weather dependent.
- State Street/16th Street intersection - Planning to start in February.
This project is substantially complete.
-
Share January 26, 2024 on Facebook
Share January 26, 2024 on X (formerly Twitter)
Share January 26, 2024 on Linkedin
Email January 26, 2024 link
- State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
- Minor stripe work remains at ped crossings.
- Landscape repair ongoing- weather dependent.
- State Street/16th Street intersection - Planning to start in February.
- State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
- Minor stripe work remains at ped crossings.
- Landscape repair ongoing- weather dependent.
- State Street/16th Street intersection - Planning to start in February.
This project is substantially complete.
-
Share January 19, 2024 on Facebook
Share January 19, 2024 on X (formerly Twitter)
Share January 19, 2024 on Linkedin
Email January 19, 2024 link
- State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
- Minor stripe work remains at ped crossings.
- Landscape repair ongoing - weather dependent.
- State Street/16th Street intersection - Planning to start in February.
- State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
- Minor stripe work remains at ped crossings.
- Landscape repair ongoing - weather dependent.
- State Street/16th Street intersection - Planning to start in February.
This project is substantially complete.
-
Share January 12, 2024 on Facebook
Share January 12, 2024 on X (formerly Twitter)
Share January 12, 2024 on Linkedin
Email January 12, 2024 link
- State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
- Minor stripe work remains at ped crossings.
- Landscape repair ongoing.
- State Street/16th Street intersection - Planning to start in February.
- State Street, 2nd Street to east of 4th Street - Minor concrete placements continue under flagging operations.
- Minor stripe work remains at ped crossings.
- Landscape repair ongoing.
- State Street/16th Street intersection - Planning to start in February.
This project is substantially complete.
-
Share January 5, 2024 on Facebook
Share January 5, 2024 on X (formerly Twitter)
Share January 5, 2024 on Linkedin
Email January 5, 2024 link
- State Street, 2nd Street to east of 4th Street - Electrical work complete. Waiting on landscape repair (including bioretention beds) and signal install.
- Ped ramp walkarounds and sidewalk repair behind curb lines complete.
- Road has been re-opened.
- Minor concrete placements continue under flagging operations. State Street/16th Street intersection.
- State Street, 2nd Street to east of 4th Street - Electrical work complete. Waiting on landscape repair (including bioretention beds) and signal install.
- Ped ramp walkarounds and sidewalk repair behind curb lines complete.
- Road has been re-opened.
- Minor concrete placements continue under flagging operations. State Street/16th Street intersection.
This project is substantially complete.
-
Share December 22, 2023 on Facebook
Share December 22, 2023 on X (formerly Twitter)
Share December 22, 2023 on Linkedin
Email December 22, 2023 link
- State Street, 2nd Street to east of 4th Street
- Electrical work complete.
- Waiting on landscape repair (including bioretention beds) and signal install.
- Ped ramp walkarounds and sidewalk repair behind curb lines remains. Crews still working.
- Anticipate re-opening the road in late December.
- State Street, 2nd Street to east of 4th Street
- Electrical work complete.
- Waiting on landscape repair (including bioretention beds) and signal install.
- Ped ramp walkarounds and sidewalk repair behind curb lines remains. Crews still working.
- Anticipate re-opening the road in late December.
This project is substantially complete.