- 9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work is complete.
- Brick replacement is on-going.
- Removal of existing asphalt is complete.
- Concrete paving is scheduled.
- 9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work is complete.
- Brick replacement is on-going.
- Removal of existing asphalt is complete.
- Concrete paving is scheduled.
This project is substantially complete.
Share March 29, 2024 on Facebook
Share March 29, 2024 on X (formerly Twitter)
Share March 29, 2024 on Linkedin
Email March 29, 2024 link
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work is scheduled to be done the week of March 25th.
- Removal of existing asphalt is scheduled to start March 28th.
- Concrete paving is scheduled to start the week of April 1st.
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work is scheduled to be done the week of March 25th.
- Removal of existing asphalt is scheduled to start March 28th.
- Concrete paving is scheduled to start the week of April 1st.
This project is substantially complete.
Share March 21, 2024 on Facebook
Share March 21, 2024 on X (formerly Twitter)
Share March 21, 2024 on Linkedin
Email March 21, 2024 link
- 9th Street, Idaho Street to Bannock Street - Waterline work by Veolia is complete. ACHD’s project started March 4th. 9th Street will be closed during the work. The existing signal at 9th Street & Bannock Street has been removed. New signal installation is on-going. Concrete sidewalk work is scheduled to be done the week of March 25th . Removal of existing asphalt is scheduled to start March 26th.
- 9th Street, Idaho Street to Bannock Street - Waterline work by Veolia is complete. ACHD’s project started March 4th. 9th Street will be closed during the work. The existing signal at 9th Street & Bannock Street has been removed. New signal installation is on-going. Concrete sidewalk work is scheduled to be done the week of March 25th . Removal of existing asphalt is scheduled to start March 26th.
This project is substantially complete.
Share March 15, 2024 on Facebook
Share March 15, 2024 on X (formerly Twitter)
Share March 15, 2024 on Linkedin
Email March 15, 2024 link
- 9th Street, Idaho Street to Bannock Street - Waterline work by Veolia is complete. ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete demolition is nearly complete.
- Concrete sidewalk work is on-going.
- Alley work on the west side of 9th Street started March 14th.
- The alley is expected to reopen the afternoon of March 18th.
- 9th Street, Idaho Street to Bannock Street - Waterline work by Veolia is complete. ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete demolition is nearly complete.
- Concrete sidewalk work is on-going.
- Alley work on the west side of 9th Street started March 14th.
- The alley is expected to reopen the afternoon of March 18th.
This project is substantially complete.
Share March 8, 2024 on Facebook
Share March 8, 2024 on X (formerly Twitter)
Share March 8, 2024 on Linkedin
Email March 8, 2024 link
9th and Bannock
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th .
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- Concrete demolition on-going.
- Concrete pour today for signal bases.
- Concrete sidewalk work starts next week.
9th and Bannock
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th .
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- Concrete demolition on-going.
- Concrete pour today for signal bases.
- Concrete sidewalk work starts next week.
This project is substantially complete.
Share March 1, 2024 on Facebook
Share March 1, 2024 on X (formerly Twitter)
Share March 1, 2024 on Linkedin
Email March 1, 2024 link
- 9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project is anticipated to begin March 4th.
- 9th Street closed between Idaho Street to Bannock Street.

- 9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project is anticipated to begin March 4th.
- 9th Street closed between Idaho Street to Bannock Street.

This project is substantially complete.
Share February 23, 2024 on Facebook
Share February 23, 2024 on X (formerly Twitter)
Share February 23, 2024 on Linkedin
Email February 23, 2024 link
- 9th Street, Idaho Street to Bannock Street - Waterline work by Veolia is complete.
- ACHD’s project is anticipated to begin March 4th.
- 9th Street will be closed during the work.
- 9th Street, Idaho Street to Bannock Street - Waterline work by Veolia is complete.
- ACHD’s project is anticipated to begin March 4th.
- 9th Street will be closed during the work.
This project is substantially complete.
Share February 16, 2024 on Facebook
Share February 16, 2024 on X (formerly Twitter)
Share February 16, 2024 on Linkedin
Email February 16, 2024 link
- 9th Street, Idaho Street to Bannock Street - Waterline work by Veolia is complete.
- ACHD’s project is anticipated to begin March 4th
- 9th Street, Idaho Street to Bannock Street - Waterline work by Veolia is complete.
- ACHD’s project is anticipated to begin March 4th
This project is substantially complete.
Share December 15, 2023 on Facebook
Share December 15, 2023 on X (formerly Twitter)
Share December 15, 2023 on Linkedin
Email December 15, 2023 link
- 9th Street, Idaho Street to Bannock Street -
- Waterline work by Veolia is complete.
- ACHD’s project is postponed to 2024.
- Maple Grove Road - I-84 Overpass to Franklin Road
- Concrete work is complete.
- Roadway work is postponed to 2024
- 9th Street, Idaho Street to Bannock Street -
- Waterline work by Veolia is complete.
- ACHD’s project is postponed to 2024.
- Maple Grove Road - I-84 Overpass to Franklin Road
- Concrete work is complete.
- Roadway work is postponed to 2024
This project is substantially complete.
Share December 8, 2023 on Facebook
Share December 8, 2023 on X (formerly Twitter)
Share December 8, 2023 on Linkedin
Email December 8, 2023 link
- 9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project will be postponed to 2024.
- 20th Street, Lemp Street to Irene Street
- Asphalt paving complete.
- Minor work remains.
- Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Castle Hill Way, Castle Drive to Drawbridge Drive
- Drawbridge Drive, west of Crimson Drive to Turret Way
- Turret Way, Drawbridge Drive to Castle Drive
- Morris Hill Road, west of Liberty Street to Hartman Street
- Spaulding Street, Philippi Street to Orchard Street
- Roosevelt Street, Emerald Street to Irving Street
- Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
- Roadway work is delayed to spring 2024.
- Amity Road, Enterprise Street to Production Avenue
- Enterprise Street,
- 9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project will be postponed to 2024.
- 20th Street, Lemp Street to Irene Street
- Asphalt paving complete.
- Minor work remains.
- Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Castle Hill Way, Castle Drive to Drawbridge Drive
- Drawbridge Drive, west of Crimson Drive to Turret Way
- Turret Way, Drawbridge Drive to Castle Drive
- Morris Hill Road, west of Liberty Street to Hartman Street
- Spaulding Street, Philippi Street to Orchard Street
- Roosevelt Street, Emerald Street to Irving Street
- Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
- Roadway work is delayed to spring 2024.
- Amity Road, Enterprise Street to Production Avenue
- Enterprise Street,
This project is substantially complete.