State Street, 8th Street to 4th Street

Share State Street, 8th Street to 4th Street on Facebook Share State Street, 8th Street to 4th Street on Twitter Share State Street, 8th Street to 4th Street on Linkedin Email State Street, 8th Street to 4th Street link

This project is substantially complete. 

  • Reconstruct State Street between 8th and 4th streets.
  • Upgrade all three traffic signals on this section of State St.
  • Construct bulb-outs for shorter pedestrian crossings and better visibility.
  • Add vegetated bioretention facilities for stormwater treatment.
  • Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
  • Reconstruct State Street between 8th and 4th streets.
  • Upgrade all three traffic signals on this section of State St.
  • Construct bulb-outs for shorter pedestrian crossings and better visibility.
  • Add vegetated bioretention facilities for stormwater treatment.
  • Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.

This project is substantially complete. 

  • July 17, 2024

    Share July 17, 2024 on Facebook Share July 17, 2024 on Twitter Share July 17, 2024 on Linkedin Email July 17, 2024 link
    17 Jul 2024

    An unforeseen utility conflict has been found at the State Street and 8th Street intersection. It is anticipated to take two months for the utility’s contractor to resolve. ACHD construction crews will now focus on the east end of the project.

    The State Street and 4th Street intersection will be paved first and then paving will continue moving west.

    As the intersections are paved, ACHD plans to open them to north/south traffic.

  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link
    12 Jul 2024
    • Project includes work on State Street between 4th Street and 8th Street - Veolia water work complete.
    • 8th Street electrical/fiber work ongoing.
    • Fiber swap is scheduled for the weekend of July 20th.
    • Contractor completed demo on State and 8th this week.
    • Excavation started this week, on the north side, in preparation for base materials.
  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link
    28 Jun 2024
    • Veolia water work started April 1st and is on-going.
    • State and 8th intersection work is complete.
    • 8th Street electrical work ongoing.
    • Contractor completed demo on State and 8th this week.
  • June 21, 2024

    Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link
    21 Jun 2024
    • Project includes work on State Street between 4th Street and 8th Street.
    • Veolia water work started April 1st and is on-going.
    • State and 8th intersection work is complete.
    • 8th Street electrical work ongoing.
    • Contractor completed demo on State and 8th this week.
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link
    14 Jun 2024

    Project includes work on State Street between 4th Street and 8th Street

    • Veolia water work started April 1st and is on-going
      • State and 8th intersection work is complete
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
    • Contractor started demo on State and 8th this week.
  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link
    07 Jun 2024
    • Veolia water work started April 1st and is on-going
      • State and 8th intersection work is complete minus a hydrant tieover
    • 8th Street utility work ongoing
    • Electrical work ongoing
    • Contractor expects to start demo on State and 8th as early as next week
  • May 31, 2024

    Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link
    31 May 2024
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
  • May 23, 2024

    Share May 23, 2024 on Facebook Share May 23, 2024 on Twitter Share May 23, 2024 on Linkedin Email May 23, 2024 link
    23 May 2024
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
    • Pole bases on 5th and 6th have been placed.
  • May 16, 2024

    Share May 16, 2024 on Facebook Share May 16, 2024 on Twitter Share May 16, 2024 on Linkedin Email May 16, 2024 link
    16 May 2024
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
    • Pole bases on 5th and 6th have been placed.
  • May 10, 2024

    Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link
    10 May 2024
    • Project includes work on State Street between 4th Street and 8th Street.
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.