2025 Meridian Downtown Pavement and Pedestrian Improvements
This Project is substantially complete
The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.
Work could include
- Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
- Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
- Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
- Adding crosswalk markings for school walk route crossings
- Stormwater and irrigation upgrades to improve flows
Street Segments
- Broadway Avenue, East 3rd Street to East 6th Street
- Cherry Avenue, West 4th Street to Meridian Road
- East 2nd Street, Idaho Avenue to Pine Avenue
- East 4th Street, Broadway Avenue to State Avenue
- Idaho Avenue, West 8th Street to Meridian Road
- Maple Avenue, West 1st Street to Meridian Road
- West 2nd Street, Cherry Avenue to Cherry Lane
- West 3rd Street, Pine Street to North End
- West 4th Street, Broadway Avenue to North of Maple Avenue
- West 5th Street, Carlton Avenue to Washington Street
- West 6th Street, Carlton Avenue to Washington Street
- West 7th Street, Washington Street to the pathway South of McFadden Avenue
- Washington Street, West 7th Street to Meridian Road
To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org.
Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org
The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.
Work could include
- Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
- Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
- Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
- Adding crosswalk markings for school walk route crossings
- Stormwater and irrigation upgrades to improve flows
Street Segments
- Broadway Avenue, East 3rd Street to East 6th Street
- Cherry Avenue, West 4th Street to Meridian Road
- East 2nd Street, Idaho Avenue to Pine Avenue
- East 4th Street, Broadway Avenue to State Avenue
- Idaho Avenue, West 8th Street to Meridian Road
- Maple Avenue, West 1st Street to Meridian Road
- West 2nd Street, Cherry Avenue to Cherry Lane
- West 3rd Street, Pine Street to North End
- West 4th Street, Broadway Avenue to North of Maple Avenue
- West 5th Street, Carlton Avenue to Washington Street
- West 6th Street, Carlton Avenue to Washington Street
- West 7th Street, Washington Street to the pathway South of McFadden Avenue
- Washington Street, West 7th Street to Meridian Road
To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org.
Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org
This Project is substantially complete
-
April 25, 2025
Share April 25, 2025 on Facebook Share April 25, 2025 on X (formerly Twitter) Share April 25, 2025 on Linkedin Email April 25, 2025 linkProject includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Prepping for concrete. Grade work started.
- Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
- E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west. Demo ongoing.
- W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
- W 3rd Street, Pine Ave to north end - Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St - Demo started.
- NW 7th Street, McFadden Ave to Washington St - Demo started.
- *Irrigation work complete.
Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Prepping for concrete. Grade work started.
- Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - COMPLETE.
- E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west. Demo ongoing.
- W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
- W 3rd Street, Pine Ave to north end - Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St - Demo started.
- NW 7th Street, McFadden Ave to Washington St - Demo started.
- *Irrigation work complete.
This Project is substantially complete
-
April 17, 2025
Share April 17, 2025 on Facebook Share April 17, 2025 on X (formerly Twitter) Share April 17, 2025 on Linkedin Email April 17, 2025 linkProject includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - COMPLETE. Asphalt paving this week.
- E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west.
- W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
- W 3rd Street, Pine Ave to north end.Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St
- NW 7th Street, McFadden and Washington
- *Irrigation work complete.
Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - COMPLETE
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - COMPLETE.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - COMPLETE. Asphalt paving this week.
- E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west.
- W 2nd Street, Cherry Ave to Cherry Lane - COMPLETE.
- W 3rd Street, Pine Ave to north end.Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St
- NW 7th Street, McFadden and Washington
- *Irrigation work complete.
This Project is substantially complete
-
April 11, 2025
Share April 11, 2025 on Facebook Share April 11, 2025 on X (formerly Twitter) Share April 11, 2025 on Linkedin Email April 11, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Reopening at the end of this week.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Reopening at the end of this week.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving this week.
- E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west.
- W 2nd Street, Cherry Ave to Cherry Lane - Reopening at the end of this week.
- W 3rd Street, Pine Ave to north end - Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Reopening at the end of this week.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Reopening at the end of this week.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving this week.
- E 4th Street, Broadway Ave to State Ave - Milled – intersections are open east/west.
- W 2nd Street, Cherry Ave to Cherry Lane - Reopening at the end of this week.
- W 3rd Street, Pine Ave to north end - Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
This Project is substantially complete
-
April 4, 2025
Share April 4, 2025 on Facebook Share April 4, 2025 on X (formerly Twitter) Share April 4, 2025 on Linkedin Email April 4, 2025 linkProject includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Paving this week – reopening next week.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Paving this week – reopening next week.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving this week.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane - Asphalt paving is scheduled for early next week.
