2025 Meridian Downtown Pavement and Pedestrian Improvements
This Project is substantially complete
The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.
Work could include
- Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
- Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
- Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
- Adding crosswalk markings for school walk route crossings
- Stormwater and irrigation upgrades to improve flows
Street Segments
- Broadway Avenue, East 3rd Street to East 6th Street
- Cherry Avenue, West 4th Street to Meridian Road
- East 2nd Street, Idaho Avenue to Pine Avenue
- East 4th Street, Broadway Avenue to State Avenue
- Idaho Avenue, West 8th Street to Meridian Road
- Maple Avenue, West 1st Street to Meridian Road
- West 2nd Street, Cherry Avenue to Cherry Lane
- West 3rd Street, Pine Street to North End
- West 4th Street, Broadway Avenue to North of Maple Avenue
- West 5th Street, Carlton Avenue to Washington Street
- West 6th Street, Carlton Avenue to Washington Street
- West 7th Street, Washington Street to the pathway South of McFadden Avenue
- Washington Street, West 7th Street to Meridian Road
To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org.
Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org
The Ada County Highway District (ACHD) will be repaving or reconstructing several streets in Meridian as part of a locally funded project to improve pavement conditions and upgrade the streets for all users.
Work could include
- Filling in sidewalk gaps and replacing deteriorated sidewalk to improve connectivity
- Adding bulb-outs and narrowing travel lanes where appropriate to improve safety
- Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA)
- Adding crosswalk markings for school walk route crossings
- Stormwater and irrigation upgrades to improve flows
Street Segments
- Broadway Avenue, East 3rd Street to East 6th Street
- Cherry Avenue, West 4th Street to Meridian Road
- East 2nd Street, Idaho Avenue to Pine Avenue
- East 4th Street, Broadway Avenue to State Avenue
- Idaho Avenue, West 8th Street to Meridian Road
- Maple Avenue, West 1st Street to Meridian Road
- West 2nd Street, Cherry Avenue to Cherry Lane
- West 3rd Street, Pine Street to North End
- West 4th Street, Broadway Avenue to North of Maple Avenue
- West 5th Street, Carlton Avenue to Washington Street
- West 6th Street, Carlton Avenue to Washington Street
- West 7th Street, Washington Street to the pathway South of McFadden Avenue
- Washington Street, West 7th Street to Meridian Road
To arrange for a translator or other accommodation, contact ACHD at (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org.
Se les recomienda a las personas que necesiten un intérprete o arreglos especiales que llamen a la coordinadora de participación pública, al (208) 387-6100 | TTY 1-800-377-3529 | projects@achdidaho.org
This Project is substantially complete
-
September 12, 2025
Share September 12, 2025 on Facebook Share September 12, 2025 on X (formerly Twitter) Share September 12, 2025 on Linkedin Email September 12, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk complete. Working on storm drain installation.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Complete.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Grade prep and curb and gutter install ongoing.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk complete. Working on storm drain installation.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Complete.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Grade prep and curb and gutter install ongoing.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
This Project is substantially complete
-
September 5, 2025
Share September 5, 2025 on Facebook Share September 5, 2025 on X (formerly Twitter) Share September 5, 2025 on Linkedin Email September 5, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Complete
- Cherry Ave, NW 4th Street to Meridian Rd - Complete
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk complete. Working on storm drain installation. Utility work will be completed this week.
- Maple Ave, W 1st Street to Meridian Rd - Complete
- Washington St, NW 7th Street to Meridian Rd - Complete
- E 2nd Street, Idaho Ave to Pine Ave - Complete
- E 4th Street, Broadway Ave to State Ave - Complete
- W 2nd Street, Cherry Ave to Cherry Lane - Grade prep and curb and gutter install ongoing.
- W 3rd Street, Pine Ave to north end - Complete
- NW 4th Street, Broadway Ave to Maple Ave - Complete
- NW 6th Street, Carlton Ave to Washington St - Complete
- NW 7th Street, McFadden Ave to Washington St - Complete
- Broadway Ave, E 3rd Street to E 6th Street - Complete
- Cherry Ave, NW 4th Street to Meridian Rd - Complete
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk complete. Working on storm drain installation. Utility work will be completed this week.
- Maple Ave, W 1st Street to Meridian Rd - Complete
- Washington St, NW 7th Street to Meridian Rd - Complete
- E 2nd Street, Idaho Ave to Pine Ave - Complete
- E 4th Street, Broadway Ave to State Ave - Complete
- W 2nd Street, Cherry Ave to Cherry Lane - Grade prep and curb and gutter install ongoing.
