2025 Meridian Downtown Pavement and Pedestrian Improvements

Share 2025 Meridian Downtown Pavement and Pedestrian Improvements on Facebook Share 2025 Meridian Downtown Pavement and Pedestrian Improvements on Twitter Share 2025 Meridian Downtown Pavement and Pedestrian Improvements on Linkedin Email 2025 Meridian Downtown Pavement and Pedestrian Improvements link

This Project is substantially complete

The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.

Work could include

  • Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
  • Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
  • Adding crosswalk markings for school walk route crossings
  • Stormwater and irrigation upgrades to improve flows

Street Segments


To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org.

Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org


The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.

Work could include

  • Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
  • Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
  • Adding crosswalk markings for school walk route crossings
  • Stormwater and irrigation upgrades to improve flows

Street Segments


To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org.

Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org


This Project is substantially complete

  • November 20, 2025

    Share November 20, 2025 on Facebook Share November 20, 2025 on Twitter Share November 20, 2025 on Linkedin Email November 20, 2025 link
    • Minor punch list items remain.
  • November 14, 2025

    Share November 14, 2025 on Facebook Share November 14, 2025 on Twitter Share November 14, 2025 on Linkedin Email November 14, 2025 link

    Project includes work on the following segments:

    • Broadway Ave, E 3rd Street to E 6th Street - COMPLETE
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE
    • Idaho Ave, W 8th St to Meridian Rd - Minor concrete and landscape items remain. Projected completion date 11/26.
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE
    • Washington St, NW 7th Street to Meridian Rd - COMPLETE
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE
    • E 4th Street, Broadway Ave to State Ave - COMPLETE
    • W 2nd Street, Cherry Ave to Cherry Lane - Sidewalk and landscaping remain.
    • W 3rd Street, Pine Ave to north end - COMPLETE
    • NW 4th Street, Broadway Ave to Maple Ave - COMPLETE
    • NW 6th Street, Carlton Ave to Washington St - COMPLETE
    • NW 7th Street, McFadden Ave to Washington St - COMPLETE
  • November 7, 2025

    Share November 7, 2025 on Facebook Share November 7, 2025 on Twitter Share November 7, 2025 on Linkedin Email November 7, 2025 link

    Project includes work on the following segments:

    • Broadway Ave, E 3rd Street to E 6th Street - COMPLETE
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE
    • Idaho Ave, W 8th St to Meridian Rd - Minor concrete and landscape items remain.
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE
    • Washington St, NW 7th Street to Meridian Rd - COMPLETE
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE
    • E 4th Street, Broadway Ave to State Ave - COMPLETE
    • W 2nd Street, Cherry Ave to Cherry Lane - Sidewalk and landscaping remain.
    • W 3rd Street, Pine Ave to north end - COMPLETE
    • NW 4th Street, Broadway Ave to Maple Ave - COMPLETE
    • NW 6th Street, Carlton Ave to Washington St - COMPLETE
    • NW 7th Street, McFadden Ave to Washington St - COMPLETE
  • October 31, 2025

