Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st
- Remaining work includes manhole adjustments and permanent pavement markings.
- The pedestrian signal at Shoup was activated on June 11th.
Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st
- Remaining work includes manhole adjustments and permanent pavement markings.
- The pedestrian signal at Shoup was activated on June 11th.
This project is substantially complete.
Share June 7, 2024 on Facebook
Share June 7, 2024 on X (formerly Twitter)
Share June 7, 2024 on Linkedin
Email June 7, 2024 link
Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st and includes manhole adjustments, permanent pavement markings, and activation of the pedestrian signal at Shoup.
Maple Grove Road, I-84 Overpass to Franklin Road
- Asphalt paving is complete.
- One lane in each direction was opened on June 7th.
- Remaining work will be on-going through June 21st and includes manhole adjustments, permanent pavement markings, and activation of the pedestrian signal at Shoup.
This project is substantially complete.
Share May 31, 2024 on Facebook
Share May 31, 2024 on X (formerly Twitter)
Share May 31, 2024 on Linkedin
Email May 31, 2024 link
- Roadway work began May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.
- Existing asphalt has been removed.
- Contractor is re-grading the base gravels.
- Asphalt paving is scheduled to start the week of June 3rd.
- Roadway work began May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.
- Existing asphalt has been removed.
- Contractor is re-grading the base gravels.
- Asphalt paving is scheduled to start the week of June 3rd.
This project is substantially complete.
Share May 23, 2024 on Facebook
Share May 23, 2024 on X (formerly Twitter)
Share May 23, 2024 on Linkedin
Email May 23, 2024 link
Maple Grove - I84 Work
- Concrete work is complete.
- Work anticipated to begin May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.
Maple Grove - I84 Work
- Concrete work is complete.
- Work anticipated to begin May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.
This project is substantially complete.
Share May 16, 2024 - Detour Map & Update Maple Grove on Facebook
Share May 16, 2024 - Detour Map & Update Maple Grove on X (formerly Twitter)
Share May 16, 2024 - Detour Map & Update Maple Grove on Linkedin
Email May 16, 2024 - Detour Map & Update Maple Grove link
- Concrete work is complete.
- Work anticipated to begin May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.

- Concrete work is complete.
- Work anticipated to begin May 28th.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed at Franklin Road.

This project is substantially complete.
Share May 10, 2024 on Facebook
Share May 10, 2024 on X (formerly Twitter)
Share May 10, 2024 on Linkedin
Email May 10, 2024 link
- Maple Grove Road, I-84 Overpass to Franklin Road -
- Concrete work is complete.
- Roadway work is postponed to 2024.
- Work anticipated to begin as early as June 3rd.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed through the work zone.
- Maple Grove Road, I-84 Overpass to Franklin Road -
- Concrete work is complete.
- Roadway work is postponed to 2024.
- Work anticipated to begin as early as June 3rd.
- Maple Grove Road will be closed for approximately 4 weeks.
- Local traffic will be allowed through the work zone.
This project is substantially complete.
Share May 3, 2024 on Facebook
Share May 3, 2024 on X (formerly Twitter)
Share May 3, 2024 on Linkedin
Email May 3, 2024 link
9th and Bannock has been completed.
9th and Bannock has been completed.
This project is substantially complete.
Share April 25, 2024 on Facebook
Share April 25, 2024 on X (formerly Twitter)
Share April 25, 2024 on Linkedin
Email April 25, 2024 link
- 9th Street, Idaho Street to Bannock Street
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- Concrete sidewalk work and brick work is complete.
- Concrete paving was completed April 19th.
- Remaining work includes concrete curing, sealing joints, installation of pavement markings, and traffic signal installation/activation. Some work is weather dependent.
- Anticipate opening the road at least partially on May 3rd.
- 9th Street, Idaho Street to Bannock Street
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- Concrete sidewalk work and brick work is complete.
- Concrete paving was completed April 19th.
- Remaining work includes concrete curing, sealing joints, installation of pavement markings, and traffic signal installation/activation. Some work is weather dependent.
- Anticipate opening the road at least partially on May 3rd.
This project is substantially complete.
Share April 19, 2024 on Facebook
Share April 19, 2024 on X (formerly Twitter)
Share April 19, 2024 on Linkedin
Email April 19, 2024 link
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- Concrete sidewalk work and brick work is complete.
- Concrete paving is anticipated to be complete April 19th.
- Remaining work includes concrete curing, sealing joints, installation of pavement markings, and traffic signal installation/activation.
- Some work is weather dependent
9th Street, Idaho Street to Bannock Street
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th.
- 9th Street will be closed during the work.
- Concrete sidewalk work and brick work is complete.
- Concrete paving is anticipated to be complete April 19th.
- Remaining work includes concrete curing, sealing joints, installation of pavement markings, and traffic signal installation/activation.
- Some work is weather dependent
This project is substantially complete.
Share April 12, 2024 on Facebook
Share April 12, 2024 on X (formerly Twitter)
Share April 12, 2024 on Linkedin
Email April 12, 2024 link
9th and Bannock
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th .
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work and brick work is complete.
- Removal of existing asphalt is complete.
- Concrete paving started April 12th and will be on-going for the next two weeks.
- Work is weather dependent.
9th and Bannock
- Waterline work by Veolia is complete.
- ACHD’s project started March 4th .
- 9th Street will be closed during the work.
- The existing signal at 9th Street & Bannock Street has been removed.
- New signal installation is on-going.
- Concrete sidewalk work and brick work is complete.
- Removal of existing asphalt is complete.
- Concrete paving started April 12th and will be on-going for the next two weeks.
- Work is weather dependent.
This project is substantially complete.