- W 3rd Street, Pine Ave to north end - Complete
- NW 4th Street, Broadway Ave to Maple Ave - Complete
- NW 6th Street, Carlton Ave to Washington St - Complete
- NW 7th Street, McFadden Ave to Washington St - Complete
This Project is substantially complete
-
August 29, 2025
Share August 29, 2025 on Facebook Share August 29, 2025 on X (formerly Twitter) Share August 29, 2025 on Linkedin Email August 29, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk complete. Working on storm drain installation. Utility work will be completed this week.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Complete.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete placements ongoing. Grade prep ongoing. Working on storm drain install.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk complete. Working on storm drain installation. Utility work will be completed this week.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Complete.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete placements ongoing. Grade prep ongoing. Working on storm drain install.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
This Project is substantially complete
-
August 21, 2025
Share August 21, 2025 on Facebook Share August 21, 2025 on X (formerly Twitter) Share August 21, 2025 on Linkedin Email August 21, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk complete. Working on storm drain installation. Utility work will be completed this week.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Complete.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete placements ongoing. Grade prep ongoing. Working on storm drain install.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington Street - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk complete. Working on storm drain installation. Utility work will be completed this week.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Complete.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete placements ongoing. Grade prep ongoing. Working on storm drain install.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington Street - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
This Project is substantially complete
-
August 15, 2025
Share August 15, 2025 on Facebook Share August 15, 2025 on X (formerly Twitter) Share August 15, 2025 on Linkedin Email August 15, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk started. Working on storm drain install.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Paving scheduled for Friday.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete placements ongoing. Grade prep ongoing. Working on storm drain install.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk started. Working on storm drain install.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Paving scheduled for Friday.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete placements ongoing. Grade prep ongoing. Working on storm drain install.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
This Project is substantially complete
-
August 8, 2025
Share August 8, 2025 on Facebook Share August 8, 2025 on X (formerly Twitter) Share August 8, 2025 on Linkedin Email August 8, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk started.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Grade prep complete. Utility work complete. Concrete prep and placements ongoing. Grade prep ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete placements ongoing. Grade prep ongoing.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete. Demo for sidewalk started.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Grade prep complete. Utility work complete. Concrete prep and placements ongoing. Grade prep ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Complete.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete placements ongoing. Grade prep ongoing.
- W 3rd Street, Pine Ave to north end - Complete.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Complete.
- NW 7th Street, McFadden Ave to Washington St - Complete.
This Project is substantially complete
-
August 1, 2025
Share August 1, 2025 on Facebook Share August 1, 2025 on X (formerly Twitter) Share August 1, 2025 on Linkedin Email August 1, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Grade prep complete. Utility work complete. Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep complete. Concrete placements complete. Paving this week.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete complete. Grade prep ongoing.
- W 3rd Street, Pine Ave to north end - Site prep complete. Concrete placements minor work remains. Pine will be closed starting June 24th. Broadway will be the detour. Paving this week.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
- NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete.
- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Grade prep complete. Utility work complete. Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep complete. Concrete placements complete. Paving this week.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete complete. Grade prep ongoing.
- W 3rd Street, Pine Ave to north end - Site prep complete. Concrete placements minor work remains. Pine will be closed starting June 24th. Broadway will be the detour. Paving this week.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
- NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete.
This Project is substantially complete
-
July 25, 2025
Share July 25, 2025 on Facebook Share July 25, 2025 on X (formerly Twitter) Share July 25, 2025 on Linkedin Email July 25, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Grade prep complete. Utility work complete. Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep complete. Concrete placements complete. Paving next week.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete complete. Paving next week.
- W 3rd Street, Pine Ave to north end - Site prep complete. Concrete placements minor work remains. Pine will be closed starting June 24th. Broadway will be the detour. Paving next week.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
- NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements ongoing
- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd - Grade prep complete. Utility work complete. Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep complete. Concrete placements complete. Paving next week.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work complete. Concrete complete. Paving next week.
- W 3rd Street, Pine Ave to north end - Site prep complete. Concrete placements minor work remains. Pine will be closed starting June 24th. Broadway will be the detour. Paving next week.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
- NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements ongoing
This Project is substantially complete
-
July 18, 2025
Share July 18, 2025 on Facebook Share July 18, 2025 on X (formerly Twitter) Share July 18, 2025 on Linkedin Email July 18, 2025 linkProject includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Complete
- Cherry Ave, NW 4th Street to Meridian Rd - Complete
- Idaho Ave, W 8th St to Meridian Rd - Complete
- Maple Ave, W 1st Street to Meridian Rd - Complete
- Washington St, NW 7th Street to Meridian Rd
- Grade prep complete.
- Utility work complete.
- Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete
- E 4th Street, Broadway Ave to State Ave
- Demo, utility work, and grade prep are ongoing.
- Concrete placements are ongoing.
-
W 2nd Street, Cherry Ave to Cherry Lane
- Milling complete.
- Utility work started.
-
W 3rd Street, Pine Ave to north end
- Site prep ongoing.
- Concrete placements have started.
-
Pine will be closed starting June 24th. Broadway will be the detour.
- NW 4th Street, Broadway Ave to Maple Ave - Complete
-
NW 6th Street, Carlton Ave to Washington St
- Demo complete.
