Eagle Road, Lake Hazel Road to Amity Road
Share Eagle Road, Lake Hazel Road to Amity Road on Facebook
Share Eagle Road, Lake Hazel Road to Amity Road on Twitter
Share Eagle Road, Lake Hazel Road to Amity Road on Linkedin
Email Eagle Road, Lake Hazel Road to Amity Road link
The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.
Roadway Description
- Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
- Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
- Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.
Eagle and Lake Hazel Intersection Description
- Widen and signalize the Lake Hazel and Eagle intersection
- Add dual left-turn lanes on most approaches
- Include additional thru lanes
- Add dedicated right turn lanes on two approaches
- Install a multi-use pathway for bicyclists and pedestrians
- Include painted crosswalks
The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.
Roadway Description
- Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
- Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
- Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.
Eagle and Lake Hazel Intersection Description
- Widen and signalize the Lake Hazel and Eagle intersection
- Add dual left-turn lanes on most approaches
- Include additional thru lanes
- Add dedicated right turn lanes on two approaches
- Install a multi-use pathway for bicyclists and pedestrians
- Include painted crosswalks
-
June 20, 2025
Share June 20, 2025 on Facebook Share June 20, 2025 on Twitter Share June 20, 2025 on Linkedin Email June 20, 2025 link- Lake Hazel and Eagle Intersection closed
- Wall A and other miscellaneous walls ongoing
- Conduits and pole foundations being placed
- Placing road base
- Sidewalk being placed
- Concrete Paving completed until Soundwall installed
- Preparing road for asphalt
- Paving anticipated June 26th
- Phase 2 Anticipated starting first week of July
- Lake Hazel to Amity closed for duration of 2nd phase
- Lake Hazel & Eagle Intersection will be open in the East/West direction.
- Lake Hazel and Eagle Intersection closed
- Wall A and other miscellaneous walls ongoing
- Conduits and pole foundations being placed
- Placing road base
- Sidewalk being placed
- Concrete Paving completed until Soundwall installed
- Preparing road for asphalt
- Paving anticipated June 26th
- Phase 2 Anticipated starting first week of July
- Lake Hazel to Amity closed for duration of 2nd phase
- Lake Hazel & Eagle Intersection will be open in the East/West direction.
-
June 13, 2025
Share June 13, 2025 on Facebook Share June 13, 2025 on Twitter Share June 13, 2025 on Linkedin Email June 13, 2025 link- Lake Hazel and Eagle Intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving started June 2nd and will be on-going through June 18th.
- South and West legs complete.
- Lake Hazel and Eagle Intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving started June 2nd and will be on-going through June 18th.
- South and West legs complete.
-
June 6, 2025
Share June 6, 2025 on Facebook Share June 6, 2025 on Twitter Share June 6, 2025 on Linkedin Email June 6, 2025 link- Lake Hazel and Eagle Intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving June 2nd and will be on-going through June 18th.
- Lake Hazel and Eagle Intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving June 2nd and will be on-going through June 18th.
-
May 30, 2025
Share May 30, 2025 on Facebook Share May 30, 2025 on Twitter Share May 30, 2025 on Linkedin Email May 30, 2025 link- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving anticipated starting June 2nd – 18th.
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving anticipated starting June 2nd – 18th.
-
May 23, 2025
Share May 23, 2025 on Facebook Share May 23, 2025 on Twitter Share May 23, 2025 on Linkedin Email May 23, 2025 link- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving anticipated starting June 2nd – 18th.
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving anticipated starting June 2nd – 18th.
-
May 16, 2025
Share May 16, 2025 on Facebook Share May 16, 2025 on Twitter Share May 16, 2025 on Linkedin Email May 16, 2025 link- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
-
May 8, 2025
Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 link- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
-
May 2, 2025
Share May 2, 2025 on Facebook Share May 2, 2025 on Twitter Share May 2, 2025 on Linkedin Email May 2, 2025 link- Lake Hazel and Eagle Intersection closed.
- Walls ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk prep ongoing.
- Lake Hazel and Eagle Intersection closed.
- Walls ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk prep ongoing.
-
April 25, 2025
Share April 25, 2025 on Facebook Share April 25, 2025 on Twitter Share April 25, 2025 on Linkedin Email April 25, 2025 link- Lake Hazel and Eagle Intersection closed.
- Wall construction ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk prep ongoing.
- Lake Hazel and Eagle Intersection closed.
- Wall construction ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk prep ongoing.
-
April 17, 2025
Share April 17, 2025 on Facebook Share April 17, 2025 on Twitter Share April 17, 2025 on Linkedin Email April 17, 2025 link- Lake Hazel and Eagle Intersection closed.
- Wall excavation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk anticipated starting April 21st.
- Lake Hazel and Eagle Intersection closed.
- Wall excavation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk anticipated starting April 21st.
Page last updated: 21 May 2026, 09:47 AM
Follow Project
Stay informed
Subscribe for project updates
254 members of your community are following this project
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Supervisor, Capital Projects
Phone 208-387-6100 Email connect@achdidaho.org