2024 Arterial and Collector Capital Maintenance

Share 2024 Arterial and Collector Capital Maintenance on Facebook Share 2024 Arterial and Collector Capital Maintenance on Twitter Share 2024 Arterial and Collector Capital Maintenance on Linkedin Email 2024 Arterial and Collector Capital Maintenance link

This project is substantially complete. 

In January 2024, The Ada County Highway District (ACHD) will start construction on the 2024 Arterial and Collector Capital Maintenance Project. This maintenance project includes pavement rehabilitation, upgraded pedestrian ramps, and new curb, gutter, and sidewalk at certain locations. Construction is anticipated to be completed late in the summer of 2024.

Road Segments

  • Swan Falls Road, King Road to Sunbeam Street
  • Stagecoach Way, Swan Falls Road to Luker Road
  • Luker Road, King Road to Stagecoach Way
    • Fill in a sidewalk gap on Luker Road between Access Street and Stage Coach Way
    • Replace an existing culvert at the Luker Road and Stagecoach Road intersection
  • Poen Road, Swan Falls Road to Cloverdale Road

Construction Impacts

  • Temporary road closures and lane restrictions
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

In January 2024, The Ada County Highway District (ACHD) will start construction on the 2024 Arterial and Collector Capital Maintenance Project. This maintenance project includes pavement rehabilitation, upgraded pedestrian ramps, and new curb, gutter, and sidewalk at certain locations. Construction is anticipated to be completed late in the summer of 2024.

Road Segments

  • Swan Falls Road, King Road to Sunbeam Street
  • Stagecoach Way, Swan Falls Road to Luker Road
  • Luker Road, King Road to Stagecoach Way
    • Fill in a sidewalk gap on Luker Road between Access Street and Stage Coach Way
    • Replace an existing culvert at the Luker Road and Stagecoach Road intersection
  • Poen Road, Swan Falls Road to Cloverdale Road

Construction Impacts

  • Temporary road closures and lane restrictions
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

This project is substantially complete. 

  • August 23, 2024

    Share August 23, 2024 on Facebook Share August 23, 2024 on Twitter Share August 23, 2024 on Linkedin Email August 23, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Complete.
    • Stagecoach Way, Swan Falls Rd to Luker Rd - Complete.
    • Luker Rd, King Rd to Stagecoach Way - Concrete repair of ped ramps remains.
    • Poen Rd, Swan Falls to Cloverdale - Complete.
  • August 15, 2024

    Share August 15, 2024 on Facebook Share August 15, 2024 on Twitter Share August 15, 2024 on Linkedin Email August 15, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Complete.
    • Stagecoach Way, Swan Falls Rd to Luker Rd - Complete.
    • Luker Rd, King Rd to Stagecoach Way - Concrete repair of ped ramps remains.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete.
  • August 9, 2024

    Share August 9, 2024 on Facebook Share August 9, 2024 on Twitter Share August 9, 2024 on Linkedin Email August 9, 2024 link

    Project includes work on the following segments:

    • Swan Falls Rd, King Rd to Sunbeam St - Complete.
    • Stagecoach Way, Swan Falls Rd to Luker Rd - Complete.
    • Luker Rd, King Rd to Stagecoach Way - Paving complete.Minor sidewalk placements remain. Lane lines are scheduled for next week.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete.
  • August 2, 2024

    Share August 2, 2024 on Facebook Share August 2, 2024 on Twitter Share August 2, 2024 on Linkedin Email August 2, 2024 link
    • Project includes work on the following segments:
      • Swan Falls Rd, King Rd to Sunbeam St - Complete.
      • Stagecoach Way, Swan Falls Rd to Luker Rd - Complete.
      • Luker Rd, King Rd to Stagecoach Way - Paving Complete. Minor sidewalk placements remain. Lane lines are scheduled for next week.
      • Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete.
  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Complete.
    • Stagecoach Way, Swan Falls Rd to Luker Rd - Complete.
    • Luker Rd, King Rd to Stagecoach Way - Milling and demo complete.
    • Water line work for City of Kuna complete.
    • Concrete prep ongoing and placements are scheduled for this week and next. Paving is tentatively scheduled for July 29th – 30th.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.
  • July 19, 2024

    Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Complete.
    • Stagecoach Way, Swan Falls Rd to Luker Rd - Complete.
    • Luker Rd, King Rd to Stagecoach Way - Milling and demo complete.
    • Water line work for City of Kuna complete. Concrete prep started and placements are scheduled for this week and next. Paving is tentatively scheduled for July 25th – 26th.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.
  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Complete.
    • Stagecoach Way, Swan Falls Rd to Luker Rd - Complete.
    • Luker Rd, King Rd to Stagecoach Way - Milling and demo complete.
    • Water line work for City of Kuna complete.
    • Concrete prep started and placements are scheduled for this week and next. Paving is tentatively scheduled for July 25th – 26th.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.
  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Complete.
    • Stagecoach Way, Swan Falls Rd to Luker Rd - Paved this week. Shouldering started.
    • Luker Rd, King Rd to Stagecoach Way - Milling and demo started. Water line work for City of Kuna starting Friday.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.
  • June 21, 2024

    Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link
    • Swan Falls Rd, King Rd to Sunbeam St - Complete.
    • Stagecoach Way, Swan Falls Rd to Luker Rd - Paved this week. Shouldering started.
    • Luker Rd, King Rd to Stagecoach Way - Irrigation pipe crossing complete and patched back. Remaining work expected to start next week.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd - Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link

    Project includes work on the following segments:

    • Swan Falls Rd, King Rd to Sunbeam St
      • Complete.
    • Stagecoach Way, Swan Falls Rd to Luker Rd
      • Paved this week.
      • Shouldering started.
    • Luker Rd, King Rd to Stagecoach Way
      • Irrigation pipe crossing complete and patched back.
      • Remaining work expected to start next week.
    • Poen Rd, Swan Falls Rd to Cloverdale Rd
      • Complete – waiting 45 days before second coat of paint is applied. This is applicable at all locations.