- Utility work ongoing. Waiting on Idaho Power.
- Grade work for the basin is nearly complete.
- Wingwalls placed, placing aprons and cut off walls by April 21st.
- Veolia starting water line.
- Utility work ongoing. Waiting on Idaho Power.
- Grade work for the basin is nearly complete.
- Wingwalls placed, placing aprons and cut off walls by April 21st.
- Veolia starting water line.
This project is substantially complete
-
Share April 14, 2023 on Facebook
Share April 14, 2023 on X (formerly Twitter)
Share April 14, 2023 on Linkedin
Email April 14, 2023 link
- Utility work ongoing. Waiting on Idaho Power.
- Grade work for the basin is nearly complete.
- North and south foundation formwork complete.
- Culvert pieces placed April 11th.
- Grouting and waterproof membrane ongoing.
- Utility work ongoing. Waiting on Idaho Power.
- Grade work for the basin is nearly complete.
- North and south foundation formwork complete.
- Culvert pieces placed April 11th.
- Grouting and waterproof membrane ongoing.
This project is substantially complete
-
Share April 7, 2023 on Facebook
Share April 7, 2023 on X (formerly Twitter)
Share April 7, 2023 on Linkedin
Email April 7, 2023 link
- Utility work ongoing - waiting for Idaho Power.
- Grade work for the basin is nearly complete.
- North and south foundation form work complete.
- Placement of box culvert scheduled for early to mid April.
- Utility work ongoing - waiting for Idaho Power.
- Grade work for the basin is nearly complete.
- North and south foundation form work complete.
- Placement of box culvert scheduled for early to mid April.
This project is substantially complete
-
Share March 31, 2023 on Facebook
Share March 31, 2023 on X (formerly Twitter)
Share March 31, 2023 on Linkedin
Email March 31, 2023 link
- Utility work ongoing. Waiting on Idaho Power.
- Grade work for the basin is nearly complete.
- North and south foundation form work complete.
- Placement of box culvert scheduled for early-mid April.
- Utility work ongoing. Waiting on Idaho Power.
- Grade work for the basin is nearly complete.
- North and south foundation form work complete.
- Placement of box culvert scheduled for early-mid April.
This project is substantially complete
-
Share March 24, 2023 on Facebook
Share March 24, 2023 on X (formerly Twitter)
Share March 24, 2023 on Linkedin
Email March 24, 2023 link
- Utility work ongoing.
- Contractor closed Reutzel on March 6th.
- Grade work for the basin is nearly complete.
- North and south foundation form work complete.
- Placement of box culvert scheduled for early April.
- Utility work ongoing.
- Contractor closed Reutzel on March 6th.
- Grade work for the basin is nearly complete.
- North and south foundation form work complete.
- Placement of box culvert scheduled for early April.
This project is substantially complete
-
Share March 17, 2023 on Facebook
Share March 17, 2023 on X (formerly Twitter)
Share March 17, 2023 on Linkedin
Email March 17, 2023 link
- Utility work ongoing.
- Contractor closed Reutzel on March 6th.
- Grade work for the basin is nearly complete.
- North and south foundation form work - complete.
- Utility work ongoing.
- Contractor closed Reutzel on March 6th.
- Grade work for the basin is nearly complete.
- North and south foundation form work - complete.
This project is substantially complete
-
Share March 10, 2023 on Facebook
Share March 10, 2023 on X (formerly Twitter)
Share March 10, 2023 on Linkedin
Email March 10, 2023 link
- Contractor has removed the majority of the trees.
- Utility work ongoing.
- Contractor closed Reutzel on March 6th.
- Grade work for the basin is nearly complete. Contractor needs topsoil.
- North and south foundation formwork complete. Concrete placed March 6th.
- Contractor has removed the majority of the trees.
- Utility work ongoing.
- Contractor closed Reutzel on March 6th.
- Grade work for the basin is nearly complete. Contractor needs topsoil.
- North and south foundation formwork complete. Concrete placed March 6th.
This project is substantially complete
-
Share March 3, 2023 on Facebook
Share March 3, 2023 on X (formerly Twitter)
Share March 3, 2023 on Linkedin
Email March 3, 2023 link
- Contractor has removed the majority of the trees.
- Utility work ongoing.
- Contractor anticipates closing Reutzel on March 6th.
- Grade work for the basin is nearly complete.
- North and south foundation formwork complete. Waiting for rebar.
- Contractor has removed the majority of the trees.
- Utility work ongoing.
- Contractor anticipates closing Reutzel on March 6th.
- Grade work for the basin is nearly complete.
- North and south foundation formwork complete. Waiting for rebar.
This project is substantially complete
-
Share February 24, 2023 on Facebook
Share February 24, 2023 on X (formerly Twitter)
Share February 24, 2023 on Linkedin
Email February 24, 2023 link
- Contractor has removed the majority of the trees.
- Utility work ongoing.
- Road has been re-opened back up to traffic until the contractor can procure the precast structure.
- Grade work for the basin is nearly complete.
- Contractor has removed the majority of the trees.
- Utility work ongoing.
- Road has been re-opened back up to traffic until the contractor can procure the precast structure.
- Grade work for the basin is nearly complete.
This project is substantially complete
-
Share February 17, 2023 on Facebook
Share February 17, 2023 on X (formerly Twitter)
Share February 17, 2023 on Linkedin
Email February 17, 2023 link
- Contractor has removed the majority of the trees.
- Utility work ongoing.
- Road has been re-opened back up to traffic until the contractor can procure the precast structure.
- Grade work for the basin is nearly complete.
- Cofferdams have been installed and dewatering has started.
- Contractor has removed the majority of the trees.
- Utility work ongoing.
- Road has been re-opened back up to traffic until the contractor can procure the precast structure.
- Grade work for the basin is nearly complete.
- Cofferdams have been installed and dewatering has started.
This project is substantially complete