Lake Hazel and Maple Grove Roundabout
This project is substantially complete.
The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.
Project Description
- Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
- Add curb, gutter, and a detached 10-foot wide multi-use pathway
- Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
- Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
- Add a truck apron for larger vehicles to use if necessary
The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.
Project Description
- Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
- Add curb, gutter, and a detached 10-foot wide multi-use pathway
- Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
- Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
- Add a truck apron for larger vehicles to use if necessary
This project is substantially complete.
-
April 25, 2024
Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link- Contractor working on sidewalk at various locations around the project.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete.
- Installation of pavement markings is on-going.
- Anticipate opening three legs of the roundabout as early as April 26th.
- Contractor working on sidewalk at various locations around the project.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete.
- Installation of pavement markings is on-going.
- Anticipate opening three legs of the roundabout as early as April 26th.
This project is substantially complete.
-
April 19, 2024
Share April 19, 2024 on Facebook Share April 19, 2024 on Twitter Share April 19, 2024 on Linkedin Email April 19, 2024 link- Contractor working on sidewalk at various locations around the project.
- Splitter island concrete placements complete.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete.
- Installation of pavement markings is on-going.
- Contractor working on sidewalk at various locations around the project.
- Splitter island concrete placements complete.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete.
- Installation of pavement markings is on-going.
This project is substantially complete.
-
April 12, 2024
Share April 12, 2024 on Facebook Share April 12, 2024 on Twitter Share April 12, 2024 on Linkedin Email April 12, 2024 link- Contractor working on sidewalk at various locations around the project.
- Splitter island concrete placements complete.
- Contractor continues placing concrete pavement mainline this week and next.
- Contractor working on sidewalk at various locations around the project.
- Splitter island concrete placements complete.
- Contractor continues placing concrete pavement mainline this week and next.
This project is substantially complete.
-
April 5, 2024
Share April 5, 2024 on Facebook Share April 5, 2024 on Twitter Share April 5, 2024 on Linkedin Email April 5, 2024 link- Contractor working on sidewalk at various locations around the project.
- Splitter island concrete placements complete.
- Contractor continues placing concrete pavement mainline this week and next.
- Contractor working on sidewalk at various locations around the project.
- Splitter island concrete placements complete.
- Contractor continues placing concrete pavement mainline this week and next.
This project is substantially complete.
-
March 29, 2024
Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link- Contractor working on sidewalk at various locations around the project.
- Splitter island concrete placements complete.
- Contractor started concrete paving mainline this week.
- Contractor working on sidewalk at various locations around the project.
- Splitter island concrete placements complete.
- Contractor started concrete paving mainline this week.
This project is substantially complete.
-
March 21, 2024
Share March 21, 2024 on Facebook Share March 21, 2024 on Twitter Share March 21, 2024 on Linkedin Email March 21, 2024 link- Contractor working on curb/gutter and sidewalk at various locations around the project.
- Splitter island concrete placements nearly complete.
- Contractor is grading for paving which is scheduled for the week of March 25th.
- Contractor working on curb/gutter and sidewalk at various locations around the project.
- Splitter island concrete placements nearly complete.
- Contractor is grading for paving which is scheduled for the week of March 25th.
This project is substantially complete.
-
March 15, 2024
Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link- Contractor working on curb/gutter and sidewalk at various locations around the project.
- Light poles are set.
- Blue top survey work ongoing for final grade.
- Splitter island prep complete.
- Contractor working on curb/gutter and sidewalk at various locations around the project.
- Light poles are set.
- Blue top survey work ongoing for final grade.
- Splitter island prep complete.
This project is substantially complete.
-
March 8, 2024
Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link- Grade prep for sidewalks curb & gutter is ongoing.
- Prep for center island complete.
- Contractor working on curb/gutter and sidewalk at various locations around the project.
- Light poles are being set this week.
- Grade prep for sidewalks curb & gutter is ongoing.
- Prep for center island complete.
- Contractor working on curb/gutter and sidewalk at various locations around the project.
- Light poles are being set this week.
This project is substantially complete.
-
March 1, 2024
Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link- Contractor importing and grading base materials.
- Grade prep for sidewalks C&G is on going.
- SW retaining wall installation complete.
- Prep for center island started.
- Contractor working on C&G at various locations around the project.
- Contractor importing and grading base materials.
- Grade prep for sidewalks C&G is on going.
- SW retaining wall installation complete.
- Prep for center island started.
- Contractor working on C&G at various locations around the project.
This project is substantially complete.
-
February 23, 2024
Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link- Contractor importing and grading base materials.
- Grade prep for sidewalks C&G is on going.
- SW retaining wall installation complete.
- Prep for center island started.
- Electrical contractor on site pulling wire and setting control cabinets/boxes.
- Contractor importing and grading base materials.
- Grade prep for sidewalks C&G is on going.
- SW retaining wall installation complete.
- Prep for center island started.
- Electrical contractor on site pulling wire and setting control cabinets/boxes.
This project is substantially complete.
Who's Listening
-
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org
Drone Footage
-
April 10 2024
-
May 31 2024