Lake Hazel and Maple Grove Roundabout

Share Lake Hazel and Maple Grove Roundabout on Facebook Share Lake Hazel and Maple Grove Roundabout on Twitter Share Lake Hazel and Maple Grove Roundabout on Linkedin Email Lake Hazel and Maple Grove Roundabout link

This project is substantially complete. 

The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.

Project Description

  • Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
  • Add curb, gutter, and a detached 10-foot wide multi-use pathway
  • Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
  • Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
  • Add a truck apron for larger vehicles to use if necessary

The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.

Project Description

  • Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
  • Add curb, gutter, and a detached 10-foot wide multi-use pathway
  • Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
  • Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
  • Add a truck apron for larger vehicles to use if necessary

This project is substantially complete. 

  • December 1, 2023

    Share December 1, 2023 on Facebook Share December 1, 2023 on Twitter Share December 1, 2023 on Linkedin Email December 1, 2023 link
    • Road closure started November 13th.
    • Existing signals have been removed.
    • Roadway milling complete November 16th.
    • Grade prep started.
    • Idaho Power work nearly complete. Waiting on parts.
    • Electrical underground work started.
    • Fiber utility work ongoing.
    • Water line install has started.
    • Speed bump install around the project for TTC is scheduled for November 29th.
  • November 22, 2023

    Share November 22, 2023 on Facebook Share November 22, 2023 on Twitter Share November 22, 2023 on Linkedin Email November 22, 2023 link
    • Road closure started November 13th.
    • Existing signals have been removed.
    • Roadway milling complete November 16th.
    • Grade prep started.
    • Idaho Power work nearly complete - waiting on a part.
    • Electrical underground work started.
    • Fiber utility work ongoing.
    • Water line install is schedule to start middle of December.
    • Speed bump install around the project for TTC is scheduled for early next week.
  • November 17, 2023

    Share November 17, 2023 on Facebook Share November 17, 2023 on Twitter Share November 17, 2023 on Linkedin Email November 17, 2023 link

    ► Road closure started November 13th .

    ► Existing signals have been removed.

    ► Roadway milling started November 16th .

    ► Idaho Power work complete.

    ► Electrical work started.

    ► Fiber utility work started.

  • November 9, 2023

    Share November 9, 2023 on Facebook Share November 9, 2023 on Twitter Share November 9, 2023 on Linkedin Email November 9, 2023 link
    • Temporary signal installation will activate Sunday night at the corners of Cole and Desert and Maple Grove and Desert in preparation for the full intersection closure at Lake Hazel and Maple Grove starting November 13th.
  • November 3, 2023

    Share November 3, 2023 on Facebook Share November 3, 2023 on Twitter Share November 3, 2023 on Linkedin Email November 3, 2023 link
    • Temporary signal installation has started on the corners of Cole and Desert and Maple Grove and Desert in preparation for the full intersection closure at Lake Hazel and Maple Grove.
    • Detour Map for the Lake Hazel Roundabout Project

  • October 27, 2023

    Share October 27, 2023 on Facebook Share October 27, 2023 on Twitter Share October 27, 2023 on Linkedin Email October 27, 2023 link

    Temporary signal installation has started on the corners of Cole and Desert/Maple Grove and Desert in preparation for the full intersection closure at Lake Hazel and Maple Grove.

  • Construction to start October 2023

    Share Construction to start October 2023 on Facebook Share Construction to start October 2023 on Twitter Share Construction to start October 2023 on Linkedin Email Construction to start October 2023 link

    The Ada County Highway District will start construction on the Lake Hazel Road and Maple Grove Road roundabout project in October 2023.* Construction is anticipated to be complete summer 2024.

    Construction Impacts

    • Temporary road closures
    • Lane restrictions with flaggers
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize construction impacts


    *Due to high demand for contractors, labor and supplies, the construction schedule may change.

  • Fall 2021 Public Outreach

    Share Fall 2021 Public Outreach on Facebook Share Fall 2021 Public Outreach on Twitter Share Fall 2021 Public Outreach on Linkedin Email Fall 2021 Public Outreach link

    Find responses to the frequently asked questions received this summer and additional information at the links below. While your comments are always welcome, the comment period closed on October 12, 2021.