Share December 1, 2023 on Facebook
Share December 1, 2023 on Linkedin
Email December 1, 2023 link
- Road closure started November 13th.
- Existing signals have been removed.
- Roadway milling complete November 16th.
- Grade prep started.
- Idaho Power work nearly complete. Waiting on parts.
- Electrical underground work started.
- Fiber utility work ongoing.
- Water line install has started.
- Speed bump install around the project for TTC is scheduled for November 29th.
Share November 22, 2023 on Facebook
Share November 22, 2023 on Linkedin
Email November 22, 2023 link
- Road closure started November 13th.
- Existing signals have been removed.
- Roadway milling complete November 16th.
- Grade prep started.
- Idaho Power work nearly complete - waiting on a part.
- Electrical underground work started.
- Fiber utility work ongoing.
- Water line install is schedule to start middle of December.
- Speed bump install around the project for TTC is scheduled for early next week.
Share November 17, 2023 on Facebook
Share November 17, 2023 on Linkedin
Email November 17, 2023 link
► Road closure started November 13th .
► Existing signals have been removed.
► Roadway milling started November 16th .
► Idaho Power work complete.
► Electrical work started.
► Fiber utility work started.
Share November 9, 2023 on Facebook
Share November 9, 2023 on Linkedin
Email November 9, 2023 link
- Temporary signal installation will activate Sunday night at the corners of Cole and Desert and Maple Grove and Desert in preparation for the full intersection closure at Lake Hazel and Maple Grove starting November 13th.
Share November 3, 2023 on Facebook
Share November 3, 2023 on Linkedin
Email November 3, 2023 link
- Temporary signal installation has started on the corners of Cole and Desert and Maple Grove and Desert in preparation for the full intersection closure at Lake Hazel and Maple Grove.
- Detour Map for the Lake Hazel Roundabout Project
Share October 27, 2023 on Facebook
Share October 27, 2023 on Linkedin
Email October 27, 2023 link
Temporary signal installation has started on the corners of Cole and Desert/Maple Grove and Desert in preparation for the full intersection closure at Lake Hazel and Maple Grove.
Share Construction to start October 2023 on Facebook
Share Construction to start October 2023 on Linkedin
Email Construction to start October 2023 link
The Ada County Highway District will start construction on the Lake Hazel Road and Maple Grove Road roundabout project in October 2023.* Construction is anticipated to be complete summer 2024.
Construction Impacts
- Temporary road closures
- Lane restrictions with flaggers
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize construction impacts
*Due to high demand for contractors, labor and supplies, the construction schedule may change.
Share Fall 2021 Public Outreach on Facebook
Share Fall 2021 Public Outreach on Linkedin
Email Fall 2021 Public Outreach link
Find responses to the frequently asked questions received this summer and additional information at the links below. While your comments are always welcome, the comment period closed on October 12, 2021.