37th Street Bridge

Share 37th Street Bridge on Facebook Share 37th Street Bridge on Twitter Share 37th Street Bridge on Linkedin Email 37th Street Bridge link

Work substantially complete. 

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on 37th Street, southwest of Adams Street, as early as the beginning of October 2023 .* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Boise City Canal.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on 37th Street, southwest of Adams Street, as early as the beginning of October 2023 .* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Boise City Canal.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

Work substantially complete. 

  • February 23, 2024

    Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link
    • Sewer work for Garden City will start the first week of March.
    • Curb & gutter work complete.
    • Sidewalk placements on-going.
  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Sewer work for Garden City will start the first week of March.
    • Curb & gutter work complete.
    • Sidewalk placed this week.
  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • Utility work complete – except for the sewer work for Garden City.
    • Plan is to start that work the first week of March.
    • Curb & gutter work ongoing.
  • February 2, 2024

    Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link
    • Utility work complete – except for the sewer work for Garden City.
    • Plan is to start that work in February.
    • Curb & gutter work ongoing.
  • January 26, 2024

    Share January 26, 2024 on Facebook Share January 26, 2024 on Twitter Share January 26, 2024 on Linkedin Email January 26, 2024 link
    • Utility work complete – except for the sewer work for Garden City.
    • Plan is to start that work in February.
    • Minimal work due to weather.
  • January 19, 2024

    Share January 19, 2024 on Facebook Share January 19, 2024 on Twitter Share January 19, 2024 on Linkedin Email January 19, 2024 link
    • Utility work complete – except for the sewer work for Garden City.
    • Plan is to start that work in February.
    • Minimal work due to weather.
  • January 12, 2024

    Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link
    • Utility work complete – except for the sewer work for Garden City.
    • Preliminary plan is to start that work in February.
    • Precast sections complete.
    • Wing walls and cast-in-place box have been stripped.
    • RipRap has been placed on the east side.
  • January 5, 2024

    Share January 5, 2024 on Facebook Share January 5, 2024 on Twitter Share January 5, 2024 on Linkedin Email January 5, 2024 link
    • Utility work ongoing.
    • Precast sections have been set.
    • Coordination with Garden City sewer work continues.
    • Wing walls and cast-in-place box have been placed.
  • December 22, 2023

    Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link
    • Utility work ongoing.
    • Precast sections have been set.
    • Coordination with Garden City sewer work continues.
  • December 15, 2023

    Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link
    • 37th Street will be closed for the duration of the work.
    • Utility work continues. o Bridge/Culvert demo complete.
    • Coordination with Garden City sewer work continues.