Lake Hazel and Maple Grove Roundabout
This project is substantially complete.
The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.
Project Description
- Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
- Add curb, gutter, and a detached 10-foot wide multi-use pathway
- Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
- Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
- Add a truck apron for larger vehicles to use if necessary
The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.
Project Description
- Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
- Add curb, gutter, and a detached 10-foot wide multi-use pathway
- Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
- Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
- Add a truck apron for larger vehicles to use if necessary
This project is substantially complete.
-
February 16, 2024
Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link- Contractor importing and grading base materials.
- North leg of the project has a lot of rock excavation.
- Blasting complete.
- Grade prep for sidewalks on going.
- SW retaining wall install started.
- Electrical contractor on site pulling wire and setting control cabinets/boxes.
- Contractor importing and grading base materials.
- North leg of the project has a lot of rock excavation.
- Blasting complete.
- Grade prep for sidewalks on going.
- SW retaining wall install started.
- Electrical contractor on site pulling wire and setting control cabinets/boxes.
This project is substantially complete.
-
February 9, 2024
Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link- Electrical underground complete, apart from pulling wire.
- ILB work complete.
- Fiber utility work is complete.
- Contractor importing pit run complete.
- Contractor importing 3/4.
- North leg of the project has a lot of rock excavation. Blasting is scheduled for next week.
- Grade prep for sidewalk started.
- Electrical underground complete, apart from pulling wire.
- ILB work complete.
- Fiber utility work is complete.
- Contractor importing pit run complete.
- Contractor importing 3/4.
- North leg of the project has a lot of rock excavation. Blasting is scheduled for next week.
- Grade prep for sidewalk started.
This project is substantially complete.
-
February 2, 2024
Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link- Electrical underground complete, apart from pulling wire.
- ILB back out to re-install feed.
- Fiber utility work is nearly complete.
- Back out to re-install conduit.
- Contractor importing pit run.
- North leg of the project has a lot of rock excavation.
- Electrical underground complete, apart from pulling wire.
- ILB back out to re-install feed.
- Fiber utility work is nearly complete.
- Back out to re-install conduit.
- Contractor importing pit run.
- North leg of the project has a lot of rock excavation.
This project is substantially complete.
-
January 26, 2024
Share January 26, 2024 on Facebook Share January 26, 2024 on Twitter Share January 26, 2024 on Linkedin Email January 26, 2024 link- Electrical underground complete, apart from pulling wire.
- Fiber utility work is nearly complete.
- Water line installation complete.
- Storm drain installation complete.
- Electrical underground complete, apart from pulling wire.
- Fiber utility work is nearly complete.
- Water line installation complete.
- Storm drain installation complete.
This project is substantially complete.
-
January 19, 2024
Share January 19, 2024 on Facebook Share January 19, 2024 on Twitter Share January 19, 2024 on Linkedin Email January 19, 2024 link- Electrical underground complete, apart from pulling wire.
- Fiber utility work is nearly complete.
- Water line installation complete.
- Storm drain installation complete.
- Minimal work due to weather.
- Electrical underground complete, apart from pulling wire.
- Fiber utility work is nearly complete.
- Water line installation complete.
- Storm drain installation complete.
- Minimal work due to weather.
This project is substantially complete.
-
January 12, 2024
Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link- Idaho Power work complete.
- Electrical underground work continues.
- Fiber utility work is ongoing.
- Water line installation continues.
- Storm drain installation complete.
- Idaho Power work complete.
- Electrical underground work continues.
- Fiber utility work is ongoing.
- Water line installation continues.
- Storm drain installation complete.
This project is substantially complete.
-
January 5, 2024
Share January 5, 2024 on Facebook Share January 5, 2024 on Twitter Share January 5, 2024 on Linkedin Email January 5, 2024 link- Idaho Power work complete.
- Electrical underground work continues.
- Fiber utility work is ongoing.
- Water line installation continues.
- Storm drain installation complete.
- Idaho Power work complete.
- Electrical underground work continues.
- Fiber utility work is ongoing.
- Water line installation continues.
- Storm drain installation complete.
This project is substantially complete.
-
December 22, 2023
Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link- Grade prep continues.
- Idaho Power work nearly complete. Waiting on ILB to finish – expected completion December 22nd.
- Electrical underground work continues.
- Fiber utility work ongoing.
- Water line install continues.
- Speed bump install around the project for TTC complete.
- Storm drain install has started.
- Grade prep continues.
- Idaho Power work nearly complete. Waiting on ILB to finish – expected completion December 22nd.
- Electrical underground work continues.
- Fiber utility work ongoing.
- Water line install continues.
- Speed bump install around the project for TTC complete.
- Storm drain install has started.
This project is substantially complete.
-
December 15, 2023
Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link- Grade prep continues.
- Idaho Power work nearly complete.
- Waiting on ILB to finish – expected completion December 22nd.
- Electrical underground work continues.
- Fiber utility work ongoing.
- Water line install continues.
- Speed bump install around the project for TTC complete.
- Grade prep continues.
- Idaho Power work nearly complete.
- Waiting on ILB to finish – expected completion December 22nd.
- Electrical underground work continues.
- Fiber utility work ongoing.
- Water line install continues.
- Speed bump install around the project for TTC complete.
This project is substantially complete.
-
December 8, 2023
Share December 8, 2023 on Facebook Share December 8, 2023 on Twitter Share December 8, 2023 on Linkedin Email December 8, 2023 link- Grade prep continues.
- Idaho Power work nearly complete. Waiting on ILB to finish.
- Electrical underground work started.
- Fiber utility work ongoing.
- Water line install has started.
- Speed bump install around the project for TTC complete.
- Grade prep continues.
- Idaho Power work nearly complete. Waiting on ILB to finish.
- Electrical underground work started.
- Fiber utility work ongoing.
- Water line install has started.
- Speed bump install around the project for TTC complete.
This project is substantially complete.
Who's Listening
-
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org
Drone Footage
-
April 10 2024
-
May 31 2024