    Share October 31, 2025 on Facebook Share October 31, 2025 on Twitter Share October 31, 2025 on Linkedin Email October 31, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Complete
    • Cherry Ave, NW 4th Street to Meridian Rd - Complete
    • Idaho Ave, W 8th St to Meridian Rd -
    • Broadway Ave, E 3rd Street to E 6th Street - Complete
    • Cherry Ave, NW 4th Street to Meridian Rd - Complete
    • Idaho Ave, W 8th St to Meridian Rd - Paving complete from 3rd west. Sidewalk, curb and gutter ongoing to the east. Next pave date is scheduled for Oct 30 and 31. Landscaping and sidewalk work ongoing.
    • Maple Ave, W 1st Street to Meridian Rd - Complete
    • Washington St, NW 7th Street to Meridian Rd - Complete
    • E 2nd Street, Idaho Ave to Pine Ave - Complete
    • E 4th Street, Broadway Ave to State Ave - Complete
    • W 2nd Street, Cherry Ave to Cherry Lane - Sidewalk and landscaping remain.
    • W 3rd Street, Pine Ave to north end - Complete
    • NW 4th Street, Broadway Ave to Maple Ave - Complete
    • NW 6th Street, Carlton Ave to Washington St - Complete
    • NW 7th Street, McFadden Ave to Washington St - Complete
    • Maple Ave, W 1st Street to Meridian Rd - Complete
    • Washington St, NW 7th Street to Meridian Rd - Complete
    • E 2nd Street, Idaho Ave to Pine Ave - Complete
    • E 4th Street, Broadway Ave to State Ave - Complete
    • W 2nd Street, Cherry Ave to Cherry Lane - Sidewalk and landscaping remain.
    • W 3rd Street, Pine Ave to north end - Complete
    • NW 4th Street, Broadway Ave to Maple Ave - Complete
    • NW 6th Street, Carlton Ave to Washington St - Complete
    • NW 7th Street, McFadden Ave to Washington St - Complete
  • October 24, 2025

    Share October 24, 2025 on Facebook Share October 24, 2025 on Twitter Share October 24, 2025 on Linkedin Email October 24, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Complete
    • Cherry Ave, NW 4th Street to Meridian Rd - Complete
    • Idaho Ave, W 8th St to Meridian Rd - Paving complete from 3rd west. Sidewalk, curb and gutter ongoing to the east. Next pave date is scheduled for Oct 30 and 31. Landscaping and sidewalk work ongoing.
    • Maple Ave, W 1st Street to Meridian Rd - Complete
    • Washington St, NW 7th Street to Meridian Rd - Complete
    • E 2nd Street, Idaho Ave to Pine Ave - Complete
    • E 4th Street, Broadway Ave to State Ave - Complete
    • W 2nd Street, Cherry Ave to Cherry Lane - Sidewalk and landscaping remain.
    • W 3rd Street, Pine Ave to north end - Complete
    • NW 4th Street, Broadway Ave to Maple Ave - Complete
    • NW 6th Street, Carlton Ave to Washington St - Complete
    • NW 7th Street, McFadden Ave to Washington St - Complete
  • October 17, 2025

    Share October 17, 2025 on Facebook Share October 17, 2025 on Twitter Share October 17, 2025 on Linkedin Email October 17, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Complete
    • Cherry Ave, NW 4th Street to Meridian Rd - Complete
    • Idaho Ave, W 8th St to Meridian Rd - Paving complete from 3rd west. Sidewalk, curb and gutter ongoing to the east. Next pave date is scheduled for Oct 30 and 31. Landscaping and sidewalk work ongoing.
    • Maple Ave, W 1st Street to Meridian Rd - Complete
    • Washington St, NW 7th Street to Meridian Rd - Complete
    • E 2nd Street, Idaho Ave to Pine Ave - Complete
    • E 4th Street, Broadway Ave to State Ave - Complete
    • W 2nd Street, Cherry Ave to Cherry Lane - Sidewalk and landscaping remain.
    • W 3rd Street, Pine Ave to north end - Complete
    • NW 4th Street, Broadway Ave to Maple Ave - Complete
    • NW 6th Street, Carlton Ave to Washington St - Complete
    • NW 7th Street, McFadden Ave to Washington St - Complete
  • October 10, 2025

