Resseguie | Fort | 15th St: Pavement Preservation & ADA Project

Share Resseguie | Fort | 15th St: Pavement Preservation & ADA Project on Facebook Share Resseguie | Fort | 15th St: Pavement Preservation & ADA Project on Twitter Share Resseguie | Fort | 15th St: Pavement Preservation & ADA Project on Linkedin Email Resseguie | Fort | 15th St: Pavement Preservation & ADA Project link

The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.

  • Resseguie St., 9th to 16th streets,
  • Fort St., 16th St. to 15th St.
  • 15th St., Fort St. to Resseguie St.

Project Description

  • Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
  • Replace select sections of curb where trees will not be impacted.
  • Install pedestrian ramps as needed to improve accessibility.
  • Retain historic curb stamps wherever feasible.

*Schedule subject to change.

The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.

  • Resseguie St., 9th to 16th streets,
  • Fort St., 16th St. to 15th St.
  • 15th St., Fort St. to Resseguie St.

Project Description

  • Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
  • Replace select sections of curb where trees will not be impacted.
  • Install pedestrian ramps as needed to improve accessibility.
  • Retain historic curb stamps wherever feasible.

*Schedule subject to change.

  • September 26, 2025

    Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: Resseguie Street will be closed from 11th and 13th on August 25th – October 4th for pipe replacement work and roadway improvements. The intersection of Resseguie Street and 13th Street will be closed Friday, October 17th – Sunday, October 19th for roadway improvements.

    UTILITY WORK: Veolia’s work is complete. Fort Street, 16th Street to 15th Street

    UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street

  • September 19, 2025

    Share September 19, 2025 on Facebook Share September 19, 2025 on Twitter Share September 19, 2025 on Linkedin Email September 19, 2025 link

    Project includes work on the following segments: Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: Resseguie Street will be closed from 11th and 13th on August 25th – October 4th for pipe replacement work and roadway improvements. The intersection of Resseguie Street and 13th Street will be closed Friday, October 17th – Sunday, October 19th for roadway improvements.

    UTILITY WORK: Veolia will be closing Resseguie from 10th to 11th on September 22 nd – September 24th. Fort Street, 16th Street to 15th Street.

    UTILITY WORK: Veolia will be closing Fort Street between 15th and 16th on September 9th – September 22th. 15th Street will be closed during this phase.

    15th Street, Fort Street to Resseguie Street

  • September 12, 2025

    Share September 12, 2025 on Facebook Share September 12, 2025 on Twitter Share September 12, 2025 on Linkedin Email September 12, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: Resseguie Street will be closed from 11th and 13th on August 25th – September 30th for pipe replacement work and roadway improvements.

    UTILITY WORK: Veolia will be closing Resseguie from 10th to 11th on September 23rd – September 25th .

    Fort Street, 16th Street to 15th Street

    UTILITY WORK: Veolia will be closing Fort Street between 15th and 16th on September 9th – September 22th . 15th Street will be closed during this phase.

    15th Street, Fort Street to Resseguie Street

  • September 5, 2025

    Share September 5, 2025 on Facebook Share September 5, 2025 on Twitter Share September 5, 2025 on Linkedin Email September 5, 2025 link
    • Resseguie Street, 16th Street to 9th Street PROJECT WORK:
    • Resseguie Street will be closed from 11th and 13th on August 25th – September 30th for pipe replacement work and roadway improvements.
    • UTILITY WORK: Veolia will be closing Resseguie between 15th and 16th on August 25th – Sept 5th. 15th Street will be closed during this phase. Veolia will be closing the intersection of Resseguie and 16th Street on September 6th – 8th.
    • Fort Street, 16th Street to 15th Street
    • UTILITY WORK: Veolia will be closing Fort Street between 15th and 16th on September 9th – September 26th .
    • 15th Street, Fort Street to Resseguie Street
  • August 29, 2025

    Share August 29, 2025 on Facebook Share August 29, 2025 on Twitter Share August 29, 2025 on Linkedin Email August 29, 2025 link

    Project includes work on the following segments: Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: The intersection of Resseguie Street & 9th Street will be closed August 18th – 22nd for pipe replacement work.

    Resseguie Street will be closed from 11th and 13th on August 25th – September 30th for pipe replacement work and roadway improvements.

