Ustick Road, Black Cat Road to Ten Mile Road
This project is substantially complete.
The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.
Ustick, Black Cat to Ten Mile
- Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
- Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
- Add a traffic signal at Naomi Avenue.
- Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
- Upgrade stormwater facilities and replace irrigation pipes.
Ustick and Black Cat Intersection
- Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
- Add dedicated right and left turn lanes on all approaches.
- Install curb, gutter, and multi-use pathways.
The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.
Ustick, Black Cat to Ten Mile
- Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
- Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
- Add a traffic signal at Naomi Avenue.
- Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
- Upgrade stormwater facilities and replace irrigation pipes.
Ustick and Black Cat Intersection
- Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
- Add dedicated right and left turn lanes on all approaches.
- Install curb, gutter, and multi-use pathways.
This project is substantially complete.
-
July 11, 2025
Share July 11, 2025 on Facebook Share July 11, 2025 on Twitter Share July 11, 2025 on Linkedin Email July 11, 2025 link- Black Cat Road is back open, north of Ustick Road – at Aspenstone.
- Black Cat Road is open south of Ustick Road.
- Aspenstone is back open for one week while Elmstone is closed.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward. Due to the amount of concrete this project requires, and other very large projects in the area (such as Micron), the contractor will be doing early morning placements to ensure the project receives concrete.
- HDPE Pipe welding is complete for the City of Meridian’s sewer bypass.
- City of Meridian bypass is scheduled to start Monday, July 14.
- Black Cat Road is back open, north of Ustick Road – at Aspenstone.
- Black Cat Road is open south of Ustick Road.
- Aspenstone is back open for one week while Elmstone is closed.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward. Due to the amount of concrete this project requires, and other very large projects in the area (such as Micron), the contractor will be doing early morning placements to ensure the project receives concrete.
- HDPE Pipe welding is complete for the City of Meridian’s sewer bypass.
- City of Meridian bypass is scheduled to start Monday, July 14.
This project is substantially complete.
-
July 2, 2025
Share July 2, 2025 on Facebook Share July 2, 2025 on Twitter Share July 2, 2025 on Linkedin Email July 2, 2025 link- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install. Curb and gutter and sidewalk placements ongoing on the north side of Ustick. Concrete paving placements will be ongoing. Placement schedule will be every Monday and Wednesday moving forward. Due to the amount of concrete this project requires, and other very large projects in the area (such as Micron), the contractor will be doing early morning placements to ensure the project receives concrete.
- HDPE Pipe welding is complete for the City of Meridian’s sewer bypass.
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install. Curb and gutter and sidewalk placements ongoing on the north side of Ustick. Concrete paving placements will be ongoing. Placement schedule will be every Monday and Wednesday moving forward. Due to the amount of concrete this project requires, and other very large projects in the area (such as Micron), the contractor will be doing early morning placements to ensure the project receives concrete.
- HDPE Pipe welding is complete for the City of Meridian’s sewer bypass.
This project is substantially complete.
-
June 26, 2026
Share June 26, 2026 on Facebook Share June 26, 2026 on Twitter Share June 26, 2026 on Linkedin Email June 26, 2026 link- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: o Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing. Placement schedule will be every Monday and Wednesday moving forward.
- Due to the amount of concrete this project requires, and other very large projects in the area (such as Micron), the contractor will be doing early morning placements to ensure the project receives concrete. HDPE Pipe welding is complete for the City of Meridian’s sewer bypass.
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: o Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing. Placement schedule will be every Monday and Wednesday moving forward.
- Due to the amount of concrete this project requires, and other very large projects in the area (such as Micron), the contractor will be doing early morning placements to ensure the project receives concrete. HDPE Pipe welding is complete for the City of Meridian’s sewer bypass.
This project is substantially complete.
-
June 20, 2025
Share June 20, 2025 on Facebook Share June 20, 2025 on Twitter Share June 20, 2025 on Linkedin Email June 20, 2025 link- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open:
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation:
- Irrigation is complete for the season.
- Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward.
- HDPE Pipe welding is ongoing for the City of Meridian’s sewer bypass.
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open:
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation:
- Irrigation is complete for the season.
- Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward.
- HDPE Pipe welding is ongoing for the City of Meridian’s sewer bypass.
This project is substantially complete.
-
June 13, 2025
Share June 13, 2025 on Facebook Share June 13, 2025 on Twitter Share June 13, 2025 on Linkedin Email June 13, 2025 link- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: Irrigation is complete for the season.
- Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install. Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward.
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: Irrigation is complete for the season.
- Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install. Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward.
This project is substantially complete.
-
June 6, 2025
Share June 6, 2025 on Facebook Share June 6, 2025 on Twitter Share June 6, 2025 on Linkedin Email June 6, 2025 link- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete.
- Roadway and sidewalk demo complete, and grade prep complete on the north side of Ustick for curb, gutter, and sidewalk.
- Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward.
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is nearly complete.
- Roadway and sidewalk demo complete, and grade prep complete on the north side of Ustick for curb, gutter, and sidewalk.
- Eightmile irrigation: Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter and sidewalk placements ongoing on the north side of Ustick.
- Concrete paving placements will be ongoing.
- Placement schedule will be every Monday and Wednesday moving forward.
This project is substantially complete.
-
May 30, 2025
Share May 30, 2025 on Facebook Share May 30, 2025 on Twitter Share May 30, 2025 on Linkedin Email May 30, 2025 link- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo complete, and grade prep ongoing on the north side of Ustick for curb, gutter, and sidewalk.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter placements ongoing.
- First concrete placement on the north side of Black Cat happened this week.
- Placement schedule will be every Monday and Wednesday moving forward.
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo complete, and grade prep ongoing on the north side of Ustick for curb, gutter, and sidewalk.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter placements ongoing.
- First concrete placement on the north side of Black Cat happened this week.
- Placement schedule will be every Monday and Wednesday moving forward.
This project is substantially complete.
-
May 23, 2025
Share May 23, 2025 on Facebook Share May 23, 2025 on Twitter Share May 23, 2025 on Linkedin Email May 23, 2025 link- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo complete, and grade prep ongoing on the north side of Ustick for curb, gutter, and sidewalk.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install. Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter placements ongoing.
- Concrete paving starting May 28th.
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo complete, and grade prep ongoing on the north side of Ustick for curb, gutter, and sidewalk.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install. Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter placements ongoing.
- Concrete paving starting May 28th.
This project is substantially complete.
-
May 16, 2025
Share May 16, 2025 on Facebook Share May 16, 2025 on Twitter Share May 16, 2025 on Linkedin Email May 16, 2025 link- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo complete, and grade prep ongoing on the north side of Ustick for curb, gutter, and sidewalk.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter started this week.
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo complete, and grade prep ongoing on the north side of Ustick for curb, gutter, and sidewalk.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.
- Curb and gutter started this week.
This project is substantially complete.
-
May 8, 2025
Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 link- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo complete, and grade prep ongoing on the north side of Ustick for curb, gutter, and sidewalk.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone. Curb and gutter is scheduled for next week.
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Aspenstone Street is closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo complete, and grade prep ongoing on the north side of Ustick for curb, gutter, and sidewalk.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install.
- Contractor is continuing site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone. Curb and gutter is scheduled for next week.
This project is substantially complete.
Spring 2023 Public Outreach
-
Spring 2023 Public Outreach
-
Infographic, Spring 2023 Outreach (Ustick, Black Cat to Ten Mile) (222 KB) (pdf)
-
Comment Summary, Spring 2023 (Ustick, Black Cat to Ten Mile) (1.29 MB) (pdf)
-
Informational Slides (Ustick, Black Cat to Ten Mile) (18.9 MB) (pdf)
-
Project Design (Ustick, Black Cat to Ten Mile) (11.6 MB) (pdf)
-
Typical Sections (Ustick, Black Cat to Ten Mile) (559 KB) (pdf)
-
Timeline
-
2021
Ustick Road, Black Cat Road to Ten Mile Road has finished this stageDesign started
-
Fall 2022
Ustick Road, Black Cat Road to Ten Mile Road has finished this stagePublic input opportunity #1
-
Spring 2023
Ustick Road, Black Cat Road to Ten Mile Road has finished this stagePublic input opportunity #2
-
2024
Ustick Road, Black Cat Road to Ten Mile Road has finished this stageBegin purchasing property necessary for project
-
November 2024
Ustick Road, Black Cat Road to Ten Mile Road is currently at this stageStart construction
-
Spring 2026
this is an upcoming stage for Ustick Road, Black Cat Road to Ten Mile RoadFinish construction
Related projects
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Sr. Project Manager
Phone 208-387-6100 Email connect@achdidaho.org