Hubbard Road, Ten Mile Road to Meridian Road

Share Hubbard Road, Ten Mile Road to Meridian Road on Facebook Share Hubbard Road, Ten Mile Road to Meridian Road on Twitter Share Hubbard Road, Ten Mile Road to Meridian Road on Linkedin Email Hubbard Road, Ten Mile Road to Meridian Road link

Starting as early as November, the Ada County Highway District (ACHD) will reconstruct Hubbard Road from Ten Mile Road to Meridian Road as part of the 2025 Arterial & Collector Capital Maintenance Project. Construction is expected to be complete late summer of 2026.*

Project Highlights

  • Reconstructing the roadway pavement on Hubbard Road
  • Upgrading pedestrian ramps, sidewalks, and curb & gutter at key intersections
  • Adding 6-ft bike lanes on both sides of Hubbard Road, with multi-use or asphalt pathways at select locations
  • Replacing an irrigation culvert bridge and the existing pipe on the State Lateral canal
  • Installing railing on top of the Kuna Canal wingwalls
  • Upgrading the City of Kuna’s water and sewer

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

Starting as early as November, the Ada County Highway District (ACHD) will reconstruct Hubbard Road from Ten Mile Road to Meridian Road as part of the 2025 Arterial & Collector Capital Maintenance Project. Construction is expected to be complete late summer of 2026.*

Project Highlights

  • Reconstructing the roadway pavement on Hubbard Road
  • Upgrading pedestrian ramps, sidewalks, and curb & gutter at key intersections
  • Adding 6-ft bike lanes on both sides of Hubbard Road, with multi-use or asphalt pathways at select locations
  • Replacing an irrigation culvert bridge and the existing pipe on the State Lateral canal
  • Installing railing on top of the Kuna Canal wingwalls
  • Upgrading the City of Kuna’s water and sewer

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • April 10, 2026

    Share April 10, 2026 on Facebook Share April 10, 2026 on Twitter Share April 10, 2026 on Linkedin Email April 10, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is complete.
    • Contractor continued roadway import and grade prep at Ten Mile headed east to Linder.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
    • Contractor has started working on concrete sidewalk, curb, and gutter placements at various locations along Hubbard.
    • Paving is scheduled for the end of the month, for phase 1.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is complete.
    • Contractor continued roadway import and grade prep at Ten Mile headed east to Linder.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
    • Contractor has started working on concrete sidewalk, curb, and gutter placements at various locations along Hubbard.
    • Paving is scheduled for the end of the month, for phase 1.
  • April 2, 2026

    Share April 2, 2026 on Facebook Share April 2, 2026 on Twitter Share April 2, 2026 on Linkedin Email April 2, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation work is complete.
  • March 26, 2026

    Share March 26, 2026 on Facebook Share March 26, 2026 on Twitter Share March 26, 2026 on Linkedin Email March 26, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe complete.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe complete.
  • March 19, 2026

    Share March 19, 2026 on Facebook Share March 19, 2026 on Twitter Share March 19, 2026 on Linkedin Email March 19, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
  • March 13, 2026

    Share March 13, 2026 on Facebook Share March 13, 2026 on Twitter Share March 13, 2026 on Linkedin Email March 13, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
  • March 6, 2026

    Share March 6, 2026 on Facebook Share March 6, 2026 on Twitter Share March 6, 2026 on Linkedin Email March 6, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled, and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
  • February 27, 2026

    Share February 27, 2026 on Facebook Share February 27, 2026 on Twitter Share February 27, 2026 on Linkedin Email February 27, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled and demo of existing facilities is ongoing.
    • Contractor continued roadway excavation and grade prep this week at Ten Mile headed east.
    • Contractor completed the City of Kuna utility work, up to Linder.
    • Contactor has completed the retaining wall on the northwest end of the project.
    • Irrigation crossings installed. One minor adjustment to a supply pipe needs to be made.
  • February 19, 2025

    Share February 19, 2025 on Facebook Share February 19, 2025 on Twitter Share February 19, 2025 on Linkedin Email February 19, 2025 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled and demo of existing facilities is ongoing.
    • Contractor started roadway excavation and grade prep this week at Ten Mile headed east.
    • Utility conflict was identified, which may delay the excavation on the south side of Hubbard.
    • Contractor continuing the City of Kuna utility work.
    • Contactor continues setting the retaining wall on the northwest end of the project.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Roadway has been milled and demo of existing facilities is ongoing.
    • Contractor started roadway excavation and grade prep this week at Ten Mile headed east.
    • Utility conflict was identified, which may delay the excavation on the south side of Hubbard.
    • Contractor continuing the City of Kuna utility work.
    • Contactor continues setting the retaining wall on the northwest end of the project.
  • February 12, 2026

    Share February 12, 2026 on Facebook Share February 12, 2026 on Twitter Share February 12, 2026 on Linkedin Email February 12, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Ten Mile Road and Linder Road will remain open during this phase of work.
    • Flagging and a partial daily closure (east of Linder, on Hubbard) will be complete this week for utility installation within the intersection.
    • Roadway has been milled and demo of existing facilities is ongoing.
    • Contractor to start roadway excavation and grade prep next week at Ten Mile headed east.
    • Contractor continuing the City of Kuna utility work.
    • Contactor has started setting the retaining wall on the northwest end of the project.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Ten Mile Road and Linder Road will remain open during this phase of work.
    • Flagging and a partial daily closure (east of Linder, on Hubbard) will be complete this week for utility installation within the intersection.
    • Roadway has been milled and demo of existing facilities is ongoing.
    • Contractor to start roadway excavation and grade prep next week at Ten Mile headed east.
    • Contractor continuing the City of Kuna utility work.
    • Contactor has started setting the retaining wall on the northwest end of the project.
  • February 5, 2026

    Share February 5, 2026 on Facebook Share February 5, 2026 on Twitter Share February 5, 2026 on Linkedin Email February 5, 2026 link
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Ten Mile Road and Linder Road will remain open during this phase of work.
    • Flagging and a partial daily closure (east of Linder, on Hubbard) will occur next week for utility installation within the intersection. Partial closure will be between the hours of 10AM and 3PM starting Monday, February 9 rd through Thursday, February 12th.
    • Roadway has been milled and demo of existing facilities is ongoing.
    • Contractor continuing the City of Kuna utility work.
    • Contactor has started setting the retaining wall on the northwest end of the project.
    • Hubbard Road remains closed between Ten Mile Road and Linder Road.
    • Ten Mile Road and Linder Road will remain open during this phase of work.
    • Flagging and a partial daily closure (east of Linder, on Hubbard) will occur next week for utility installation within the intersection. Partial closure will be between the hours of 10AM and 3PM starting Monday, February 9 rd through Thursday, February 12th.
    • Roadway has been milled and demo of existing facilities is ongoing.
    • Contractor continuing the City of Kuna utility work.
    • Contactor has started setting the retaining wall on the northwest end of the project.