- W 3rd Street, Pine Ave to north end. Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Paving this week – reopening next week.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Paving this week – reopening next week.
- Washington St, NW 7th Street to Meridian Rd - Grade prep and demo ongoing. Utility work ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving this week.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane - Asphalt paving is scheduled for early next week.
- W 3rd Street, Pine Ave to north end. Site prep ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
This Project is substantially complete
-
March 28, 2025
Share March 28, 2025 on Facebook Share March 28, 2025 on X (formerly Twitter) Share March 28, 2025 on Linkedin Email March 28, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep complete. Concrete placements ongoing. Asphalt paving is scheduled for next Tuesday.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Grade work and prep complete. Concrete placements ongoing.
- Washington St, NW 7th Street to Meridian Rd - Milling complete.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving is scheduled for next Tuesday.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane - Asphalt paving is scheduled for next Tuesday.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work complete.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
- Broadway Ave, E 3rd Street to E 6th Street - City utility and storm drain work started at NW 4th. Demo complete. Broadway storm drain installation ongoing. Prepping for concrete.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep complete. Concrete placements ongoing. Asphalt paving is scheduled for next Tuesday.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Grade work and prep complete. Concrete placements ongoing.
- Washington St, NW 7th Street to Meridian Rd - Milling complete.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements complete. Asphalt paving is scheduled for next Tuesday.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane - Asphalt paving is scheduled for next Tuesday.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work complete.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work ongoing.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
This Project is substantially complete
-
March 20, 2025
Share March 20, 2025 on Facebook Share March 20, 2025 on X (formerly Twitter) Share March 20, 2025 on Linkedin Email March 20, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Contractor set a closure up (between 4th and 5th) to start irrigation work and demo. City utility and storm drain work started at NW 4th.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Washington St, NW 7th Street to Meridian Rd - Contactor is milling - started on March 17th.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements ongoing.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work started.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
- Broadway Ave, E 3rd Street to E 6th Street - Contractor set a closure up (between 4th and 5th) to start irrigation work and demo. City utility and storm drain work started at NW 4th.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Grade work and prep complete. Concrete placements started.
- Washington St, NW 7th Street to Meridian Rd - Contactor is milling - started on March 17th.
- E 2nd Street, Idaho Ave to Pine Ave - Concrete placements ongoing.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work started.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work complete.
This Project is substantially complete
-
March 14, 2025
Share March 14, 2025 on Facebook Share March 14, 2025 on X (formerly Twitter) Share March 14, 2025 on Linkedin Email March 14, 2025 link- Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Contractor to set a rolling closure up to start irrigation work, possibly next week.City utility and storm drain work to start soon at NW 4th.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep nearly complete.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Grade work and prep nearly complete.
- Washington St, NW 7th Street to Meridian Rd - Contactor is tentatively planning to mill starting on March 17th
- E 2nd Street, Idaho Ave to Pine Ave - Contractor will be starting to place concrete this week for curb, gutter, and sidewalk.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work started.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing – nearly complete
- Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Contractor to set a rolling closure up to start irrigation work, possibly next week.City utility and storm drain work to start soon at NW 4th.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work and prep nearly complete.
- Idaho Ave, W 8th St to Meridian Rd.
- Maple Ave, W 1st Street to Meridian Rd - Grade work and prep nearly complete.
- Washington St, NW 7th Street to Meridian Rd - Contactor is tentatively planning to mill starting on March 17th
- E 2nd Street, Idaho Ave to Pine Ave - Contractor will be starting to place concrete this week for curb, gutter, and sidewalk.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave - City of Meridian utility work started.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing – nearly complete
This Project is substantially complete
-
March 6, 2025
Share March 6, 2025 on Facebook Share March 6, 2025 on X (formerly Twitter) Share March 6, 2025 on Linkedin Email March 6, 2025 linkProject includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Utility potholing complete. Contractor to set a rolling closure up to start irrigation work, possibly next week.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work has started.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Grade work has started.
- Washington St, NW 7th Street to Meridian Rd - Contactor is tentatively planning to mill starting on March 14th.
- E 2nd Street, Idaho Ave to Pine Ave - Demo/Excavation work ongoing.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing.
- City of Meridian utility work is ongoing.
Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Utility potholing complete. Contractor to set a rolling closure up to start irrigation work, possibly next week.
- Cherry Ave, NW 4th Street to Meridian Rd - Grade work has started.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Grade work has started.
- Washington St, NW 7th Street to Meridian Rd - Contactor is tentatively planning to mill starting on March 14th.
- E 2nd Street, Idaho Ave to Pine Ave - Demo/Excavation work ongoing.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing.
- City of Meridian utility work is ongoing.
