Randolph Drive Storm Drain Reroute Project

Share Randolph Drive Storm Drain Reroute Project on Facebook Share Randolph Drive Storm Drain Reroute Project on Twitter Share Randolph Drive Storm Drain Reroute Project on Linkedin Email Randolph Drive Storm Drain Reroute Project link

This project is substantially complete. 

The Ada County Highway District (ACHD) will begin construction on Randolph Drive, Holiday Drive, and McMullen Street in September of 2023. Construction is expected to be completed November of 2023.

This project will reroute storm drain and irrigation flow from the existing system, as it is failing and inaccessible. Improvements includes installation of pipe and related drainage structures within the roadway. Portions of deteriorated curb and gutter will be replaced with the project.

Construction Impacts:

  • For some driveways, there may be a need for a short duration closure while work is occurring directly in front of the driveway
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

The Ada County Highway District (ACHD) will begin construction on Randolph Drive, Holiday Drive, and McMullen Street in September of 2023. Construction is expected to be completed November of 2023.

This project will reroute storm drain and irrigation flow from the existing system, as it is failing and inaccessible. Improvements includes installation of pipe and related drainage structures within the roadway. Portions of deteriorated curb and gutter will be replaced with the project.

Construction Impacts:

  • For some driveways, there may be a need for a short duration closure while work is occurring directly in front of the driveway
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize construction impacts

This project is substantially complete. 

  • November 9 , 2023

    Share November 9 , 2023 on Facebook Share November 9 , 2023 on Twitter Share November 9 , 2023 on Linkedin Email November 9 , 2023 link
    • Phase 1 - McMullen to Holiday Drive - Complete.
    • Phase 2 - Holiday Drive - Prepped for paving.
    • Phase 3 - Holiday Drive and Randolph - Pipe install, and pressure test complete. Curb & Gutter installation complete. Tentatively planning to pave Saturday, November 11th - weather dependent.
    • Phase 1 - McMullen to Holiday Drive - Complete.
    • Phase 2 - Holiday Drive - Prepped for paving.
    • Phase 3 - Holiday Drive and Randolph - Pipe install, and pressure test complete. Curb & Gutter installation complete. Tentatively planning to pave Saturday, November 11th - weather dependent.

    This project is substantially complete. 

  • November 3, 2023

    Share November 3, 2023 on Facebook Share November 3, 2023 on Twitter Share November 3, 2023 on Linkedin Email November 3, 2023 link

    Phase 1 - McMullen to Holiday Drive - Complete.

    Phase 2 - Holiday Drive - work ongoing - C&G complete - pipe pressure test complete.

    Phase 3 - Holiday Drive and Randolph - Pipe install, and pressure test complete. Curb and gutter installation complete. Tentatively planning to pave the week of November 6th, weather dependent.

    Phase 1 - McMullen to Holiday Drive - Complete.

    Phase 2 - Holiday Drive - work ongoing - C&G complete - pipe pressure test complete.

    Phase 3 - Holiday Drive and Randolph - Pipe install, and pressure test complete. Curb and gutter installation complete. Tentatively planning to pave the week of November 6th, weather dependent.

    This project is substantially complete. 

  • October 27, 2023

    Share October 27, 2023 on Facebook Share October 27, 2023 on Twitter Share October 27, 2023 on Linkedin Email October 27, 2023 link
    • Phase 1 – McMullen to Holiday Dr - Complete
    • Phase 2 – Holiday Dr - work ongoing – C&G complete – pipe pressure test complete
    • Phase 3 – Holiday Dr and Randolph – Pipe install, and pressure test complete. Prep for concrete ongoing
    • Phase 1 – McMullen to Holiday Dr - Complete
    • Phase 2 – Holiday Dr - work ongoing – C&G complete – pipe pressure test complete
    • Phase 3 – Holiday Dr and Randolph – Pipe install, and pressure test complete. Prep for concrete ongoing

    This project is substantially complete. 

  • October 20, 2023

    Share October 20, 2023 on Facebook Share October 20, 2023 on Twitter Share October 20, 2023 on Linkedin Email October 20, 2023 link
    • Phase 1 - McMullen to Holiday Dr. - Storm drain install complete and road patched back.
    • Phase 2 - Holiday Dr. - work ongoing - C&G is scheduled for October 18th and 19th.
    • Phase 3 - Holiday Dr. and Randolph - Demo has started.
    • Phase 1 - McMullen to Holiday Dr. - Storm drain install complete and road patched back.
    • Phase 2 - Holiday Dr. - work ongoing - C&G is scheduled for October 18th and 19th.
    • Phase 3 - Holiday Dr. and Randolph - Demo has started.

    This project is substantially complete. 

  • October 12, 2023

    Share October 12, 2023 on Facebook Share October 12, 2023 on Twitter Share October 12, 2023 on Linkedin Email October 12, 2023 link
    • Project Phasing
      • Phase 1 - MucMullen to Holiday Drive - Storm drain install complete and road patched back.
      • Phase 2 - Holiday Drive - work ongoing.
      • Phase 3 - Holiday Drive and Randolph - Work will start October 16th.
    • Project Phasing
      • Phase 1 - MucMullen to Holiday Drive - Storm drain install complete and road patched back.
      • Phase 2 - Holiday Drive - work ongoing.
      • Phase 3 - Holiday Drive and Randolph - Work will start October 16th.

    This project is substantially complete. 

  • October 6, 2023

    Share October 6, 2023 on Facebook Share October 6, 2023 on Twitter Share October 6, 2023 on Linkedin Email October 6, 2023 link
    • Project Phasing:
    • Phase 1 - McMullen to Holiday Dr. - Demo and install continues.
    • Phase 2 - Holiday Dr. started October 2nd with demo.
    • Phase 3 - Holiday Dr. and Randolph
    • Project Phasing:
    • Phase 1 - McMullen to Holiday Dr. - Demo and install continues.
    • Phase 2 - Holiday Dr. started October 2nd with demo.
    • Phase 3 - Holiday Dr. and Randolph

    This project is substantially complete. 

  • September 22, 2023

    Share September 22, 2023 on Facebook Share September 22, 2023 on Twitter Share September 22, 2023 on Linkedin Email September 22, 2023 link
    • Project phasing
      • Phase 1: McMullen to Holiday Drive - Demo started.
      • Phase 2: Holiday Drive
      • Holiday Drive and Randolph
    • Project phasing
      • Phase 1: McMullen to Holiday Drive - Demo started.
      • Phase 2: Holiday Drive
      • Holiday Drive and Randolph

    This project is substantially complete. 

  • September 8, 2023

    Share September 8, 2023 on Facebook Share September 8, 2023 on Twitter Share September 8, 2023 on Linkedin Email September 8, 2023 link
    • Pre-Construction Meeting held on September 6th.
    • Notice-to-proceed is tentatively scheduled for the middle of September.
    • Pre-Construction Meeting held on September 6th.
    • Notice-to-proceed is tentatively scheduled for the middle of September.

    This project is substantially complete.