State Street, 8th Street to 4th Street
Share State Street, 8th Street to 4th Street on Facebook
Share State Street, 8th Street to 4th Street on X (formerly Twitter)
Share State Street, 8th Street to 4th Street on Linkedin
Email State Street, 8th Street to 4th Street link
This project is substantially complete.
- Reconstruct State Street between 8th and 4th streets.
- Upgrade all three traffic signals on this section of State St.
- Construct bulb-outs for shorter pedestrian crossings and better visibility.
- Add vegetated bioretention facilities for stormwater treatment.
- Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
- Reconstruct State Street between 8th and 4th streets.
- Upgrade all three traffic signals on this section of State St.
- Construct bulb-outs for shorter pedestrian crossings and better visibility.
- Add vegetated bioretention facilities for stormwater treatment.
- Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
This project is substantially complete.
-
September 20, 2024
Share September 20, 2024 on Facebook Share September 20, 2024 on X (formerly Twitter) Share September 20, 2024 on Linkedin Email September 20, 2024 link- 8th Street electrical/fiber work ongoing.
- Idaho Power vault has been lowered.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St.
- South side of 5th complete.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work ongoing between 4th and 5th.
- Landscapers to follow.
- 8th Street electrical/fiber work ongoing.
- Idaho Power vault has been lowered.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St.
- South side of 5th complete.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work ongoing between 4th and 5th.
- Landscapers to follow.
This project is substantially complete.
-
September 13, 2024
Share September 13, 2024 on Facebook Share September 13, 2024 on X (formerly Twitter) Share September 13, 2024 on Linkedin Email September 13, 2024 link- 8th Street electrical/fiber work ongoing.
- Idaho Power vault needs to be lowered.
- IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St. South side of 5th complete.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work started between 4th and 5th.
- Landscapers to follow.
- 8th Street electrical/fiber work ongoing.
- Idaho Power vault needs to be lowered.
- IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St. South side of 5th complete.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work started between 4th and 5th.
- Landscapers to follow.
This project is substantially complete.
-
September 6, 2024
Share September 6, 2024 on Facebook Share September 6, 2024 on X (formerly Twitter) Share September 6, 2024 on Linkedin Email September 6, 2024 link- 8th Street electrical/fiber work ongoing.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St.
- South side of 5th will be paved on Friday September 6th.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work started between 4th and 5th. Landscapers to follow.
- 8th Street electrical/fiber work ongoing.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St.
- South side of 5th will be paved on Friday September 6th.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work started between 4th and 5th. Landscapers to follow.
This project is substantially complete.
-
August 30, 2024
Share August 30, 2024 on Facebook Share August 30, 2024 on X (formerly Twitter) Share August 30, 2024 on Linkedin Email August 30, 2024 link- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving started between 4th and 5th St.
- Power and fiber for signals ongoing.
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving started between 4th and 5th St.
- Power and fiber for signals ongoing.
This project is substantially complete.
-
August 23, 2024
Share August 23, 2024 on Facebook Share August 23, 2024 on X (formerly Twitter) Share August 23, 2024 on Linkedin Email August 23, 2024 link- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base.
- Prepping for concrete paving complete between 4th and 5th St.
- Contractor will be paving early morning starting August 22nd between 4th and 5th St.
- Power and fiber for signals ongoing.
- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base.
- Prepping for concrete paving complete between 4th and 5th St.
- Contractor will be paving early morning starting August 22nd between 4th and 5th St.
- Power and fiber for signals ongoing.
This project is substantially complete.
-
August 15, 2024
Share August 15, 2024 on Facebook Share August 15, 2024 on X (formerly Twitter) Share August 15, 2024 on Linkedin Email August 15, 2024 link- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base.
- Prepping for concrete paving ongoing – tentatively scheduled for August 21-22nd.
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base.
- Prepping for concrete paving ongoing – tentatively scheduled for August 21-22nd.
This project is substantially complete.
-
August 9, 2024
Share August 9, 2024 on Facebook Share August 9, 2024 on X (formerly Twitter) Share August 9, 2024 on Linkedin Email August 9, 2024 link- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Prepping for concrete paving ongoing.
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Prepping for concrete paving ongoing.
This project is substantially complete.
-
August 2, 2024
Share August 2, 2024 on Facebook Share August 2, 2024 on X (formerly Twitter) Share August 2, 2024 on Linkedin Email August 2, 2024 link- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Prepping for concrete paving ongoing.
- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Prepping for concrete paving ongoing.
This project is substantially complete.
-
July 26, 2024
Share July 26, 2024 on Facebook Share July 26, 2024 on X (formerly Twitter) Share July 26, 2024 on Linkedin Email July 26, 2024 link- Project includes work on State Street between 4th Street and 8th Street
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered.
- IP working with engineer consultant to retrofit box to meet new grades.
- Contractor completed demo on State and 8th.
- Excavation complete, on the north side, in preparation for base materials.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Project includes work on State Street between 4th Street and 8th Street
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered.
- IP working with engineer consultant to retrofit box to meet new grades.
- Contractor completed demo on State and 8th.
- Excavation complete, on the north side, in preparation for base materials.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
This project is substantially complete.
- Project includes work on State Street between 4th Street and 8th Street
-
July 19, 2024
Share July 19, 2024 on Facebook Share July 19, 2024 on X (formerly Twitter) Share July 19, 2024 on Linkedin Email July 19, 2024 link- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Contractor completed demo on State and 8th this week.
- Excavation started this week, on the north side, in preparation for base materials.
- Idaho Power underground work is ongoing.
- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Contractor completed demo on State and 8th this week.
- Excavation started this week, on the north side, in preparation for base materials.
- Idaho Power underground work is ongoing.
This project is substantially complete.
State Street 8th to 4th Design
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Community and Business Relations Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Sr. Project Manager
Phone 208-387-6100 Email connect@achdidaho.org