    Share October 10, 2025 on Facebook Share October 10, 2025 on Twitter Share October 10, 2025 on Linkedin Email October 10, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Complete
    • Cherry Ave, NW 4th Street to Meridian Rd - Complete
    • Idaho Ave, W 8th St to Meridian Rd - Paving complete from 3rd west. Sidewalk, curb and gutter ongoing to the east. Next pave date is scheduled for Oct 15 and 16. Landscaping and sidewalk work ongoing.
    • Maple Ave, W 1st Street to Meridian Rd - Complete
    • Washington St, NW 7th Street to Meridian Rd - Complete
    • E 2nd Street, Idaho Ave to Pine Ave - Complete
    • E 4th Street, Broadway Ave to State Ave - Complete
    • W 2nd Street, Cherry Ave to Cherry Lane - Paved on September 30th. Landscape repair ongoing.
    • W 3rd Street, Pine Ave to north end - Complete
    • NW 4th Street, Broadway Ave to Maple Ave - Complete
    • NW 6th Street, Carlton Ave to Washington St - Complete
    • NW 7th Street, McFadden Ave to Washington St - Complete
  • October 2, 2025

    Share October 2, 2025 on Facebook Share October 2, 2025 on Twitter Share October 2, 2025 on Linkedin Email October 2, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Complete
    • Cherry Ave, NW 4th Street to Meridian Rd - Complete
    • Idaho Ave, W 8th St to Meridian Rd - Paving the west end the week of October 13th. Sidewalk, curb and gutter ongoing to the east.
    • Maple Ave, W 1st Street to Meridian Rd - Complete
    • Washington St, NW 7th Street to Meridian Rd - Complete
    • E 2nd Street, Idaho Ave to Pine Ave - Complete
    • E 4th Street, Broadway Ave to State Ave - Complete
    • W 2nd Street, Cherry Ave to Cherry Lane - Paved on September 30th. Landscape repair ongoing.
    • W 3rd Street, Pine Ave to north end - Complete
    • NW 4th Street, Broadway Ave to Maple Ave - Complete
    • NW 6th Street, Carlton Ave to Washington St - Complete
    • NW 7th Street, McFadden Ave to Washington St - Complete
  • September 26, 2025

    Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - Complete
    • Cherry Ave, NW 4th Street to Meridian Rd - Complete
    • Idaho Ave, W 8th St to Meridian Rd - Paving the west end on September 17th. Sidewalk, curb and gutter ongoing to the east.
    • Maple Ave, W 1st Street to Meridian Rd - Complete
    • Washington St, NW 7th Street to Meridian Rd
    • E 2nd Street, Idaho Ave to Pine Ave - Complete
    • E 4th Street, Broadway Ave to State Ave - Complete
    • W 2nd Street, Cherry Ave to Cherry Lane - Grade prep and curb and gutter install ongoing. Sidewalk curb and gutter install ongoing.
    • W 3rd Street, Pine Ave to north end - Complete
    • NW 4th Street, Broadway Ave to Maple Ave - Complete
    • NW 6th Street, Carlton Ave to Washington St - Complete
    • NW 7th Street, McFadden Ave to Washington St - Complete
  • September 19, 2025

    Share September 19, 2025 on Facebook Share September 19, 2025 on Twitter Share September 19, 2025 on Linkedin Email September 19, 2025 link
    • Broadway Ave, E 3rd Street to E 6th Street - COMPLETE
    • Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE
    • Idaho Ave, W 8th St to Meridian Rd - Paving the west end on September 17th. Sidewalk, curb and gutter ongoing to the east.
    • Maple Ave, W 1st Street to Meridian Rd - COMPLETE
    • Washington St, NW 7th Street to Meridian Rd - COMPLETE
    • E 2nd Street, Idaho Ave to Pine Ave - COMPLETE
    • E 4th Street, Broadway Ave to State Ave - COMPLETE
    • W 2nd Street, Cherry Ave to Cherry Lane - Grade prep and curb and gutter install ongoing. Sidewalk curb and gutter install ongoing.
    • W 3rd Street, Pine Ave to north end - COMPLETE
    • NW 4th Street, Broadway Ave to Maple Ave - COMPLETE
    • NW 6th Street, Carlton Ave to Washington St - COMPLETE
    • NW 7th Street, McFadden Ave to Washington St - COMPLETE