Lake Hazel and Maple Grove Roundabout

Share Lake Hazel and Maple Grove Roundabout on Facebook Share Lake Hazel and Maple Grove Roundabout on Twitter Share Lake Hazel and Maple Grove Roundabout on Linkedin Email Lake Hazel and Maple Grove Roundabout link

This project is substantially complete. 

The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.

Project Description

  • Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
  • Add curb, gutter, and a detached 10-foot wide multi-use pathway
  • Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
  • Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
  • Add a truck apron for larger vehicles to use if necessary

The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.

Project Description

  • Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
  • Add curb, gutter, and a detached 10-foot wide multi-use pathway
  • Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
  • Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
  • Add a truck apron for larger vehicles to use if necessary

This project is substantially complete. 

  • April 25, 2024

    Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link
    • Contractor working on sidewalk at various locations around the project.
    • Contractor completed concrete pavement mainline.
    • Asphalt paving complete.
    • Installation of pavement markings is on-going.
    • Anticipate opening three legs of the roundabout as early as April 26th.
  • April 19, 2024

    Share April 19, 2024 on Facebook Share April 19, 2024 on Twitter Share April 19, 2024 on Linkedin Email April 19, 2024 link
    • Contractor working on sidewalk at various locations around the project.
    • Splitter island concrete placements complete.
    • Contractor completed concrete pavement mainline.
    • Asphalt paving complete.
    • Installation of pavement markings is on-going.
  • April 12, 2024

    Share April 12, 2024 on Facebook Share April 12, 2024 on Twitter Share April 12, 2024 on Linkedin Email April 12, 2024 link
    • Contractor working on sidewalk at various locations around the project.
    • Splitter island concrete placements complete.
    • Contractor continues placing concrete pavement mainline this week and next.
  • April 5, 2024

    Share April 5, 2024 on Facebook Share April 5, 2024 on Twitter Share April 5, 2024 on Linkedin Email April 5, 2024 link
    • Contractor working on sidewalk at various locations around the project.
    • Splitter island concrete placements complete.
    • Contractor continues placing concrete pavement mainline this week and next.
  • March 29, 2024

    Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link
    • Contractor working on sidewalk at various locations around the project.
    • Splitter island concrete placements complete.
    • Contractor started concrete paving mainline this week.
  • March 21, 2024

    Share March 21, 2024 on Facebook Share March 21, 2024 on Twitter Share March 21, 2024 on Linkedin Email March 21, 2024 link
    • Contractor working on curb/gutter and sidewalk at various locations around the project.
    • Splitter island concrete placements nearly complete.
    • Contractor is grading for paving which is scheduled for the week of March 25th.



  • March 15, 2024

    Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link
    • Contractor working on curb/gutter and sidewalk at various locations around the project.
    • Light poles are set.
    • Blue top survey work ongoing for final grade.
    • Splitter island prep complete.
  • March 8, 2024

    Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link
    • Grade prep for sidewalks curb & gutter is ongoing.
    • Prep for center island complete.
    • Contractor working on curb/gutter and sidewalk at various locations around the project.
    • Light poles are being set this week.
  • March 1, 2024

    Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link
    • Contractor importing and grading base materials.
    • Grade prep for sidewalks C&G is on going.
    • SW retaining wall installation complete.
    • Prep for center island started.
    • Contractor working on C&G at various locations around the project.
  • February 23, 2024

    Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link
    • Contractor importing and grading base materials.
    • Grade prep for sidewalks C&G is on going.
    • SW retaining wall installation complete.
    • Prep for center island started.
    • Electrical contractor on site pulling wire and setting control cabinets/boxes.