- Utility work complete.
- Concrete placements ongoing.
-
NW 7th Street, McFadden Ave to Washington St
- Demo and utility work complete.
- Concrete placements ongoing.
Project includes work on the following segments:
- Broadway Ave, E 3rd Street to E 6th Street - Complete
- Cherry Ave, NW 4th Street to Meridian Rd - Complete
- Idaho Ave, W 8th St to Meridian Rd - Complete
- Maple Ave, W 1st Street to Meridian Rd - Complete
- Washington St, NW 7th Street to Meridian Rd
- Grade prep complete.
- Utility work complete.
- Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete
- E 4th Street, Broadway Ave to State Ave
- Demo, utility work, and grade prep are ongoing.
- Concrete placements are ongoing.
-
W 2nd Street, Cherry Ave to Cherry Lane
- Milling complete.
- Utility work started.
-
W 3rd Street, Pine Ave to north end
- Site prep ongoing.
- Concrete placements have started.
-
Pine will be closed starting June 24th. Broadway will be the detour.
- NW 4th Street, Broadway Ave to Maple Ave - Complete
-
NW 6th Street, Carlton Ave to Washington St
- Demo complete.
- Utility work complete.
- Concrete placements ongoing.
-
NW 7th Street, McFadden Ave to Washington St
- Demo and utility work complete.
- Concrete placements ongoing.
This Project is substantially complete
-
July 11, 2025
Share July 11, 2025 on Facebook Share July 11, 2025 on X (formerly Twitter) Share July 11, 2025 on Linkedin Email July 11, 2025 link- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd -Grade prep complete. Utility work complete. Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep are ongoing. Concrete placements are ongoing.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work started.
- W 3rd Street, Pine Ave to north end - Site prep ongoing. Concrete placements have started. Pine will be closed starting June 24th. Broadway will be the detour.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
- NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements have started.
- Broadway Ave, E 3rd Street to E 6th Street - Complete.
- Cherry Ave, NW 4th Street to Meridian Rd - Complete.
- Idaho Ave, W 8th St to Meridian Rd - Milling complete.
- Maple Ave, W 1st Street to Meridian Rd - Complete.
- Washington St, NW 7th Street to Meridian Rd -Grade prep complete. Utility work complete. Concrete prep and placements ongoing.
- E 2nd Street, Idaho Ave to Pine Ave - Complete.
- E 4th Street, Broadway Ave to State Ave - Demo, utility work, and grade prep are ongoing. Concrete placements are ongoing.
- W 2nd Street, Cherry Ave to Cherry Lane - Milling complete. Utility work started.
- W 3rd Street, Pine Ave to north end - Site prep ongoing. Concrete placements have started. Pine will be closed starting June 24th. Broadway will be the detour.
- NW 4th Street, Broadway Ave to Maple Ave - Complete.
- NW 6th Street, Carlton Ave to Washington St - Demo complete. Utility work complete. Concrete placements ongoing.
- NW 7th Street, McFadden Ave to Washington St - Demo and utility work complete. Concrete placements have started.
This Project is substantially complete
Documents
-
Winter 2024 Update
-
Broadway (E 3rd St to E 6th St).pdf (2.48 MB) (pdf)
-
Cherry (W 4th to Meridian).pdf (4.69 MB) (pdf)
-
E 2nd St (Idaho Ave to Pine Ave).pdf (2.68 MB) (pdf)
-
E 4th Street (Broadway Ave to State Ave).pdf (1.4 MB) (pdf)
-
Idaho (W 8th St to Meridian).pdf (4.7 MB) (pdf)
-
Maple (1st to Meridian).pdf (2.4 MB) (pdf)
-
W 2nd St (Camellia to Cherry Ln).pdf (2.64 MB) (pdf)
-
W 3rd St (Pine to End).pdf (1.92 MB) (pdf)
-
W 4th St (Broadway Ave to Maple Ave).pdf (6 MB) (pdf)
-
W 6th St (W Carlton to W Washington).pdf (2.68 MB) (pdf)
-
Washington (7th to Carlton)_7th (Washington to N).pdf (9.8 MB) (pdf)
-
-
Winter 2022 Public Outreach
-
Winter 2022 Project Information and Project Designs
-
2nd St, Camellia Ave to Cherry Ln Design (1.73 MB) (pdf)
-
3rd St, Pine Ave to End Design (1.18 MB) (pdf)
-
4th St, Broadway Ave to Washington St Design (3.54 MB) (pdf)
-
Broadway Ave, 3rd St to 6th St Design (1.47 MB) (pdf)
-
Idaho Ave, 8th St to 3rd St Design (4.72 MB) (pdf)
-
Maple Ave, 1st St to Meridian Rd Design (1.83 MB) (pdf)
-
Cherry Ave, 4th St to 2nd St Design (3.33 MB) (pdf)
-
Related projects
Live Projects
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org