Lake Hazel and Maple Grove Roundabout

Share Lake Hazel and Maple Grove Roundabout on Facebook Share Lake Hazel and Maple Grove Roundabout on Twitter Share Lake Hazel and Maple Grove Roundabout on Linkedin Email Lake Hazel and Maple Grove Roundabout link

This project is substantially complete. 

The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.

Project Description

  • Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
  • Add curb, gutter, and a detached 10-foot wide multi-use pathway
  • Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
  • Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
  • Add a truck apron for larger vehicles to use if necessary

The Ada County Highway District (ACHD) is designing a future roundabout for the Lake Hazel & Maple Grove intersection. The purpose of the project is to improve traffic flow and increase safety for all users.

Project Description

  • Construct a multi-lane roundabout at the Lake Hazel and Maple Grove intersection
  • Add curb, gutter, and a detached 10-foot wide multi-use pathway
  • Construct crosswalks at each leg of the intersection with two-stage pedestrian crossings
  • Install rectangular rapid flashing beacons (RRFBs) at each pedestrian crosswalk
  • Add a truck apron for larger vehicles to use if necessary

This project is substantially complete. 

  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Contractor importing and grading base materials.
    • North leg of the project has a lot of rock excavation.
    • Blasting complete.
    • Grade prep for sidewalks on going.
    • SW retaining wall install started.
    • Electrical contractor on site pulling wire and setting control cabinets/boxes.
  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • Electrical underground complete, apart from pulling wire.
    • ILB work complete.
    • Fiber utility work is complete.
    • Contractor importing pit run complete.
    • Contractor importing 3/4.
    • North leg of the project has a lot of rock excavation. Blasting is scheduled for next week.
    • Grade prep for sidewalk started.
  • February 2, 2024

    Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link
    • Electrical underground complete, apart from pulling wire.
    • ILB back out to re-install feed.
    • Fiber utility work is nearly complete.
    • Back out to re-install conduit.
    • Contractor importing pit run.
    • North leg of the project has a lot of rock excavation.
  • January 26, 2024

    Share January 26, 2024 on Facebook Share January 26, 2024 on Twitter Share January 26, 2024 on Linkedin Email January 26, 2024 link
    • Electrical underground complete, apart from pulling wire.
    • Fiber utility work is nearly complete.
    • Water line installation complete.
    • Storm drain installation complete.
  • January 19, 2024

    Share January 19, 2024 on Facebook Share January 19, 2024 on Twitter Share January 19, 2024 on Linkedin Email January 19, 2024 link
    • Electrical underground complete, apart from pulling wire.
    • Fiber utility work is nearly complete.
    • Water line installation complete.
    • Storm drain installation complete.
    • Minimal work due to weather.
  • January 12, 2024

    Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link
    • Idaho Power work complete.
    • Electrical underground work continues.
    • Fiber utility work is ongoing.
    • Water line installation continues.
    • Storm drain installation complete.
  • January 5, 2024

    Share January 5, 2024 on Facebook Share January 5, 2024 on Twitter Share January 5, 2024 on Linkedin Email January 5, 2024 link
    • Idaho Power work complete.
    • Electrical underground work continues.
    • Fiber utility work is ongoing.
    • Water line installation continues.
    • Storm drain installation complete.
  • December 22, 2023

    Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link
    • Grade prep continues.
    • Idaho Power work nearly complete. Waiting on ILB to finish – expected completion December 22nd.
    • Electrical underground work continues.
    • Fiber utility work ongoing.
    • Water line install continues.
    • Speed bump install around the project for TTC complete.
    • Storm drain install has started.
  • December 15, 2023

    Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link
    • Grade prep continues.
    • Idaho Power work nearly complete.
    • Waiting on ILB to finish – expected completion December 22nd.
    • Electrical underground work continues.
    • Fiber utility work ongoing.
    • Water line install continues.
    • Speed bump install around the project for TTC complete.
  • December 8, 2023

    Share December 8, 2023 on Facebook Share December 8, 2023 on Twitter Share December 8, 2023 on Linkedin Email December 8, 2023 link
    • Grade prep continues.
    • Idaho Power work nearly complete. Waiting on ILB to finish.
    • Electrical underground work started.
    • Fiber utility work ongoing.
    • Water line install has started.
    • Speed bump install around the project for TTC complete.