Resseguie | Fort | 15th St: Pavement Preservation & ADA Project

Share Resseguie | Fort | 15th St: Pavement Preservation & ADA Project on Facebook Share Resseguie | Fort | 15th St: Pavement Preservation & ADA Project on Twitter Share Resseguie | Fort | 15th St: Pavement Preservation & ADA Project on Linkedin Email Resseguie | Fort | 15th St: Pavement Preservation & ADA Project link

The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.

  • Resseguie St., 9th to 16th streets,
  • Fort St., 16th St. to 15th St.
  • 15th St., Fort St. to Resseguie St.

Project Description

  • Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
  • Replace select sections of curb where trees will not be impacted.
  • Install pedestrian ramps as needed to improve accessibility.
  • Retain historic curb stamps wherever feasible.

*Schedule subject to change.

The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.

  • Resseguie St., 9th to 16th streets,
  • Fort St., 16th St. to 15th St.
  • 15th St., Fort St. to Resseguie St.

Project Description

  • Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
  • Replace select sections of curb where trees will not be impacted.
  • Install pedestrian ramps as needed to improve accessibility.
  • Retain historic curb stamps wherever feasible.

*Schedule subject to change.

  • November 14, 2025

    Share November 14, 2025 on Facebook Share November 14, 2025 on Twitter Share November 14, 2025 on Linkedin Email November 14, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK:

    • Resseguie Street will be closed from 15th Street to 16th Street on November 5th – November 18th for pipe replacement work.
    • Resseguie Street will be closed from 13th Street to 15th Street on November 19th – December 5th for pipe replacement work. Work is weather dependent.

    UTILITY WORK:

    • Veolia’s work is complete.
    • Fort Street, 16th Street to 15th Street

    UTILITY WORK:

    • Veolia’s work is complete.
    • 15th Street, Fort Street to Resseguie Street
  • November 7, 2025

    Share November 7, 2025 on Facebook Share November 7, 2025 on Twitter Share November 7, 2025 on Linkedin Email November 7, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: Resseguie Street will be closed from 15th Street to 16th Street on November 5th – November 26th for pipe replacement work.

    UTILITY WORK: Veolia’s work is complete. Fort Street, 16th Street to 15th Street

    UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street

  • October 31, 2025

    Share October 31, 2025 on Facebook Share October 31, 2025 on Twitter Share October 31, 2025 on Linkedin Email October 31, 2025 link
    • Resseguie Street, 16th Street to 9th Street
    • PROJECT WORK: Resseguie Street will be closed from 9 th Street to 11th Street on October 20th – November 4th for pipe replacement work. Resseguie Street will be closed from 15th Street to 16th Street on November 5th – November 26th for pipe replacement work.
    • UTILITY WORK: Veolia’s work is complete. Fort Street, 16th Street to 15th Street
    • UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street
  • October 24, 2025

    Share October 24, 2025 on Facebook Share October 24, 2025 on Twitter Share October 24, 2025 on Linkedin Email October 24, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: Resseguie Street will be closed from 9th Street to 11th Street on October 20th – November 30th for pipe replacement work and roadway improvements.

    UTILITY WORK:

    Veolia’s work is complete.

    Fort Street, 16th Street to 15th Street

    UTILITY WORK:

    Veolia’s work is complete.

    15th Street, Fort Street to Resseguie Street

  • October 17, 2025

    Share October 17, 2025 on Facebook Share October 17, 2025 on Twitter Share October 17, 2025 on Linkedin Email October 17, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: The intersection of Resseguie Street and 13th Street will be closed Friday, October 17th – Sunday, October 19th for pipe replacement.

    Resseguie Street will be closed from 9 th Street to 11th Street on October 20th – November 30th for pipe replacement work and roadway improvements.

    UTILITY WORK: Veolia’s work is complete. Fort Street, 16th Street to 15th Street

    UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street

  • October 10, 2025

    Share October 10, 2025 on Facebook Share October 10, 2025 on Twitter Share October 10, 2025 on Linkedin Email October 10, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK:

    Resseguie Street will be closed from 11th and 13th on August 25th – October 15th for pipe

    replacement work and roadway improvements.

    UTILITY WORK:

    Veolia’s work is complete.

    Fort Street, 16th Street to 15th Street

    UTILITY WORK:

    Veolia’s work is complete.

    15th Street, Fort Street to Resseguie Street

  • October 2, 2025

    Share October 2, 2025 on Facebook Share October 2, 2025 on Twitter Share October 2, 2025 on Linkedin Email October 2, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: Resseguie Street will be closed from 11th and 13th on August 25th – October 4th for pipe replacement work and roadway improvements. The intersection of Resseguie Street and 13th Street will be closed Friday, October 17th – Sunday, October 19th for roadway improvements.

    UTILITY WORK: Veolia’s work is complete. Fort Street, 16th Street to 15th Street

    UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street

  • September 26, 2025

    Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: Resseguie Street will be closed from 11th and 13th on August 25th – October 4th for pipe replacement work and roadway improvements. The intersection of Resseguie Street and 13th Street will be closed Friday, October 17th – Sunday, October 19th for roadway improvements.

    UTILITY WORK: Veolia’s work is complete. Fort Street, 16th Street to 15th Street

    UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street

  • September 19, 2025

    Share September 19, 2025 on Facebook Share September 19, 2025 on Twitter Share September 19, 2025 on Linkedin Email September 19, 2025 link

    Project includes work on the following segments: Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: Resseguie Street will be closed from 11th and 13th on August 25th – October 4th for pipe replacement work and roadway improvements. The intersection of Resseguie Street and 13th Street will be closed Friday, October 17th – Sunday, October 19th for roadway improvements.

    UTILITY WORK: Veolia will be closing Resseguie from 10th to 11th on September 22 nd – September 24th. Fort Street, 16th Street to 15th Street.

    UTILITY WORK: Veolia will be closing Fort Street between 15th and 16th on September 9th – September 22th. 15th Street will be closed during this phase.

    15th Street, Fort Street to Resseguie Street

  • September 12, 2025

    Share September 12, 2025 on Facebook Share September 12, 2025 on Twitter Share September 12, 2025 on Linkedin Email September 12, 2025 link

    Resseguie Street, 16th Street to 9th Street

    PROJECT WORK: Resseguie Street will be closed from 11th and 13th on August 25th – September 30th for pipe replacement work and roadway improvements.

    UTILITY WORK: Veolia will be closing Resseguie from 10th to 11th on September 23rd – September 25th .

    Fort Street, 16th Street to 15th Street

    UTILITY WORK: Veolia will be closing Fort Street between 15th and 16th on September 9th – September 22th . 15th Street will be closed during this phase.

    15th Street, Fort Street to Resseguie Street