Randolph Drive Storm Drain Reroute Project
Share Randolph Drive Storm Drain Reroute Project on Facebook
Share Randolph Drive Storm Drain Reroute Project on Twitter
Share Randolph Drive Storm Drain Reroute Project on Linkedin
Email Randolph Drive Storm Drain Reroute Project link
This project is substantially complete.
The Ada County Highway District (ACHD) will begin construction on Randolph Drive, Holiday Drive, and McMullen Street in September of 2023. Construction is expected to be completed November of 2023.
This project will reroute storm drain and irrigation flow from the existing system, as it is failing and inaccessible. Improvements includes installation of pipe and related drainage structures within the roadway. Portions of deteriorated curb and gutter will be replaced with the project.
Construction Impacts:
- For some driveways, there may be a need for a short duration closure while work is occurring directly in front of the driveway
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 6 p.m. unless otherwise approved
- The contractor will work with homeowners to minimize construction impacts
This project is substantially complete.