Share November 9 , 2023 on Facebook
Share November 9 , 2023 on Linkedin
Email November 9 , 2023 link
- Phase 1 - McMullen to Holiday Drive - Complete.
- Phase 2 - Holiday Drive - Prepped for paving.
- Phase 3 - Holiday Drive and Randolph - Pipe install, and pressure test complete. Curb & Gutter installation complete. Tentatively planning to pave Saturday, November 11th - weather dependent.
Share November 3, 2023 on Facebook
Share November 3, 2023 on Linkedin
Email November 3, 2023 link
Phase 1 - McMullen to Holiday Drive - Complete.
Phase 2 - Holiday Drive - work ongoing - C&G complete - pipe pressure test complete.
Phase 3 - Holiday Drive and Randolph - Pipe install, and pressure test complete. Curb and gutter installation complete. Tentatively planning to pave the week of November 6th, weather dependent.
Share October 27, 2023 on Facebook
Share October 27, 2023 on Linkedin
Email October 27, 2023 link
- Phase 1 – McMullen to Holiday Dr - Complete
- Phase 2 – Holiday Dr - work ongoing – C&G complete – pipe pressure test complete
- Phase 3 – Holiday Dr and Randolph – Pipe install, and pressure test complete. Prep for concrete ongoing
Share October 20, 2023 on Facebook
Share October 20, 2023 on Linkedin
Email October 20, 2023 link
- Phase 1 - McMullen to Holiday Dr. - Storm drain install complete and road patched back.
- Phase 2 - Holiday Dr. - work ongoing - C&G is scheduled for October 18th and 19th.
- Phase 3 - Holiday Dr. and Randolph - Demo has started.
Share October 12, 2023 on Facebook
Share October 12, 2023 on Linkedin
Email October 12, 2023 link
- Project Phasing
- Phase 1 - MucMullen to Holiday Drive - Storm drain install complete and road patched back.
- Phase 2 - Holiday Drive - work ongoing.
- Phase 3 - Holiday Drive and Randolph - Work will start October 16th.
Share October 6, 2023 on Facebook
Share October 6, 2023 on Linkedin
Email October 6, 2023 link
- Project Phasing:
- Phase 1 - McMullen to Holiday Dr. - Demo and install continues.
- Phase 2 - Holiday Dr. started October 2nd with demo.
- Phase 3 - Holiday Dr. and Randolph
Share September 22, 2023 on Facebook
Share September 22, 2023 on Linkedin
Email September 22, 2023 link
- Project phasing
- Phase 1: McMullen to Holiday Drive - Demo started.
- Phase 2: Holiday Drive
- Holiday Drive and Randolph
Share September 8, 2023 on Facebook
Share September 8, 2023 on Linkedin
Email September 8, 2023 link
- Pre-Construction Meeting held on September 6th.
- Notice-to-proceed is tentatively scheduled for the middle of September.