Eagle Road in front of Albertsons
- Power pole areas repaired and paved.
- Swale ongoing.
2nd Street and State Street
- Crosswalks being installed.
- Pavers being installed.
- Signal turn on anticipated November 21st.
Share November 15, 2024 on Facebook
Share November 15, 2024 on Linkedin
Email November 15, 2024 link
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
Share November 7, 2024 on Facebook
Share November 7, 2024 on Linkedin
Email November 7, 2024 link
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
Share November 1, 2024 on Facebook
Share November 1, 2024 on Linkedin
Email November 1, 2024 link
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open - moving back over to finish Eagle Rd.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- Asphalt complete.
Share October 24, 2024 on Facebook
Share October 24, 2024 on Linkedin
Email October 24, 2024 link
Eagle Road in front of Albertsons
- Idaho Power relocating poles
2nd Street and State Street
- 2nd and State intersection closed.
- Silva Cells installed.
- Light pole bases, conduit and signal work ongoing.
- Flying poles October 24th.
- Curb and sidewalk ongoing.
- Asphalt paving moved to October 29th.
- Idaho Power adjusting lines starting October 28th on 2nd Street.
Share October 17, 2024 on Facebook
Share October 17, 2024 on Linkedin
Email October 17, 2024 link
Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st
2nd Street and State Street
- 2nd and State intersection closed
- Silva Cells installed
- Light pole bases, conduit and signal work ongoing
- Curb and sidewalk being prepped
- Curb and sidewalk being placed October 10th – October 22nd
- Asphalt paving anticipated October 24th
Share October 10, 2024 on Facebook
Share October 10, 2024 on Linkedin
Email October 10, 2024 link
Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells being installed.
- Light pole bases, conduit and signal work ongoing.
- Curb and sidewalk being prepped.
- Curb and sidewalk being placed October 10th – October 22nd.
- Asphalt paving anticipated October 24th.
Share Pedestrian Detour Map on Facebook
Share Pedestrian Detour Map on Linkedin
Email Pedestrian Detour Map link
Share October 4, 2024 on Facebook
Share October 4, 2024 on Linkedin
Email October 4, 2024 link
Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed starting September 25th.
- Signal pole bases being placed.
- Concrete removed on North side.
- Storm drain complete.
- Silva Cells being installed.
- Light pole bases, conduit and signal work ongoing.
- Curb and sidewalk being prepped.
Share September 26, 2024 on Facebook
Share September 26, 2024 on Linkedin
Email September 26, 2024 link
Eagle Road in front of Albertsons
- Pavement markings remaining.
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed starting September 25th.
- Signal pole bases being placed.
- Concrete removed on north side.
- Storm drain and Veola water work ongoing.
- Historic lights being removed September 30th.
- Electrical conduit being placed afterwards.