    UTILITY WORK: Veolia will be closing Resseguie between 15th and 16th on August 25th – Sept 5th.

    15th Street will be closed during this phase. Veolia will be closing the intersection of Resseguie and 16th Street on September 6th – 8th .

    Veolia will be closing Fort Street between 15th and 16th on September 9th – September 26th .

    Fort Street, 16th Street to 15th Street

    15th Street, Fort Street to Resseguie Street

  • August 21, 2025

    Share August 21, 2025 on Facebook Share August 21, 2025 on Twitter Share August 21, 2025 on Linkedin Email August 21, 2025 link

    Project includes work on the following segments: Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: The intersection of Resseguie Street & 9th Street will be closed August 18th – 22nd for pipe replacement work.

    Resseguie Street will be closed from 11th and 13th on August 25th – September 30th for roadway improvements.

    UTILITY WORK: Veolia will be closing Resseguie between 13th and 15th on August 12th -23rd. 13th Street and 15th Street will be open during this phase. 14th Street will be closed.

    Veolia will be closing Resseguie between 15th and 16th on August 25th – Sept 5th. 15th Street will be closed during this phase.

    Fort Street, 16th Street to 15th Street.

    15th Street, Fort Street to Resseguie Street

  • August 15, 2025

    Share August 15, 2025 on Facebook Share August 15, 2025 on Twitter Share August 15, 2025 on Linkedin Email August 15, 2025 link

    Project includes work on the following segments: oResseguie Street, 16th Street to 9th Street

    PROJECT WORK: The intersection of Resseguie Street & 9th Street will be closed August 18th – 26th for pipe replacement work. Resseguie Street will be closed from 11th and 13th on August 25th – September 30th for roadway improvements. UTILITY WORK: Veolia will be closing Resseguie between 13th and 15th on August 12th -23rd. 13th Street and 15th Street will be open during this phase. 14th Street will be closed. Veolia will be closing Resseguie between 15th and 16th on August 25th – Sept 5th. 15th Street will be closed during this phase. Fort Street, 16th Street to 15th Street. 15th Street, Fort Street to Resseguie Street.

  • August 8, 2025

    Share August 8, 2025 on Facebook Share August 8, 2025 on Twitter Share August 8, 2025 on Linkedin Email August 8, 2025 link

    Project includes work on the following segments:

    • Resseguie Street, 16th Street to 9th Street - Veolia will be closing the intersection of Resseguie & 13th Street on Aug 8th – 11th to get the intersection done before school starts.
    • Veolia will be closing Resseguie between 13th and 15th on August 12th -23rd.
    • 13th Street and 15th Street will be open during this phase. 14th Street will be closed.
    • Veolia will be closing Resseguie between 15th and 16th on August 25th – Sept 5th. 15th Street will be closed during this phase.
    • Fort Street, 16th Street to 15th Street o 15th Street, Fort Street to Resseguie Street
  • August 1, 2025

    Share August 1, 2025 on Facebook Share August 1, 2025 on Twitter Share August 1, 2025 on Linkedin Email August 1, 2025 link
    • Project includes work on the following segments:
    • Resseguie Street, 16th Street to 9th Street. Veolia will be closing the intersection of Resseguie & 13th Street on Aug 8th – 11th to get the intersection done before school starts.
    • Veolia will be closing Resseguie between 13th and 15th on August 12th -23rd. 13th Street and 15th Street will be open during this phase. 14th Street will be closed.
    • Veolia will be closing Resseguie between 15th and 16th on August 25 th – Sept 5 th. 15th Street will be closed during this phase.
    • Fort Street, 16th Street to 15th Street
    • 15th Street, Fort Street to Resseguie Street
  • Completion date extended

    Share Completion date extended on Facebook Share Completion date extended on Twitter Share Completion date extended on Linkedin Email Completion date extended link

    Originally scheduled for completion in late fall 2025, the project is now expected to be complete in spring 2026 due to utility work.

    Please note that in an effort to keep a paved surface during the winter months, the bulk of the work will pause during winter since the pavement plants will be closed. Concrete work, such as sidewalk work, will continue.

Page last updated: 04 Dec 2025, 03:53 PM