State Street, 8th Street to 4th Street

Share State Street, 8th Street to 4th Street on Facebook Share State Street, 8th Street to 4th Street on Twitter Share State Street, 8th Street to 4th Street on Linkedin Email State Street, 8th Street to 4th Street link
  • Reconstruct State Street between 8th and 4th streets.
  • Upgrade all three traffic signals on this section of State St.
  • Construct bulb-outs for shorter pedestrian crossings and better visibility.
  • Add vegetated bioretention facilities for stormwater treatment.
  • Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
  • Reconstruct State Street between 8th and 4th streets.
  • Upgrade all three traffic signals on this section of State St.
  • Construct bulb-outs for shorter pedestrian crossings and better visibility.
  • Add vegetated bioretention facilities for stormwater treatment.
  • Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link
    • Veolia water work started April 1st and is on-going.
    • State and 8th intersection work is complete.
    • 8th Street electrical work ongoing.
    • Contractor completed demo on State and 8th this week.
  • June 21, 2024

    Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link
    • Project includes work on State Street between 4th Street and 8th Street.
    • Veolia water work started April 1st and is on-going.
    • State and 8th intersection work is complete.
    • 8th Street electrical work ongoing.
    • Contractor completed demo on State and 8th this week.
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link

    Project includes work on State Street between 4th Street and 8th Street

    • Veolia water work started April 1st and is on-going
      • State and 8th intersection work is complete
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
    • Contractor started demo on State and 8th this week.
  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link
    • Veolia water work started April 1st and is on-going
      • State and 8th intersection work is complete minus a hydrant tieover
    • 8th Street utility work ongoing
    • Electrical work ongoing
    • Contractor expects to start demo on State and 8th as early as next week
  • May 31, 2024

    Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
  • May 23, 2024

    Share May 23, 2024 on Facebook Share May 23, 2024 on Twitter Share May 23, 2024 on Linkedin Email May 23, 2024 link
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
    • Pole bases on 5th and 6th have been placed.
  • May 16, 2024

    Share May 16, 2024 on Facebook Share May 16, 2024 on Twitter Share May 16, 2024 on Linkedin Email May 16, 2024 link
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
    • Pole bases on 5th and 6th have been placed.
  • May 10, 2024

    Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link
    • Project includes work on State Street between 4th Street and 8th Street.
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
  • May 3, 2024

    Share May 3, 2024 on Facebook Share May 3, 2024 on Twitter Share May 3, 2024 on Linkedin Email May 3, 2024 link
    • Veolia water work started April 1st and is on-going.
    • 8 th Street utility work ongoing.
  • April 25, 2024

    Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link
    • Milling between 4th and 6th Streets is complete.
    • Veolia water work started April 1st and is on-going.
    • Milling between 6th and 8th Streets is complete.
Page last updated: 06 Sep 2024, 03:50 PM