This Project is substantially complete
-
February 28, 2025
Share February 28, 2025 on Facebook Share February 28, 2025 on X (formerly Twitter) Share February 28, 2025 on Linkedin Email February 28, 2025 link- Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Contractor to set a rolling closure up to start irrigation work, next week.
- Cherry Ave, NW 4th Street to Meridian Rd - Demo/Excavation work ongoing.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Demo/Excavation work ongoing.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo/Excavation work started.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing.
- City of Meridian utility work is ongoing.
- Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Contractor to set a rolling closure up to start irrigation work, next week.
- Cherry Ave, NW 4th Street to Meridian Rd - Demo/Excavation work ongoing.
- Idaho Ave, W 8th St to Meridian Rd
- Maple Ave, W 1st Street to Meridian Rd - Demo/Excavation work ongoing.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo/Excavation work started.
- E 4th Street, Broadway Ave to State Ave.
- W 2nd Street, Cherry Ave to Cherry Lane.
- W 3rd Street, Pine Ave to north end - Demo/Excavation work ongoing.
- NW 4th Street, Broadway Ave to Maple Ave.
- NW 6th Street, Carlton Ave to Washington St.
- NW 7th Street, McFadden Ave to Washington St.
- *Irrigation work at various locations is ongoing.
- City of Meridian utility work is ongoing.
This Project is substantially complete
-
February 20, 2025
Share February 20, 2025 on Facebook Share February 20, 2025 on X (formerly Twitter) Share February 20, 2025 on Linkedin Email February 20, 2025 link- Broadway Ave, E 3rd Street to E 6th Street
- Cherry Ave, NW 4th Street to Meridian Rd - Demo has started.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Demo has started.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo is expected to start next week.
- E 4th Street, Broadway Ave to State Ave
- W 2nd Street, Cherry Ave to Cherry Lane
- W 3rd Street, Pine Ave to north end - Demo has started.
- NW 4th Street, Broadway Ave to Maple Ave - Demo has started.
- NW 6th Street, Carlton Ave to Washington St
- NW 7th Street, McFadden Ave to Washington St
- *Irrigation work has started.
- Broadway Ave, E 3rd Street to E 6th Street
- Cherry Ave, NW 4th Street to Meridian Rd - Demo has started.
- Idaho Ave, W 8th St to Meridian Rd o Maple Ave, W 1st Street to Meridian Rd - Demo has started.
- Washington St, NW 7th Street to Meridian Rd
- E 2nd Street, Idaho Ave to Pine Ave - Demo is expected to start next week.
- E 4th Street, Broadway Ave to State Ave
- W 2nd Street, Cherry Ave to Cherry Lane
- W 3rd Street, Pine Ave to north end - Demo has started.
- NW 4th Street, Broadway Ave to Maple Ave - Demo has started.
- NW 6th Street, Carlton Ave to Washington St
- NW 7th Street, McFadden Ave to Washington St
- *Irrigation work has started.
This Project is substantially complete
Documents
-
Winter 2024 Update
-
Broadway (E 3rd St to E 6th St).pdf (2.48 MB) (pdf)
-
Cherry (W 4th to Meridian).pdf (4.69 MB) (pdf)
-
E 2nd St (Idaho Ave to Pine Ave).pdf (2.68 MB) (pdf)
-
E 4th Street (Broadway Ave to State Ave).pdf (1.4 MB) (pdf)
-
Idaho (W 8th St to Meridian).pdf (4.7 MB) (pdf)
-
Maple (1st to Meridian).pdf (2.4 MB) (pdf)
-
W 2nd St (Camellia to Cherry Ln).pdf (2.64 MB) (pdf)
-
W 3rd St (Pine to End).pdf (1.92 MB) (pdf)
-
W 4th St (Broadway Ave to Maple Ave).pdf (6 MB) (pdf)
-
W 6th St (W Carlton to W Washington).pdf (2.68 MB) (pdf)
-
Washington (7th to Carlton)_7th (Washington to N).pdf (9.8 MB) (pdf)
-
-
Winter 2022 Public Outreach
-
Winter 2022 Project Information and Project Designs
-
2nd St, Camellia Ave to Cherry Ln Design (1.73 MB) (pdf)
-
3rd St, Pine Ave to End Design (1.18 MB) (pdf)
-
4th St, Broadway Ave to Washington St Design (3.54 MB) (pdf)
-
Broadway Ave, 3rd St to 6th St Design (1.47 MB) (pdf)
-
Idaho Ave, 8th St to 3rd St Design (4.72 MB) (pdf)
-
Maple Ave, 1st St to Meridian Rd Design (1.83 MB) (pdf)
-
Cherry Ave, 4th St to 2nd St Design (3.33 MB) (pdf)
-
Related projects
Live Projects
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org